RERA ID: P51600022772
Project Name: RIVIERA TOWER
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-08-01
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Anadwali Nashik, Near Navshya Ganpati Temple, Aanandwali, Nashik-422013

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
65/1/1A

Boundaries:
GODAPARK
SURVEY NO 65 PartN SURVEY NO 66
WE
S
24M WIDE ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 3114 sq.mt.
Sanctioned Built-up Area: 5786 sq.mt.
Recreational Open Space: 311 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 16
No. of Plinths: 2
No. of Stilts: 2
No. of Open Parking: 31
No. of Closed Parking: 39

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 47694 sq ft 40 18
3BHK 1291 sq ft 7 0
Project Developer:
SHINDE AND SHINDE
Organization Type: Partnership

Address: Flat No 1, Sonika Housing Society, Sharanpur Road, New Pandit Colony, Rajiv Gandhi Bhavan, Nashik-422002

Office Phone: +91 25323 15512


Member details:
Member Name Designation
SHASHIKANT RAOJI SHINDE Authorized Signatory
SHASHIKANT RAOJI SHINDE Partner
RAVINDRA RAOJI SHINDE Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
SHINDE AND SHINDE Partnership Area Share
ASHOK FAKIRRAO SOPE Individual Area Share
ASHA SURJUSE Individual Area Share
BHARGAV SOPE Individual Area Share
UJWALLA SOPE Individual Area Share
PALLAVI SOPE Individual Area Share


Other Professionals involved:
Professional Name Professional Type
SANJAY RAMESH NAIK Architect
SAGAR SHINDE Engineer
SANTOSH NAMDEV KASAR Chartered Accountant
JOGINDAR PANDIT Contractor
RANJIT NAIK Contractor


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Riviera Tower: A New Residential Development in Nashik

Nestled in the tranquil locale of Aanandwali, Nashik, Riviera Tower is a new residential project promising a luxurious and comfortable lifestyle. Developed by Shinde and Shinde, a renowned partnership firm, this project is registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under the ID P51600022772.

Riviera Tower occupies a generous plot area of 3114 sq. meters, encompassing two beautifully designed buildings. With a sanctioned FSI of 5786, the project offers a total built-up area of 5786 sq. meters. Construction is underway and the project is expected to be completed by August 1st, 2025.

The project boasts a prime location in Aanandwali, Nashik, close to amenities like Navshya Ganpati Temple. Situated near a 24-meter wide road, the project enjoys excellent connectivity to other parts of the city.

A Blend of Modern Living and Comfort

Riviera Tower provides a choice of spacious 2BHK and 3BHK apartments, designed with meticulous attention to detail and contemporary aesthetics. The project offers a total of 47 units, including 40 2BHK apartments ranging from 476.94 sq. ft. and 7 3BHK apartments spanning 1291 sq. ft.

The project caters to the diverse needs of modern residents with a comprehensive range of amenities. These include:

  • Generous Parking: With 31 open parking spaces and 39 closed parking spaces, residents are assured of ample parking space for their vehicles.
  • Recreational Open Space: The project dedicates 311 sq. meters to recreational open space, providing residents with a tranquil escape from the hustle and bustle of city life.
  • Well-planned Structure: The project features two stilts, two plinth levels, and 16 sanctioned floors, ensuring a well-ventilated and spacious living experience.

A Promising Investment Opportunity

Riviera Tower presents an ideal investment opportunity for individuals seeking a comfortable and modern living space in Nashik. With its prime location, exceptional amenities, and the proven track record of Shinde and Shinde, the project is poised to provide long-term value and appreciation.

For further details and inquiries, please contact:

Shinde and Shinde FLAT NO 1 SONIKA HOUSING SOCIETY SHARANPUR ROAD NEW PANDIT COLONY Nashik, Maharashtra 422002 Phone: +91 2532315512

Website: [Add website link if available]

Note: This essay can be further tailored to include specific details about the project’s target audience, pricing information, or additional amenities.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 4431 40 18
3BHK 119.94 7 0

 

New documents listed below were uploaded to the Documents section:

  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
1 Overall Percentage of Completion of the work done For the entire Building /Wing 83.5
2 X number of Slabs of Super Structure 80
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
2 Overall Percentage of Completion of the work done For the entire Building /Wing 42

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Street Lighting : 30
Internal Roads & Footpaths : 70

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 95
1 Overall Percentage of Completion of the work done For the entire Building /Wing 81.5
2 X number of Slabs of Super Structure 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 38

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 50
Water Supply : 60 NMC WATER CONNECTION SHALL BE PROVIDED

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 4431 40 18

 

New documents listed below were uploaded to the Documents section:

  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 4431 40 17

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 90 SEPTIC TANK WILL BE PROVIDED
Water Supply : 50 NMC WATER CONNECTION SHALL BE PROVIDED
Electrical Meter Room, Sub-Station, Receiving Station : 50 ELECTRIC METER ROOM WILL BE PROVIDED

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
1 Overall Percentage of Completion of the work done For the entire Building /Wing 78.5
2 Excavation 100
2 X number of Basement(s) and Plinth 100
2 Stilt Floor 100
2 X number of Slabs of Super Structure 30
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
2 Overall Percentage of Completion of the work done For the entire Building /Wing 36

 

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [2]
  • Building Plan Approval / NA Order for plotted development [3]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B [6]
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [2]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Proforma of Allotment letter [2]