P51900049483
RERA ID: P51900049483
Project Name: Amara
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Mumbai, Gnorth-400028, Ward Gnorth, Mumbai City-400028

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
696, 696/1

Boundaries:
Ranade Road
H M Patil MargN Sushrusha Hospital
WE
S
Ganesh Building

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1479 sq.mt.
Sanctioned Built-up Area: 6016 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 16
No. of Plinths: 1
No. of Podiums: 6
No. of Stilts: 1
No. of Open Parking: 77
No. of Closed Parking: 112

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 698 to 765 sq ft 3 3
3BHK 1032 to 1739 sq ft 49 31
Project Developer:
Sharcon Mutha
Organization Type: Others (Association of Persons)

Address: Cts No 669 And Cts No 696 (1), 0, H. M. Patil Marg, Shivaji Park, Dadar (West), Mumbai City-400028

Office Phone: +91 98200 08006


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Sharcon Infrastructure Private Limited Company Area Share
Neela Ramkrishna Patil Individual Area Share
Sandeep Madhusudan Patil - HUF Others Area Share


Other Professionals involved:
Professional Name Professional Type
Ashish Bhatt Architect
Asif Choudhari Engineer
CA Paresh Sabadra Chartered Accountant
Ajay Mahale & Associates Other Professional
Digamber Asscociates LLP Contractor


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Amara: A New Residential Project in the Heart of Mumbai

Amara, a new residential project by Sharcon Mutha, an Association of Persons, is set to redefine luxury living in the heart of Mumbai. Located in Shivaji Park, Dadar (west), this 16-storey building offers a unique blend of modern architecture and prime location, catering to discerning individuals seeking a prestigious lifestyle.

The project, registered with MahaRERA under ID P51900049483, boasts a prime location nestled between Sushrusha Hospital to the east, H M Patil Marg to the west, Ranade Road to the north, and Ganesh Building to the south. Situated on a plot of 1479 sq. mtrs. with a total permissible built-up area of 6016 sq. mtrs., Amara offers a limited number of meticulously designed 2BHK and 3BHK apartments, ranging from 698 to 1739 sq ft.

The project prioritizes comfort and convenience with its carefully planned amenities. These include 77 open parking spaces for 4-wheelers and 2-wheelers, along with 112 closed parking spaces. The building features a single plinth level, six podium levels, one stilt level, and 16 sanctioned floors, promising a harmonious living experience.

Amara distinguishes itself by its focus on quality and sustainability. The project is designed to meet the highest standards of construction and adheres to all applicable regulations. The developer, Sharcon Mutha, is committed to transparency and timely completion, with the estimated date of completion set for December 31st, 2026.

For those seeking a luxurious and convenient lifestyle in a prime location, Amara offers an unparalleled opportunity. The project’s limited units and meticulous planning ensure a unique living experience, where residents can enjoy the vibrant energy of Shivaji Park while retreating to the serenity of their spacious and well-appointed apartments. With its strategic location, modern amenities, and dedicated developer, Amara is poised to become a landmark destination for discerning homebuyers.

New documents listed below were uploaded to the Documents section:

  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 64.88 1 1

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 64.88 1 1

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 64.88 1 0
2BHK 71.08 2 2
3BHK 95.94 1 1
3BHK 96.12 1 1
3BHK 98.53 2 2
3BHK 98.91 2 2
3BHK 100.74 2 2
3BHK 102.43 1 1
3BHK 103.06 1 1
3BHK 103.27 1 1
3BHK 105.54 1 1
3BHK 105.64 1 1
3BHK 107.7 1 0
3BHK 108.19 1 1
3BHK 109.45 5 2
3BHK 110.29 2 1
3BHK 110.84 6 2
3BHK 111.26 1 1
3BHK 112.85 1 1
3BHK 113.28 1 1
3BHK 119.19 4 2
3BHK 119.91 1 1
3BHK 120.2 3 2
3BHK 120.22 3 1
3BHK 120.76 4 1
3BHK 135.57 1 1
3BHK 151.48 1 1
3BHK 161.62 1 0

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 20

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Disclosure of sold/ booked inventory

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 71.08 2 2
3BHK 100.74 2 2
3BHK 102.43 1 1
3BHK 103.06 1 1
3BHK 103.27 1 1
3BHK 105.54 1 1
3BHK 105.64 1 1
3BHK 108.19 1 1
3BHK 109.45 5 2
3BHK 110.29 2 1
3BHK 110.84 6 2
3BHK 111.26 1 1
3BHK 112.85 1 1
3BHK 113.28 1 1
3BHK 119.19 4 2
3BHK 119.91 1 1
3BHK 120.2 3 2
3BHK 120.22 3 1
3BHK 135.57 1 1
3BHK 151.48 1 1
3BHK 95.94 1 1
3BHK 96.12 1 1
3BHK 98.53 2 2
3BHK 98.91 2 2

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of Interest in Other Real Estate Organizations

 

New documents listed below were uploaded to the Documents section:

  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Disclosure of sold/ booked inventory
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 120.76 4 1

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 19

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [3]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory [4]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Other – Legal [8]
  • Other – Technical [2]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]