RERA ID: P52900024380
Project Name: AXIS BLUES
Project Type: Commercial
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-10-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2024-10-30).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Yog City, Yog City Main Road, Maneri, Dodamarg, Sindhudurg-416512

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
285,430,431,440,441,443,444,445

Boundaries:
PLOT NO 543
PLOT NO 432 439 AND 446N 15 MTR ROAD
WE
S
15 MTR ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3995 sq.mt.
Sanctioned Built-up Area: 5009 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 4
No. of Floors sanctioned: 16
No. of Plinths: 4
No. of Stilts: 1
No. of Open Parking: 12
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Others 340 sq ft 120 109
Shop 134 to 391 sq ft 7 0
Studio 232 to 248 sq ft 45 30
Project Developer:
EEJAK HOLDINGS PRIVATE LIMITED
Organization Type: Company

Address: Plot No. 434, Axis Blues, Yog City Main Road, Yog City,, Yog Resort, Maneri, Dodamarg, Sindhudurg-416512

Office Phone: +91 23632 05300


Member details:
Member Name Designation
Devesh Kumar Authorized Signatory
Ashish Kushwaha Director
Padmaja Kushwaha Director
Devesh Kumar Director


Other Professionals involved:
Professional Name Professional Type
SPACE DESIGN GROUP Architect
SPACE DESIGN GROUP Engineer
SATYA PRAKASH KUSHWAHA Chartered Accountant
ASHOK JAYESH & ASSOCIATES Other Professional
PALLAVI MOHAN Other Professional
K VENKATANARAYANA REDDY Other Professional
MS DEEPAK ASSOCIATES Other Professional


Projects in the state by this developer:
P52900024380 - AXIS BLUES - Sindhudurg
P52900021725 - AXIS BLUES - Sindhudurg
P52900019883 - AXIS BLUES - Sindhudurg
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

AXIS BLUES: A New Commercial Project in the Heart of Yog City

AXIS BLUES, a new commercial project with RERA ID P52900024380, is set to redefine the landscape of Yog City, Sindhudurg, Maharashtra. Developed by EEJAK HOLDINGS PRIVATE LIMITED, this project boasts a prime location on Yog City Main Road, close to the renowned Yog Resort.

A Strategic Location:

AXIS BLUES is strategically located on Plot Nos. 285, 430, 431, 440, 441, 443, 444, and 445 in Maneri village, Dodamarg Taluka. With its proximity to the 15 MTR Road and neighboring plots, AXIS BLUES enjoys excellent connectivity and visibility.

A Visionary Design:

The project comprises four buildings with a total plot area of 3995 sq. meters. With a sanctioned FSI of 5009, the project offers a substantial built-up area. The design incorporates 16 floors, including a stilt floor, providing ample space for commercial ventures.

Focus on Convenience and Comfort:

AXIS BLUES prioritizes comfort and convenience with 12 open parking spaces for both 4-wheelers and 2-wheelers, and one closed parking space. These features aim to cater to the needs of potential occupants and visitors.

A Project Ready for Growth:

As a new project with a proposed completion date of October 30, 2024, AXIS BLUES presents a unique investment opportunity. With no existing litigations and a strong financial foundation, backed by ICICI Bank (IFSC code: ICIC0001580), this project offers a secure and promising platform for commercial success.

A Gateway to Opportunity:

AXIS BLUES is more than just a real estate development; it represents a gateway to new possibilities in Yog City. Its strategic location, modern design, and focus on convenience make it an attractive proposition for businesses seeking a vibrant and growing location to establish their presence.

Investment in a Thriving Future:

Investors seeking a lucrative opportunity in a dynamic location will find AXIS BLUES to be an ideal choice. The project’s commitment to quality construction and its potential to attract a diverse range of businesses makes it a promising investment for the future.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
SERVICE STUDIOS 21.58 30 21
SERVICE STUDIOS 23.09 15 9
SERVICE SUITES 31.65 120 109
Shop 12.52 1 0
Shop 13.5 1 0
Shop 17.09 1 0
Shop 36.4 4 0

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2025-10-30

 

New documents listed below were uploaded to the Documents section:

  • 4 Disclosure of sold/ booked inventory
  • 3 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration in FORM B
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 b Details of encumbrances concerned to Legal
  • 2 Disclosure of sold/ booked inventory
  • 2 a Details of encumbrances concerned to Finance
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 59
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
2 Overall Percentage of Completion of the work done For the entire Building /Wing 49
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
3 Overall Percentage of Completion of the work done For the entire Building /Wing 45
4 X number of Slabs of Super Structure 70
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 15
4 Overall Percentage of Completion of the work done For the entire Building /Wing 31.5

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Proforma of Allotment letter
  • Status of Conveyance