Project Name: Shree Chaitanya Apartment
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-06-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Sinnar, Nashik-422103

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S no 1065/1(1135)-5/1/3/5/B/1070/2 P no 20

Boundaries:
Adj S no 1069
Plot no 21N Plot No 19
WE
S
12 mtr wilde road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 410 sq.mt.
Sanctioned Built-up Area: 1091 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 791 to 826 sq ft 10 3
Commercial 757 sq ft 1 0
Shop 171 to 300 sq ft 3 0
Project Developer:
Bhumi Buildcon
Organization Type: Partnership

Address: Shop No 6, Udyog Bhavan, S No 923/6/6/7, Sinnar, Nashik-422103

Office Phone: +91 85549 94658


Member details:
Member Name Designation
Umesh Tukaram Ugale Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Ganesh Bhanudas Handore Architect
Nithesh Wankhede Chartered Accountant
Ganesh Bhanudas Handore Engineer


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Shree Chaitanya Apartment: A New Residential Development in Sinnar, Nashik

Shree Chaitanya Apartment, a newly launched real estate project in Sinnar, Nashik, is poised to offer a unique blend of modern living and comfortable spaces. Developed by Bhumi Buildcon, a trusted partnership firm, this project is registered under MahaRERA with ID P51600050365.

Located in a prime location within Sinnar, the project sits on a plot spanning 410 square meters, with clear boundaries defined by adjacent plots and a 12-meter wide road. This strategic location ensures convenient access to essential amenities and facilitates a peaceful and serene living environment.

Shree Chaitanya Apartment boasts a single, elegantly designed building that rises seven stories high, offering a diverse range of residential and commercial units. The project comprises 10 spacious 2BHK apartments, ranging from 791 to 826 square feet, catering to the needs of growing families. Additionally, the project includes 1 commercial unit spanning 757 square feet, ideal for business ventures, and 3 shop units ranging from 171 to 300 square feet, suitable for retail businesses.

The project is meticulously planned to maximize living comfort, with a focus on optimal utilization of space and modern amenities. Though it does not feature dedicated recreational spaces, the project’s strategic location and thoughtfully designed units allow residents to enjoy a peaceful and comfortable lifestyle.

Construction is currently underway and the project is scheduled for completion by June 30th, 2026. With its strategic location, diverse unit options, and commitment to quality construction, Shree Chaitanya Apartment presents an attractive investment opportunity for those seeking a comfortable and convenient lifestyle in the bustling town of Sinnar.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 76.8 5 2

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 2 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 89

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 73.57 5 1
2BHK 76.8 5 2
Commercial hall 70.41 1 0
Shop 15.93 1 0
Shop 27.94 1 0
Shop 27.95 1 0

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Disclosure of sold/ booked inventory
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
1 Overall Percentage of Completion of the work done For the entire Building /Wing 40

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Ganesh Bhanudas Handore Engineer

 

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 44

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 73.57 5 1
2BHK 76.8 5 1

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance