Project Type: Commercial
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-05-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2024-05-30).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Yog City, Yog City Main Road, Maneri, Dodamarg, Sindhudurg-416512

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
434, 435, 436, 437, 448, 449

Boundaries:
Plot No 543
Plot No 543N Plot No 433
WE
S
15 Mtr Road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3000 sq.mt.
Sanctioned Built-up Area: 5366 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 12
No. of Plinths: 3
No. of Stilts: 1
No. of Open Parking: 12

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Others 340 sq ft 88 57
Shop 134 to 391 sq ft 7 0
Studio 232 to 248 sq ft 33 13
Project Developer:
EEJAK HOLDINGS PRIVATE LIMITED
Organization Type: Company

Address: Plot No. 434, Axis Blues, Yog City Main Road, Yog City,, Yog Resort, Maneri, Dodamarg, Sindhudurg-416512

Office Phone: +91 23632 05300


Member details:
Member Name Designation
Devesh Kumar Authorized Signatory
Ashish Kushwaha Director
Padmaja Kushwaha Director
Devesh Kumar Director


Other Professionals involved:
Professional Name Professional Type
Space design Group Architect
Space design Group Engineer
Satya Prakash Kushwaha Chartered Accountant
Ashok Jayesh and Associates Chartered Accountant
Landscape Architect Pallavi Mohan Other Professional
Vaastu consultant K Venkatanarayana Reddy Other Professional


Projects in the state by this developer:
P52900024380 - AXIS BLUES - Sindhudurg
P52900021725 - AXIS BLUES - Sindhudurg
P52900019883 - AXIS BLUES - Sindhudurg
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

AXIS BLUES: A New Commercial Project in the Heart of Yog City

Introducing AXIS BLUES, a brand new commercial project situated in the vibrant location of Yog City, Maneri, Sindhudurg. Developed by EEJAK HOLDINGS PRIVATE LIMITED, this project is set to redefine the commercial landscape of the region.

AXIS BLUES is a meticulously planned development spread across a sprawling 3000 square meters of prime land, encompassing three buildings with a total of 12 floors each. The project boasts a strategic location, nestled on Yog City Main Road with proximity to Yog Resort, ensuring high visibility and accessibility. The project’s completion is slated for May 30th, 2024, making it an attractive investment opportunity for businesses seeking a modern and well-connected space.

Strategic Location & Amenities

The project’s location in Yog City, a bustling locality, ensures significant footfall and proximity to various amenities. The open parking space with a capacity for 12 vehicles caters to the convenience of both employees and visitors.

Project Details & Compliance

AXIS BLUES adheres to all relevant regulations, as evidenced by its RERA registration number P52900019883. With a sanctioned FSI of 5366, the project offers ample built-up area for diverse commercial ventures. Notably, AXIS BLUES is free from any ongoing litigation, further solidifying its credibility and investor confidence.

Investment Opportunity

AXIS BLUES presents a compelling investment opportunity for businesses seeking a modern and well-equipped commercial space in a prime location. The project’s strategic location, comprehensive amenities, and adherence to all regulatory requirements make it an attractive prospect for those looking to establish a successful venture in the vibrant Konkan region.

Contact Details

For more information about AXIS BLUES, interested parties can contact EEJAK HOLDINGS PRIVATE LIMITED at 2363205300. This project promises to be a valuable addition to the commercial landscape of Yog City, offering both investors and businesses a unique and rewarding opportunity.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
SERVICE STUDIO 21.58 16 10
SERVICE STUDIO 23.09 11 0
SERVICE STUDIOS 21.58 6 3
SERVICE SUITES 31.65 24 12
SERVICE SUITS 31.65 64 45
SHOP 12.52 1 0
SHOP 13.5 1 0
SHOP 17.09 1 0
SHOPS 36.4 4 0

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2025-05-30

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration in FORM B
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
SERVICE SUITES 31.65 24 12

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Disclosure of sold/ booked inventory
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 b Details of encumbrances concerned to Legal
  • 2 a Details of encumbrances concerned to Finance

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 55
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
1 Overall Percentage of Completion of the work done For the entire Building /Wing 58.5
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 85
2 Overall Percentage of Completion of the work done For the entire Building /Wing 61.5
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 85
3 Overall Percentage of Completion of the work done For the entire Building /Wing 62.5

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval (IOD)
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Proforma of Allotment letter [2]
  • Status of Conveyance