MH
Nashik
P51600045974
RERA ID: P51600045974
Project Name: SURYA HARMONY
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-03-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Pathardi Shiwar, S.No.290/1/2/3/4/5/P, Nashik-422013

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 8 TO 15, 26 TO 34 AND 37 TO 57

Boundaries:
SR NO 2 AND 3
SR NO 1 PROPRTY OF KHEMANIN SR NO 280 1B
WE
S
SR NO 1 PROPERTY OF KHEMANI

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 2916 sq.mt.
Sanctioned Built-up Area: 3220 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 38
No. of Floors sanctioned: 76
No. of Plinths: 38

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Bungalow 956 to 1023 sq ft 38 0
Project Developer:
PRADEEPKUMAR MADANLAL GUPTA c/o MADANLAL MISHRILAL GUPTA
Organization Type: Individual

Address: Sr No 681 Plot No 2 And 7, Khanha Bunglow, Off Ganagapur Road, Gurudatta Nagar, Off Gangapur Road, Nashik (M Corp.), Nashik-422013

Office Phone: +91 25325 72722


Other Professionals involved:
Professional Name Professional Type
Yogesh Tukaram Gaikwad Architect
Yogesh Thatte Engineer
CA LALIT ASHOK PAWAR Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Surya Harmony: A New Residential Development in Nashik

Surya Harmony, a new residential project registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under ID P51600045974, promises a tranquil and modern living experience in the picturesque locale of Pathardi Shiwar, Nashik. This project, scheduled for completion by March 31st, 2026, is a testament to the developer’s commitment to delivering high-quality, contemporary homes in a sought-after location.

Nestled within the serene surroundings of Nashik, Surya Harmony occupies a prime plot spanning 2916 sq. meters (approximately 31,400 sq. ft.). The project encompasses a total of 38 bungalows, each meticulously designed to offer a spacious and comfortable living experience, ranging in size from 956 to 1023 sq. ft. The project’s strategic location within Pathardi Shiwar provides residents with easy access to the city’s amenities and attractions while maintaining a peaceful and secluded atmosphere.

Surya Harmony is built upon a foundation of transparency and accountability, adhering to the guidelines set forth by MahaRERA. The project’s details, including its boundaries, plot area, sanctioned FSI, and amenities, are readily available on the MahaRERA website. The project is supported by RBL Bank, ensuring financial stability and security for investors.

Key Features of Surya Harmony:

  • Exclusive Bungalow Living: The project offers a limited number of spacious and well-designed bungalows, catering to those seeking a private and luxurious lifestyle.
  • Tranquil Location: Situated in Pathardi Shiwar, Surya Harmony provides residents with a peaceful and serene living environment away from the hustle and bustle of the city.
  • RERA Compliant: The project is registered with MahaRERA, ensuring transparency, accountability, and consumer protection.
  • Financial Security: The project is supported by RBL Bank, providing investors with confidence and assurance.

Surya Harmony represents a unique opportunity to own a piece of Nashik’s burgeoning real estate market. With its commitment to quality, transparency, and a serene location, this project promises a fulfilling and comfortable living experience. For those seeking a tranquil and modern home in a thriving location, Surya Harmony offers an ideal choice.

New documents listed below were uploaded to the Documents section:

  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Architect’s Certificate on Completion of Project (Form 4)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Bungalow 88.82 32 0
Bungalow 95.08 6 0

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 100 DONE
Electrical Meter Room, Sub-Station, Receiving Station : 100 DONE
Water Supply : 100 DONE
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 DONE
Storm Water Drains : 100 DONE
Landscaping & Tree Planting : 100 DONE
Internal Roads & Footpaths : 100 DONE
Water Conservation, Rain water Harvesting : 100 DONE

 

New documents listed below were uploaded to the Documents section:

  • 7 Disclosure of sold/ booked inventory
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)
  • 1 Status of Conveyance

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Excavation 100
2 X number of Basement(s) and Plinth 100
2 X number of Podiums 100
2 Stilt Floor 100
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 100
3 Excavation 100
3 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
3 Stilt Floor 100
3 X number of Slabs of Super Structure 100
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
3 Overall Percentage of Completion of the work done For the entire Building /Wing 100
4 Excavation 100
4 X number of Basement(s) and Plinth 100
4 X number of Podiums 100
4 Stilt Floor 100
4 X number of Slabs of Super Structure 100
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
4 Overall Percentage of Completion of the work done For the entire Building /Wing 100
5 Excavation 100
5 X number of Basement(s) and Plinth 100
5 X number of Podiums 100
5 Stilt Floor 100
5 X number of Slabs of Super Structure 100
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
5 Overall Percentage of Completion of the work done For the entire Building /Wing 100
6 Excavation 100
6 X number of Basement(s) and Plinth 100
6 X number of Podiums 100
6 Stilt Floor 100
6 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
6 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
6 Overall Percentage of Completion of the work done For the entire Building /Wing 100
7 Excavation 100
7 X number of Basement(s) and Plinth 100
7 X number of Podiums 100
7 Stilt Floor 100
7 X number of Slabs of Super Structure 100
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
7 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
7 Overall Percentage of Completion of the work done For the entire Building /Wing 100
8 Excavation 100
8 X number of Basement(s) and Plinth 100
8 X number of Podiums 100
8 Stilt Floor 100
8 X number of Slabs of Super Structure 100
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
8 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
8 Overall Percentage of Completion of the work done For the entire Building /Wing 100
9 Excavation 100
9 X number of Basement(s) and Plinth 100
9 X number of Podiums 100
9 Stilt Floor 100
9 X number of Slabs of Super Structure 100
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
9 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
9 Overall Percentage of Completion of the work done For the entire Building /Wing 100
10 Excavation 100
10 X number of Basement(s) and Plinth 100
10 X number of Podiums 100
10 Stilt Floor 100
10 X number of Slabs of Super Structure 100
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
10 Overall Percentage of Completion of the work done For the entire Building /Wing 100
11 Excavation 100
11 X number of Basement(s) and Plinth 100
11 X number of Podiums 100
11 Stilt Floor 100
11 X number of Slabs of Super Structure 100
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
11 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
12 Excavation 100
12 X number of Basement(s) and Plinth 100
12 X number of Podiums 100
12 Stilt Floor 100
12 X number of Slabs of Super Structure 100
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
12 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
12 Overall Percentage of Completion of the work done For the entire Building /Wing 100
13 Excavation 100
13 X number of Basement(s) and Plinth 100
13 X number of Podiums 100
13 Stilt Floor 100
13 X number of Slabs of Super Structure 100
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
13 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
13 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
13 Overall Percentage of Completion of the work done For the entire Building /Wing 100
14 Excavation 100
14 X number of Basement(s) and Plinth 100
14 X number of Podiums 100
14 Stilt Floor 100
14 X number of Slabs of Super Structure 100
14 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
14 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
14 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
14 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
14 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
14 Overall Percentage of Completion of the work done For the entire Building /Wing 100
15 Excavation 100
15 X number of Basement(s) and Plinth 100
15 X number of Podiums 100
15 Stilt Floor 100
15 X number of Slabs of Super Structure 100
15 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
15 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
15 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
15 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
15 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
15 Overall Percentage of Completion of the work done For the entire Building /Wing 100
16 Excavation 100
16 X number of Basement(s) and Plinth 100
16 X number of Podiums 100
16 Stilt Floor 100
16 X number of Slabs of Super Structure 100
16 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
16 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
16 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
16 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
16 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
16 Overall Percentage of Completion of the work done For the entire Building /Wing 100
17 Excavation 100
17 X number of Basement(s) and Plinth 100
17 X number of Podiums 100
17 Stilt Floor 100
17 X number of Slabs of Super Structure 100
17 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
17 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
17 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
17 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
17 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
17 Overall Percentage of Completion of the work done For the entire Building /Wing 100
18 Excavation 100
18 X number of Basement(s) and Plinth 100
18 X number of Podiums 100
18 Stilt Floor 100
18 X number of Slabs of Super Structure 100
18 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
18 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
18 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
18 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
18 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
18 Overall Percentage of Completion of the work done For the entire Building /Wing 100
19 Excavation 100
19 X number of Basement(s) and Plinth 100
19 X number of Podiums 100
19 Stilt Floor 100
19 X number of Slabs of Super Structure 100
19 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
19 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
19 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
19 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
19 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
19 Overall Percentage of Completion of the work done For the entire Building /Wing 100

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [6]
  • Building Plan Approval / NA Order for plotted development [2]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [6]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [6]
  • Proforma of Allotment letter [2]