2025-07-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2024-07-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Yog Resort, 416512, Maneri, Dodamarg, Sindhudurg-416512

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
432, 433,438,439, 446, 447

Boundaries:
GREEN AREA
PLOT NO437N PLOT NO 440
WE
S
15 MTR ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3000 sq.mt.
Sanctioned Built-up Area: 5366 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 12
No. of Plinths: 3
No. of Stilts: 1
No. of Open Parking: 12
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Others 340 sq ft 64 47
Shop 134 to 391 sq ft 7 0
Studio 232 to 340 sq ft 57 42
Project Developer:
EEJAK HOLDINGS PRIVATE LIMITED
Organization Type: Company

Address: Plot No. 434, Axis Blues, Yog City Main Road, Yog City,, Yog Resort, Maneri, Dodamarg, Sindhudurg-416512

Office Phone: +91 23632 05300


Member details:
Member Name Designation
Devesh Kumar Authorized Signatory
Ashish Kushwaha Director
Padmaja Kushwaha Director
Devesh Kumar Director


Other Professionals involved:
Professional Name Professional Type
Space design Group Architect
Space design Group Engineer
Satya Prakash Kushwaha Chartered Accountant
Ashok Jayesh and Associates Chartered Accountant
Pallavi Mohan Other Professional
K Venkatanarayana Reddy Other Professional


Projects in the state by this developer:
P52900024380 - AXIS BLUES - Sindhudurg
P52900021725 - AXIS BLUES - Sindhudurg
P52900019883 - AXIS BLUES - Sindhudurg
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Axis Blues: A New Commercial Project in the Heart of Yog City

Introducing Axis Blues, a brand-new commercial project developed by EEJAK HOLDINGS PRIVATE LIMITED, poised to revolutionize the commercial landscape of Yog City, Sindhudurg. This RERA-registered project (P52900021725) promises a unique blend of modern design and prime location, catering to the growing demands of the commercial sector.

Located strategically at the heart of Yog City, Axis Blues enjoys a prominent position on Plot Nos. 432, 433, 438, 439, 446, and 447. The project boasts a total plot area of 3000 square meters and boasts a sanctioned FSI of 5366. The project will encompass three buildings, each rising to a maximum of 12 floors, including a stilt level. The construction of these modern structures is well underway, with a projected completion date of July 31st, 2024.

Axis Blues is designed to provide a premium commercial experience. The project offers a range of amenities, including 12 open parking spaces and one closed parking space. The project’s strategic location within Yog City ensures easy access to major thoroughfares, providing unparalleled connectivity and exposure to a bustling commercial hub.

Investing in Axis Blues offers an opportunity to secure a prime location within a thriving commercial hub. The project’s strategic location, modern design, and comprehensive amenities are sure to attract a diverse range of tenants, ensuring a strong return on investment.

This introduction is just the beginning of the Axis Blues story. For those looking to invest in a promising commercial project in a vibrant location, Axis Blues represents a remarkable opportunity to build success.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
SERVICE STUDIOS 21.58 22 18
SERVICE STUDIOS 23.09 11 0
SERVICE STUDIOS 31.65 24 24
SERVICE SUITES 31.65 64 47
SHOP 12.52 1 0
SHOP 13.5 1 0
SHOP 17.09 1 0
SHOPS 36.4 4 0

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2025-07-30

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
SERVICE STUDIOS 31.65 24 24

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 b Details of encumbrances concerned to Legal
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 2 Disclosure of sold/ booked inventory
  • 2 a Details of encumbrances concerned to Finance

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
1 Overall Percentage of Completion of the work done For the entire Building /Wing 60
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 47
2 Overall Percentage of Completion of the work done For the entire Building /Wing 52.7
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
3 Overall Percentage of Completion of the work done For the entire Building /Wing 52

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [5]
  • Building Plan Approval (IOD)
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Proforma of Allotment letter [2]
  • Status of Conveyance