Project Name: SHREE KRUSHNA SAMARPAN
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-09-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2023-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Adgaon, Shriram Nagar, Jatra Hotel, Nashik-422003

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
GAT N0. 504/2,Plot No. 12, Shriram Nagar, Jatra Hotel, Adgaon - 422003

Boundaries:
0
0N 12 Meters Colony Road
WE
S
0

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 464 sq.mt.
Sanctioned Built-up Area: 1500 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 6
No. of Plinths: 1
No. of Open Parking: 19
No. of Closed Parking: 21

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 326 sq ft 12 6
2BHK 524 to 537 sq ft 12 8
Project Developer:
WARKHEDE PROPERTIES
Organization Type: Partnership

Address: 11, Iti Housing Society, Indira Nagar, Nashik-422009

Office Phone: +91 99229 918656


Member details:
Member Name Designation
Shubham Suresh Warkhede Authorized Signatory
PANKAJ SURESH WARKHEDE Partner


Other Professionals involved:
Professional Name Professional Type
Tejashree S. Vadaje Architect
Tejashree S. Vadaje Engineer
CA TUSHAR S LOKHANDE MS BHALGAT BOTHARA AND ASSOCIATES Chartered Accountant
CA NINAD METKAR AND ASSOCIATES Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing “Shree Krushna Samarpana”: A New Residential Project in Nashik

“Shree Krushna Samarpana,” a new residential project in Nashik, Maharashtra, offers a unique opportunity for discerning homebuyers seeking comfortable and modern living spaces. Developed by Warkhede Properties, a well-established partnership firm, this project is registered under MahaRERA with ID P51600047133, ensuring transparency and accountability.

Located in Adgaon, Nashik, the project boasts an ideal address in the heart of the city, offering easy access to essential amenities and key infrastructure. Situated on Plot No. 12, Shriram Nagar, Jatra Hotel, the project occupies a plot area of 464 sq. mts. and comprises a single building with six sanctioned floors. The project benefits from convenient connectivity, being located near a 12-meter colony road, with proximity to various essential amenities like banks, schools, and hospitals.

“Shree Krushna Samarpana” is designed to cater to diverse housing needs, offering a total of 19 open parking spaces and 21 closed parking spaces for the convenience of residents. The project is designed with a sanctioned FSI of 1500, ensuring ample space for comfortable living. With a proposed completion date of December 31st, 2023, “Shree Krushna Samarpana” promises a timely delivery of quality homes.

The project is financed through Axis Bank, with the IFSC code UTIB0003370, providing assurance of financial stability and transparency.

“Shree Krushna Samarpana” by Warkhede Properties promises a fulfilling and comfortable lifestyle, meticulously planned to offer residents a harmonious and enriching living experience.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 30.3 12 6

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-09-30

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 30.3 12 6
2BHK 48.7 6 3
2BHK 49.9 6 5

 

New documents listed below were uploaded to the Documents section:

  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 33 14 50

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

New documents listed below were uploaded to the Documents section:

  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 75 Septic Tank Proposed

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 33 10 30

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 30.3 12 2
2BHK 49.9 6 5

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
1 Overall Percentage of Completion of the work done For the entire Building /Wing 77

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [5]
  • Other – Legal
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal