MH
Mumbai City
P51900008625
RERA ID: P51900008625
Project Name: MEHRABAD
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2024-09-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2022-12-30, 2021-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Mahim, Veer Savarkar Marg, Gnorth-400016, Ward Gnorth, Mumbai City-400016

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
936

Boundaries:
CS NO 935
27 M WIDE SWATANTRA VEER SAWARKAR MARGN CS NO 943-937
WE
S
CS NO 948

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 615 sq.mt.
Sanctioned Built-up Area: 2492 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 23
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 42

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 325 to 536 sq ft 15 3
1RK 300 sq ft 1 0
2BHK 569 to 683 sq ft 30 10
3BHK 777 to 821 sq ft 2 1
Project Developer:
KHANDWANI EXPORT PVT LTD
Organization Type: Company

Address: 14, Pathan Manzil, Balamiya Lane, Mahim, Mumbai, Gnorth-400016, Ward Gnorth, Mumbai City-400016

Office Phone: +91 22244 41964
Website URL: WWW.KHANDWANIGROUP.COM


Member details:
Member Name Designation
SUHAIL MOHAMED YACOOB KHANDWANI Managing Director
NABILA SUHAIL KHANDWANI Managing Director
SUHAIL MOHAMED YACOOB KHANDWANI Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
ANKIT P DHARIA Architect
BLUE STONE DEVELOPERS Contractor
RANGWALA ADVISIORY AND CONSULTANTS Chartered Accountant
MITESH KANJI PATEL Engineer


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Mehrabad: A New Landmark in the Heart of Mahim

Mehrabad, a prestigious residential project developed by Khandwani Export Pvt Ltd, is poised to redefine luxury living in the bustling heart of Mahim, Mumbai. This ongoing project, registered under RERA ID P51900008625, promises to deliver a modern and sophisticated living experience, seamlessly blending comfort and convenience.

Located at Plot No. 936 in Mahim, the project boasts a strategic position, bordered by CS NO 943-937 to the east, the wide expanse of Swatantra Veer Sawarkar Marg to the west, CS NO 935 to the north, and CS NO 948 to the south. This prime location grants residents effortless access to the city’s vibrant tapestry of commerce, entertainment, and cultural hubs.

The project comprises a single building, encompassing 23 sanctioned floors, supported by a single stilt and a plinth. The building is designed to maximize space utilization, with a sanctioned FSI of 2492, enabling the development of 42 closed parking spaces for resident convenience.

While the proposed completion date was initially set for December 31st, 2021, the revised date of completion has been set for December 30th, 2022. This extension ensures meticulous attention to detail and unwavering commitment to delivering a project that surpasses expectations.

The project’s status is currently “On-Going,” reflecting the developer’s dedication to timely completion. Furthermore, the absence of any reported litigations underscores the project’s solid foundation and transparent operations.

Mehrabad stands as a testament to Khandwani Export Pvt Ltd’s commitment to delivering exceptional real estate solutions. The company, with its rich experience and impeccable reputation, is dedicated to providing residents with a lifestyle of unparalleled quality and comfort.

For those seeking a harmonious blend of modern living and prime location, Mehrabad presents an unparalleled opportunity. This project promises to be a defining landmark in Mahim, offering residents a truly exceptional living experience.

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-09-30

 

New documents listed below were uploaded to the Documents section:

  • 3 Declaration in FORM B

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
PAP 1 BHK 41.39 1 0
PAP 1 BHK 43.23 1 0
PAP 1 BHK 45.96 1 0
PAP 1 BHK 46.03 1 0
REHAB 1 BHK 33.7 1 0
REHAB 1 BHK 36.95 1 0
REHAB 1 BHK 49.77 1 0
REHAB 1 RK 27.88 1 0
REHAB 2 BHK 53.57 1 0
REHAB 2 BHK 53.78 1 0
REHAB 2 BHK 54.12 1 0
REHAB 2 BHK 63.5 1 0
REHAB 3 BHK 72.25 1 0
SALE 1 BHK 30.2 1 0
SALE 1 BHK 35.78 2 1
SALE 1 BHK 39.49 2 0
SALE 1 BHK 42.96 1 1
SALE 1 BHK 45.6 1 0
SALE 1 BHK 49.86 1 1
SALE 2 BHK 52.92 3 3
SALE 2 BHK 52.97 9 1
SALE 2 BHK 53.08 1 1
SALE 2 BHK 54.12 5 5
SALE 2 BHK 54.18 8 0
SALE 3 BHK 76.35 1 1

 

New documents listed below were uploaded to the Documents section:

  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 2 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
PAP 1 BHK 41.39 1 0
PAP 1 BHK 43.23 1 0
PAP 1 BHK 45.96 1 0
PAP 1 BHK 46.03 1 0
REHAB 1 BHK 33.7 1 0
REHAB 1 BHK 36.95 1 0
REHAB 1 BHK 49.77 1 0
REHAB 1 RK 27.88 1 0
REHAB 2 BHK 53.57 1 0
REHAB 2 BHK 53.78 1 0
REHAB 2 BHK 54.12 1 0
REHAB 2 BHK 63.5 1 0
REHAB 3 BHK 72.25 1 0
SALE 1 BHK 30.2 1 0
SALE 1 BHK 35.78 2 1
SALE 1 BHK 39.49 2 0
SALE 1 BHK 42.96 1 1
SALE 1 BHK 45.6 1 0
SALE 1 BHK 49.86 1 1
SALE 2 BHK 52.92 3 3
SALE 2 BHK 52.97 9 1
SALE 2 BHK 53.08 1 1
SALE 2 BHK 54.12 5 5
SALE 2 BHK 54.18 8 0
SALE 3 BHK 76.35 1 1

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 85

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 92 0
Electrical Meter Room, Sub-Station, Receiving Station : 100 COMPLETED
Water Supply : 100 COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : 92 WIP

 

Number of Closed Parking field under Building/Plot Details section updated with new value 42

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • 4 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Disclosure of sold/ booked inventory

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 23

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 30.2 1 0
1BHK 33.7 1 1
1BHK 35.78 2 1
1BHK 36.95 1 1
1BHK 39.49 2 0
1BHK 41.39 1 0
1BHK 43.23 1 0
1BHK 45.6 1 0
1BHK 45.96 1 0
1BHK 46.03 1 0
1BHK 49.77 1 1
1BHK 49.86 1 1
1RK 27.88 1 1
2BHK 52.92 3 3
2BHK 52.97 9 1
2BHK 53.08 1 1
2BHK 53.57 1 1
2BHK 53.78 1 1
2BHK 54.12 6 6
2BHK 54.18 8 0
2BHK 63.5 1 1
3BHK 72.25 1 1
3BHK 76.35 1 1

 

New documents listed below were uploaded to the Documents section:

  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) [2]
  • Building Plan Approval (IOD) [4]
  • CERSAI details
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [2]
  • Certificates of CA (Form 5)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [2]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B [2]
  • Details of encumbrances
  • Disclosure of Interest in Other Real Estate Organizations [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]