Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2028-09-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Mahalaxmi, Keshavrao Khadye Mart, E-400011, Ward E, Mumbai City-400011

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO D1 C.S. NO. 7/1895 OF BYCULLA DIVISION

Boundaries:
KESHAVRAO KHADYE MARG
RAILWAY LINES OF WESTERN RAILWAYSN PARTLY by SUBDIVIDED PLOT A1 and PARTLY by PLOT B
WE
S
SUBDIVIDED PLOT C

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 12601 sq.mt.
Sanctioned Built-up Area: 31653 sq.mt.
Recreational Open Space: 3226 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 30
No. of basements: 2
No. of Plinths: 1
No. of Podiums: 6
No. of Stilts: 1
No. of Closed Parking: 435

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 948 sq ft 1 0
3BHK 1668 sq ft 69 38
4BHK 2180 sq ft 70 46
Others 2811 to 3042 sq ft 12 3
Project Developer:
K RAHEJA CORP REAL ESTATE PRIVATE LIMITED
Organization Type: Company

Address: Plot No C-30, Block ‘G’, Raheja Tower, Bandra Kurla Complex, Bandra East, Next To Bank Of Baroda, Andheri, Mumbai Suburban-400051

Office Phone: +91 22265 64000
Website URL: www.krahejacorp.com


Member details:
Member Name Designation
SUNIL MADHAV HINGORANI Director
RAMESH RANGANATHAN Director
JIGNASHA CHETAN THAKKAR Company Secretory
RAVI CHANDRU RAHEJA Director
NEEL CHANDRU RAHEJA Director


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Modern India Limited - Landowner Company Revenue Share


Other Professionals involved:
Professional Name Professional Type
Kapadia Associate Design LLP Other Professional
Pankage Dharkar & Associates Other Professional
PVN Associates Other Professional
Mohan Jakati Engineer
Preeti Kashyap Barai Architect
Kiran Kapadia Architect
S N Doshi & Associates Chartered Accountant
Omsai Projects Contractor
Kapadia Associates Chartered Accountant


Projects in the state by this developer:
P51900054152 - RAHEJA AMALTIS - WING B - Mumbai City
P51900054129 - RAHEJA AMALTIS - WING A - Mumbai City
P51800051079 - MAESTRO - Mumbai Suburban
P51800046901 - VALLETTA - Mumbai Suburban
P51900034289 - RAHEJA MODERN VIVAREA NORTH TOWER - Mumbai City
P51900034288 - RAHEJA MODERN VIVAREA SOUTH TOWER - Mumbai City
P51800028506 - RAHEJA ASCENCIO - Mumbai Suburban
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
City Civil Court Mumbai 104240 Civil Suit 2010 Pending
City Civil Court Mumbai 104754 Civil Suit 2011 Pending
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

RAHEJA MODERN VIVAREA SOUTH TOWER: A Luxurious Residential Haven in the Heart of Mahalaxmi

RAHEJA MODERN VIVAREA SOUTH TOWER, a new residential project by renowned developer K Raheja Corp Real Estate Private Limited, promises a life of unparalleled luxury and comfort in the coveted locality of Mahalaxmi, Mumbai. This project, registered with MahaRERA under ID P51900034288, is poised to become a landmark development, offering residents an exclusive and sophisticated lifestyle.

Situated on a sprawling plot spanning 12601 sq. mts., the project boasts a single tower rising majestically to 30 sanctioned floors. The building, designed with meticulous attention to detail, includes two basements, one plinth, six podiums, and one stilt, offering ample parking space for residents with a capacity of 435 closed parking slots.

A Prime Location, Unbeatable Convenience:

RAHEJA MODERN VIVAREA SOUTH TOWER is strategically located in Mahalaxmi, a prime residential hub in Mumbai. The project enjoys excellent connectivity to various parts of the city, with easy access to major thoroughfares like Keshavrao Khadye Marg. Its proximity to the Western Railway lines offers convenient commuting options.

Luxury Living, Redefined:

The project offers a range of exquisitely designed apartments, catering to diverse needs and preferences. Residents can choose from spacious 2BHK, 3BHK, and 4BHK units, ranging from 948 sq. ft. to 2180 sq. ft. The project also features exclusive penthouses ranging from 2811 to 3042 sq. ft. offering panoramic views of the city.

World-Class Amenities:

RAHEJA MODERN VIVAREA SOUTH TOWER is designed to cater to the discerning needs of its residents, offering a plethora of world-class amenities within its premises. The project includes a generous 3150 sq. mt. dedicated to recreational open space, promising residents a tranquil and fulfilling lifestyle.

A Legacy of Excellence:

K Raheja Corp Real Estate Private Limited, renowned for its commitment to quality and innovation, brings its expertise to RAHEJA MODERN VIVAREA SOUTH TOWER. The project is expected to be completed by September 30th, 2028, and will be a testament to the company’s dedication to delivering exceptional residential experiences.

Investment Opportunity:

RAHEJA MODERN VIVAREA SOUTH TOWER presents an unparalleled opportunity to invest in a prime location with excellent growth potential. With its luxurious amenities and strategic location, the project is expected to appreciate significantly over time, making it an attractive investment proposition.

Note: It’s important to note that the project is currently facing legal issues. Prospective buyers should conduct thorough due diligence and seek legal advice before making any investment decisions.

New documents listed below were uploaded to the Documents section:

  • 3 Copy of the legal title report
  • 7 Disclosure of sold/ booked inventory
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Declaration about Commencement Certificate
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 26
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
1 Overall Percentage of Completion of the work done For the entire Building /Wing 43.7

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 435 226 0

 

Total Recreational Open Space as Per Sanctioned Plan field under Firm Details section updated with new value 3226.68

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 155.02 69 38
4BHK 202.61 70 46

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 88.13 1 0
3BHK 155.02 69 37
4BHK 202.61 70 44
5 BHK 261.16 11 3
5 BHK 282.66 1 0

 

New documents listed below were uploaded to the Documents section:

  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Disclosure of sold/ booked inventory
  • 10 Details of encumbrances

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 435 217 0

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 155.02 69 37
4BHK 202.61 70 44

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 17
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 6
1 Overall Percentage of Completion of the work done For the entire Building /Wing 42.3

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration in FORM B
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Other – Legal

 

Members added or updated under Firm details section

Member Name Designation
MOHAN ALMAL Director

 

New documents listed below were uploaded to the Documents section:

  • 5 Building Plan Approval / NA Order for plotted development

 

A correction has been made to the Developer’s address. The complete address is now: Plot No C-30, Block ‘G’, Raheja Tower, Bandra Kurla Complex, Bandra East, Next To Bank Of Baroda, Andheri, Mumbai Suburban-400051

 

Office Number field under Firm Details section updated with new value 2226564000.0

 

Please note that the developer responsible for this project has changed their name to K RAHEJA CORP REAL ESTATE PRIVATE LIMITED. This change could be due to a simple name correction, but it’s more likely indicative of a shift in project management or ownership. We recommend understanding the reasons behind this change as it may impact the project’s trajectory.

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 31653.43

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 88.13 1 0
3BHK 155.02 69 33
5 BHK 261.16 11 3
5 BHK 282.66 1 0

 

New documents listed below were uploaded to the Documents section:

  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 435 179 0

 

New documents listed below were uploaded to the Documents section:

  • 5 Disclosure of sold/ booked inventory
  • 9 Details of encumbrances

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 100
1 Stilt Floor 100
1 X number of Slabs of Super Structure 7
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 4
1 Overall Percentage of Completion of the work done For the entire Building /Wing 41.1

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 155.02 70 33
4BHK 202.61 70 34
5 BHK 261.16 12 3

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [2]
  • Building Plan Approval / NA Order for plotted development [4]
  • CERSAI details [4]
  • Commencement Certificates / NA Order for plotted development [3]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate [3]
  • Declaration in FORM B
  • Details of encumbrances [5]
  • Disclosure of sold/ booked inventory [4]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter [3]
  • a Details of encumbrances concerned to Finance [3]
  • b Details of encumbrances concerned to Legal [3]