Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
2 | X number of Slabs of Super Structure | Percentage of Work | 20 |
2 | Stilt Floor | Percentage of Work | 70 |
2 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 29 |
Ambika Harmony field under Building details/Main section updated with new value for Number of Closed Parking as 13.0
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Excavation | Percentage of Work | 100 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 67.5 |
1 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | Percentage of Work | 85 |
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 90 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 58.77 | Number of Booked Apartment | 6 |
1 | 2BHK | 59.48 | Number of Booked Apartment | 2 |
1 | 2BHK | 60.48 | Number of Booked Apartment | 5 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 90 |
1 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | Percentage of Work | 100 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 1 BHK FLAT | 42.7 | Number of Booked Apartment | 4 |
HARI OM PLAZA field under Building details/Main section updated with new value for Number of Closed Parking as 20.0
Electrical Meter Room, Sub-Station, Receiving Station : field under Development work/Amenities progress section updated with new value for Percent as 100.0
Project details/Amenities section updated for field(s) as below:
Name | Field updated | New value |
---|---|---|
Covered Parking ( In Numbers) | Booked | 20 |
Covered Parking ( In Numbers) | WorkDone(In %) | 100 |
Development work/Amenities progress section updated for field(s) as below:
Common areas And Facilities, Amenities | Field updated | New value |
---|---|---|
Water Conservation, Rain water Harvesting : | Percent | 100.0 |
Water Supply : | Details | BOREWELL |
Water Conservation, Rain water Harvesting : field under Development work/Amenities progress section updated with new value for Percent as 100.0
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 90 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 85 |
1 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | Percentage of Work | 30 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 41.5 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 72 |
1 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | Percentage of Work | 30 |
1 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | Percentage of Work | 80 |
1 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | Percentage of Work | 70 |
1 | Stilt Floor | Percentage of Work | 90 |
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 50 |
Project details section updated for field(s) as below:
Field updated | New value |
---|---|
Bank Name | AXIS BANK |
IFSC Code | UTIB0001882 |
GLOBAL VILLE field under Building details/Main section updated with new value for Number of Basement’s as 2.0
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
5 | Shop | 16.74 | Number of Booked Apartment | 1 |
1 | Shop | 14.15 | Number of Booked Apartment | 2 |
1 | 3BHK | 71.48 | Number of Booked Apartment | 48 |
3 | 2BHK | 50.65 | Number of Booked Apartment | 23 |
3 | 2BHK | 51.84 | Number of Booked Apartment | 53 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 55.84 | Number of Booked Apartment | 4 |
1 | Shop | 19.91 | Number of Booked Apartment | 1 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 35 |
1 | X number of Slabs of Super Structure | Percentage of Work | 50 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 47.4 |
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 87 |
Building details/Main section updated for field(s) as below:
Name (Also mention identification of building/wing/other as per approved plan) | Field updated | New value |
---|---|---|
TIRUPATI HILLS | Number of Sanctioned Floors | 7 |
TIRUPATI HILLS | Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) | 100 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 74.06 | Number of Apartment | 7 |
1 | 2BHK | 58.42 | Number of Apartment | 12 |
1 | Shop | 16 | Number of Booked Apartment | 1 |
1 | 2BHK | 65.26 | Number of Booked Apartment | 3 |
1 | 2BHK | 58.42 | Number of Booked Apartment | 7 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
2 | 3BHK | 105.11 | Number of Booked Apartment | 3 |
Project details/Amenities section updated for field(s) as below:
Name | Field updated | New value |
---|---|---|
Covered Parking ( In Numbers) | Booked | 7 |
Covered Parking ( In Numbers) | WorkDone(In %) | 35 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | Percentage of Work | 80 |
1 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | Percentage of Work | 20 |
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 50 |
1 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | Percentage of Work | 30 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 58 |