MH
Nashik
P51600028710
RERA ID: P51600028710
Project Name: Anika Residency
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-06-30
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Dnyaneshwar Nagar, Pathardi, Behind Atul Dairy, Nashik-422010

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Plot No. 17/18/19, S.No. 325/2B/1/2B/2, Pathardi

Boundaries:
Plot No 21-22-23
Plot No 20N Adj S No 330-1 to 7-2
WE
S
9 Meter Road

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 719 sq.mt.
Sanctioned Built-up Area: 1978 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 2
No. of Closed Parking: 24

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 588 to 604 sq ft 24 18
Project Developer:
Bhagwan Govindrao Gore and Bhaskar Govindrao Gore
Organization Type: Others (Association of Persons)

Address: Plot No. 260, Kaushalya Sadan, Ambad Link Road, Ambad, Near Saigram, Nashik-422010




Other Professionals involved:
Professional Name Professional Type
Siya Construction Contractor
Ashok Jamdar Architect
Dnyanesh Kurne Engineer
Nirav Shah Chartered Accountant
SNS RERA Consultants Other Professional
Siya Construction Contractor
Santosh Construction Contractor
Anand Construction Contractor
S P Electricals Contractor


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introduction

Welcome to the Anika Residency, an exciting new residential development poised to redefine urban living in the heart of Pathardi. This meticulously planned project, nestled amidst a vibrant neighborhood, embodies the essence of contemporary design and modern amenities.

This meticulously planned residential enclave, registered under the stringent regulations of MahaRERA (P51600028710), is meticulously designed to cater to the discerning tastes of homebuyers seeking an unparalleled living experience. The project’s unwavering commitment to quality and transparency ensures peace of mind for our esteemed clients.

Anika Residency boasts a prime location, strategically situated in the coveted Dnyaneshwar Nagar locality. Its proximity to essential amenities such as schools, hospitals, and shopping malls renders it an ideal destination for families and professionals alike.

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) [2]
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [2]
  • Architect’s Certificate on Completion of Project (Form 4)
  • Building Plan Approval / NA Order for plotted development [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Proforma of Allotment letter [2]
  • Status of Formation of Legal Entity (Society/Co Op etc.)