Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Nashik Road, Jai Bhavani Road, Near Suman Hospital, Nashik-422101

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S. No./G. No. 87/1/2/11/3 of Deolali Shiwar, Nashik - 422101

Boundaries:
Survey No 87 - 1 - 2 - 11 - 1
Survey No 87 oblique 1A oblique 9N 18 Meter Wide D P Road
WE
S
12 Meter Wide Road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3000 sq.mt.
Sanctioned Built-up Area: 5523 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 8
No. of Plinths: 2
No. of Open Parking: 88
No. of Closed Parking: 37

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 605 to 675 sq ft 36 0
3BHK 752 to 849 sq ft 20 0
Shop 178 to 416 sq ft 22 2
Project Developer:
A C JAIN BUILDERS AND DEVELOPERS LLP
Organization Type: Partnership

Address: Vitraag Bunglow,, Gopal Nagar, Artillery Center Road,, Nasikroad, Nasik, , Nashik-422101

Office Phone: +91 25324 51202
Website URL: www.acjain.com


Member details:
Member Name Designation
RUSHABH ABHAY TODARWAL JAIN Authorized Signatory
VIDHYA ABHAY JAIN TODARWAL Partner
ABHAY CHANDMAL JAIN Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
A V Enterprises Contractor
Altaf Khan Contractor
Mahajan Contractor
Kashinath Dhage Contractor
Kishor Contractor
Satyanarayan Sharma Contractor
Raju Ghodeswar Architect
Sanjay Shriram Patil Engineer
Milind Rathi Engineer
CA Paresh Sabadra. Chartered Accountant


Projects in the state by this developer:
P51600077025 - BEL AIR - Nashik
P51600052680 - Abhinav - Nashik
P51600051353 - AARADHYA RESIDENCY PHASE II - Nashik
P51600031439 - ARADHANA ENCLAVE - Nashik
P51600025468 - AARADHANA VILLAS - Nashik
P51600025195 - AARADHANA RESIDENCY - A - Nashik
P51600025163 - AARADHANA RESIDENCY - B - Nashik
P51600022627 - ARRPAN HOUSING - Nashik
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Abhinav: A Premier Real Estate Development in the Heart of Nashik

Abhinav, a meticulously planned real estate project by A C JAIN BUILDERS AND DEVELOPERS LLP, is set to redefine the urban landscape of Nashik. Nestled in the burgeoning locality of Jai Bhavani Road, this new-build development offers a perfect blend of contemporary living and modern amenities.

Project Overview

With a total plot area of 3000 square meters, Abhinav boasts a spacious layout featuring two stunning buildings and a total of 56 residential units. The project has been meticulously designed to provide residents with ample natural light, cross-ventilation, and breathtaking views. The project is slated for completion by December 2026, ensuring timely delivery of your dream abode.

Exemplary Location

Abhinav enjoys an enviable location in the heart of Nashik Road, offering unparalleled connectivity and convenience. The project is in close proximity to major landmarks, including Suman Hospital, schools, banks, and shopping centers. The 18-meter-wide D P Road on the east side of the project provides seamless access to the city’s vital infrastructure.

Wide Range of Units

Abhinav offers a diverse range of unit types to cater to the varied needs of homebuyers. The project features 36 well-appointed 2BHK units ranging from 605 to 675 square feet, 20 spacious 3BHK units ranging from 752 to 849 square feet, and 22 convenient shop units ranging from 178 to 416 square feet. Each unit has been meticulously designed to maximize space utilization and create a comfortable living environment.

Uncompromised Amenities

Abhinav offers an array of state-of-the-art amenities to enhance the residents’ lifestyle. The project boasts a total no. of 125 open and closed parking spaces, ensuring ample parking for residents and visitors. The eight-story structure houses two plinths and eight sanctioned floors, providing ample space for a variety of amenities, including a recreational open space and other modern conveniences.

Firm Reputation

A C JAIN BUILDERS AND DEVELOPERS LLP, the developer behind Abhinav, is renowned for its unwavering commitment to quality, innovation, and customer satisfaction. The firm has a proven track record of delivering exceptional real estate projects across Nashik and surrounding areas. With its deep understanding of the local real estate market and its dedication to customer service, A C JAIN BUILDERS AND DEVELOPERS LLP is the ideal partner for your dream home.

Conclusion

Abhinav is an exceptional real estate project that seamlessly blends modern architectural design with a prime location and an array of amenities. Its diverse range of unit types, coupled with its commitment to quality construction and customer satisfaction, makes Abhinav the perfect choice for discerning homebuyers seeking a premium living experience in the vibrant city of Nashik.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Shop 28 1 0
Shop 38.74 2 1

 

New documents listed below were uploaded to the Documents section:

  • 4 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
1 Overall Percentage of Completion of the work done For the entire Building /Wing 83
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 48

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Stilt Floor 70
2 X number of Slabs of Super Structure 20
2 Overall Percentage of Completion of the work done For the entire Building /Wing 29

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 56.29 4 0
2BHK 59.41 8 0
2BHK 59.94 4 0
2BHK 60.38 4 0
2BHK 60.83 8 0
2BHK 62.73 8 0
3BHK 69.95 4 0
3BHK 74.72 4 0
3BHK 78.43 8 0
3BHK 78.94 4 0
Shop 16.54 1 0
Shop 20.16 1 0
Shop 21.06 1 0
Shop 22.13 1 0
Shop 22.54 1 0
Shop 23.4 1 0
Shop 23.79 1 0
Shop 24.03 1 0
Shop 24.4 1 0
Shop 24.59 1 0
Shop 24.6 1 0
Shop 24.61 1 0
Shop 24.95 1 0
Shop 25.01 1 0
Shop 26.23 1 0
Shop 26.24 1 0
Shop 27.46 1 1
Shop 27.94 1 0
Shop 28 1 0
Shop 30.52 1 0
Shop 38.74 2 1

 

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 1 Disclosure of sold/ booked inventory
  • 2 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Shop 27.46 1 1

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 100
1 X number of Slabs of Super Structure 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5
2 Excavation 100
2 X number of Basement(s) and Plinth 100
2 Stilt Floor 100
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 63

 

New documents listed below were uploaded to the Documents section:

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Building Plan Approval / NA Order for plotted development [3]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]