P51900009939
RERA ID: P51900009939
Project Name: FUEGO
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2024-12-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2022-12-30, 2016-06-30).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
, Mumbai City-400008

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CS NO 207 1/207 208

Boundaries:
CS NO 209
CS NO 201 202N SHUKLAJI STREET
WE
S
CS NO 206

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 4245 sq.mt.
Sanctioned Built-up Area: 15936 sq.mt.
Recreational Open Space: 313 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 46
No. of basements: 6
No. of Plinths: 3
No. of Podiums: 4
No. of Stilts: 3
No. of Closed Parking: 190

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 334 to 428 sq ft 65 30
1RK 0 sq ft 0 0
2BHK 587 to 831 sq ft 141 85
Others 499 sq ft 14 4
Project Developer:
HILTON INFRASTRUCTURE
Organization Type: Partnership

Address: 1896, Rubberwala House, Dr A B Nair Marg, Agripada, Next To Agripada Police Quarters, Mumbai City-400011

Office Phone: +91 22230 27800


Member details:
Member Name Designation
TABREZ SHAFIAHMED SHAIKH Partner
TABREZ SHAFIAHMED SHAIKH Authorized Signatory
RUBBERWALA HOUSING AND INFRASTRUCTURE DEVELOPMENT Partner
MOHIUDDIN AHMED ABDUL HAMID ANSARI Partner


Other Professionals involved:
Professional Name Professional Type
GREENWORLD CONSTRUCTIONS PVT LTD Contractor
IRANI ARCHITECTS Architect
MEP CONSULTING ENGINEERS Other Professional
SHAIKH & ASSOCIATES Other Professional
STRUCT BOMBAY CONSULTANTS Engineer
MOHAN L GUPTA & ASSOCIATES Chartered Accountant
SHAIKH & ASSOCIATES Architect


Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
SMALL CAUSES 201197 Civil Suit 2012 EVIDENCE AND HEARING
CITY CIVIL 4656 Civil Suit 2012 FOR RECORDING EVIDENCE
CITY CIVIL 4655 Civil Suit 2012 FOR RECORDING EVIDENCE
Complaints

Complaint No Complainant Name
CC006000000210073 M/S HILTON INFRASTRUCTRE
CC006000000198417 Harsha Sanjay Siroya
CC006000000198534 Hulas B. Siroya
CC006000000198418 Nisha J. Singhvi
CC006000000198528 Neeta Rajesh Lodha
CC006000000198535 Sheela Naresh Lodha
CC006000000198532 Dipti Pratik Singhvi
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

FUEGO: A Residential Project in Mumbai’s Heart

FUEGO, a residential project situated in the heart of Mumbai City, promises a unique living experience with its convenient location and comprehensive amenities. This ongoing project, registered with MahaRERA under ID P51900009939, has experienced some delays in its completion timeline. Initially scheduled for completion in June 2016, the revised date of completion is now December 2024. This delay is attributed to ongoing legal disputes, a common challenge faced by many real estate projects in India.

Despite the legal complications, FUEGO boasts an impressive scope. Developed by HILTON INFRASTRUCTURE, a partnership firm based in Mumbai, the project occupies a prime plot of land spanning 4245 sq mts (CS NO 207 1/207 208). Situated in a central location, the project is bordered by Shuklajistreet to the east, CS NO 201 202 to the west, CS NO 209 to the north, and CS NO 206 to the south. The strategic location offers residents easy access to vital amenities and major transportation hubs.

FUEGO’s design encompasses three buildings, all sanctioned and currently under construction, with a total sanctioned FSI of 15936 sq mts. The project also includes an impressive 313 sq mts of recreational open space, ensuring residents enjoy a balanced lifestyle. The project comprises a diverse range of units, catering to various needs and preferences. These include 65 1BHK units ranging from 334 to 428 sq ft, 141 2BHK units ranging from 587 to 831 sq ft, and 14 other units with a 499 sq ft area.

The project boasts a robust infrastructure with 6 basements, 3 plinths, 4 podiums, and 46 sanctioned floors. The stilt parking area accommodates 190 vehicles, ensuring convenient parking for residents. The project’s construction is underway, with ICICI Bank serving as the project’s financial partner.

While the ongoing legal issues pose challenges, FUEGO remains a promising project with potential for lucrative returns. Potential investors and homebuyers should conduct thorough due diligence and understand the risks associated with the legal complications before making any decisions. However, the project’s location, amenities, and diverse unit options make it an attractive option for those seeking a comfortable and well-connected living space in Mumbai.

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 65 WORK IN PROGRESS
Solid Waste Management And Disposal : 35 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : 60 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : 75 WORK IN PROGRESS
Water Supply : 65 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : 75 WORK IN PROGRESS
Storm Water Drains : 65 WORK IN PROGRESS

 

New documents listed below were uploaded to the Documents section:

  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 78
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 75.8

 

New documents listed below were uploaded to the Documents section:

  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 55 WORK IN PROGRESS

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1.5BHK 46.37 14 4
1BHK 31.09 14 7
1BHK 32.61 14 11
1BHK 35.86 1 1
1BHK 36.07 13 3
1BHK 38.5 9 5
1BHK 39.79 14 3
1RK 0 0 0
2BHK 54.57 14 4
2BHK 54.93 16 5
2BHK 56.33 7 1
2BHK 58.12 7 5
2BHK 59.86 14 5
2BHK 66.5 30 21
2BHK 71.88 26 20
2BHK 75.47 21 18
2BHK 77.24 6 6

 

New documents listed below were uploaded to the Documents section:

  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

New complaints added under Complaints section

Complaint No Complainant Name
CC006000000198535 Sheela Naresh Lodha
CC006000000198534 Hulas B. Siroya
CC006000000198532 Dipti Pratik Singhvi
CC006000000198528 Neeta Rajesh Lodha
CC006000000198418 Nisha J. Singhvi
CC006000000198417 Harsha Sanjay Siroya

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • 4 Certificates of CA (Form 5)

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-12-30

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 12
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 45
1 Overall Percentage of Completion of the work done For the entire Building /Wing 73.7
2 X number of Podiums 0
2 Overall Percentage of Completion of the work done For the entire Building /Wing 90
3 X number of Podiums 0
3 Overall Percentage of Completion of the work done For the entire Building /Wing 90

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1.5BHK 46.37 14 4
1BHK 31.09 14 7
1BHK 32.61 14 11
1BHK 36.07 13 3
1BHK 39.79 14 3
2BHK 54.57 14 4
2BHK 56.33 7 1
2BHK 58.12 7 5
2BHK 59.86 14 5

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 CERSAI details
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
SHAIKH & ASSOCIATES Architect
MOHAN L GUPTA & ASSOCIATES Chartered Accountant

 

Members added or updated under Firm details section

Member Name Designation
RUBBERWALA HOUSING AND INFRASTRUCTURE DEVELOPMENT Partner
MOHIUDDIN AHMED ABDUL HAMID ANSARI Partner

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of sold/ booked inventory
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 2 Disclosure of Interest in Other Real Estate Organizations
  • 3 Disclosure of Interest in Other Real Estate Organizations
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 2 Declaration in FORM B
  • 5 Commencement Certificates / NA Order for plotted development

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Building Plan Approval (IOD) [24]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [11]
  • Certificates of CA (Form 5) [3]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [11]
  • Commencement Certificates / NA Order for plotted development [4]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Other
  • Proforma of Agreement for sale
  • Proforma of Allotment letter