P51900007411
RERA ID: P51900007411
Project Name: Annapurna Sadan
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2026-06-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2024-12-30, 2021-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
, Mumbai City-400004

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
2879 2883

Boundaries:
urvey no 2878
bhuleshwerN Oad
WE
S
urvey no 2881

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 841 sq.mt.
Sanctioned Built-up Area: 9793 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 21
No. of basements: 2
No. of Plinths: 1
No. of Podiums: 2
No. of Closed Parking: 58

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 414 sq ft 2 2
1RK 125 sq ft 1 1
2BHK 482 to 685 sq ft 11 10
3BHK 804 to 941 sq ft 13 9
4BHK 1060 to 1064 sq ft 4 4
Project Developer:
D R Developers
Organization Type: Others (Proprietorship)

Address: 207, Mantri Building, J S S Road, Girgaon, Girgaon Church, Abcd-400004, Ward Abcd, Mumbai City-400004




Other Professionals involved:
Professional Name Professional Type
Vijay Kabre Architect
A D Shintre Consultants Engineer
Himanshu Gandhi Chartered Accountant
KARIA CHHEDA & ASSOCIATES Chartered Accountant
SK Consultants & Engineers Engineer
Rutuja Narsingh & Associates Chartered Accountant


Projects in the state by this developer:
P51900055307 - Shakuntala Sadan - Mumbai City
P51900007411 - Annapurna Sadan - Mumbai City
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Unveiling Annapurna Sadan: A Prime Residential Project in the Heart of Mumbai City

Annapurna Sadan, a meticulously planned residential project, is poised to redefine modern living in the bustling metropolis of Mumbai. Located in the heart of the city, this ongoing project promises to offer a unique blend of convenience, comfort, and luxury to its residents.

Project Details:

Registered under the Maharashtra Real Estate Regulatory Authority (MahaRERA) with ID P51900007411, Annapurna Sadan is a testament to meticulous planning and commitment to quality. Situated on a plot spanning 841 square meters, this project encompasses a single, elegantly designed building with a sanctioned FSI of 9793. The project boasts a total of 21 floors, including 2 basements, 1 plinth, and 2 podiums, offering residents a spacious and well-ventilated living experience.

Prime Location:

Strategically positioned in Mumbai City, Annapurna Sadan enjoys an enviable location. The project’s boundaries are defined by a road to the east, Bhuleshwer to the west, survey no. 2878 to the north, and survey no. 2881 to the south. This prime location ensures easy access to essential amenities, including renowned educational institutions, healthcare facilities, shopping centers, and recreational spaces, making it an ideal choice for families and individuals alike.

Developer Expertise:

The project is spearheaded by D R Developers, a renowned proprietorship with a track record of delivering exceptional real estate projects. Their commitment to quality construction and customer satisfaction is reflected in their meticulous planning and execution of Annapurna Sadan.

Amenities:

Annapurna Sadan offers a comprehensive range of amenities designed to enhance the residents’ lifestyle. These amenities include a well-secured closed parking facility for 58 vehicles, ensuring the safety and convenience of residents.

Investment Opportunity:

With its prime location, meticulously planned design, and comprehensive amenities, Annapurna Sadan presents an unparalleled investment opportunity. The project’s strategic positioning in Mumbai City guarantees high rental yields and capital appreciation, making it an attractive proposition for discerning investors.

Future Outlook:

While the initial proposed completion date was December 31, 2021, the project timeline has been extended to June 30, 2026. However, the project remains on track, with construction progressing steadily.

Conclusion:

Annapurna Sadan is an exceptional residential project that offers a unique blend of convenience, comfort, and luxury in the heart of Mumbai City. Its prime location, well-planned design, and comprehensive amenities make it an ideal choice for families, individuals, and investors seeking a fulfilling and enriching lifestyle. With its ongoing construction and commitment to quality, Annapurna Sadan is poised to become a landmark destination in the city.

There are additions/modifications under Professionals section

Professional Name Professional Type
Rutuja Narsingh & Associates Chartered Accountant

 

New documents listed below were uploaded to the Documents section:

  • 28 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1RK 11.67 1 1
3BHK 74.78 3 3

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 38.55 2 2
2BHK 44.86 1 1
2BHK 44.88 1 1
2BHK 58.3 1 1
2BHK 58.7 1 0
2BHK 58.72 1 1
2BHK 62 1 1
2BHK 62.99 1 1
2BHK 63.2 1 1
2BHK 63.4 2 2
2BHK 63.66 1 1
3BHK 74.76 3 2
3BHK 74.78 3 2
3BHK 77.73 1 1
3BHK 83.29 1 1
3BHK 83.77 1 0
3BHK 86.27 2 0
3BHK 86.88 1 1
3BHK 87.5 1 1
4BHK 98.55 2 2
4BHK 98.59 1 1
4BHK 98.88 1 1

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of sold/ booked inventory

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2026-06-30

 

New documents listed below were uploaded to the Documents section:

  • 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 44.86 1 1
2BHK 44.88 1 1
2BHK 58.3 1 1
2BHK 58.7 1 0
2BHK 58.72 1 1
3BHK 74.76 3 2
3BHK 74.78 3 2
3BHK 77.73 1 1
4BHK 98.55 2 2
4BHK 98.59 1 1
4BHK 98.88 1 1

 

New documents listed below were uploaded to the Documents section:

  • 27 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 Declaration in FORM B

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Solid Waste Management And Disposal : 0 As per approved Plan
Landscaping & Tree Planting : 0 As per Approved Plan
Storm Water Drains : 0 As per Approved Plan
Fire Protection And Fire Safety Requirements : 80 As per Approved Plan
Electrical Meter Room, Sub-Station, Receiving Station : 100 Completed

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
5BHK & more 158.97 2 2
5BHK & more 138.86 1 1
5BHK & more 157.76 1 1

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 97
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 96
1 Overall Percentage of Completion of the work done For the entire Building /Wing 97.2

 

New documents listed below were uploaded to the Documents section:

  • 5 Certificates of CA (Form 5)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 CERSAI details
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
5BHK & more 158.97 2 2
5BHK & more 138.86 1 1
5BHK & more 157.76 1 1

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 21

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 9793.57

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 44.86 2 2
1BHK 44.88 1 1
1BHK 57.2 3 3
2BHK 62 1 1
2BHK 74.76 4 3
3BHK 86.27 2 0
3BHK 98.55 2 2
5BHK & more 158.97 2 2
5BHK & more 138.86 1 1
5BHK & more 157.76 1 1

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 37.68 1 1
1BHK 38.55 2 2
1BHK 40.8 1 1
1BHK 41.86 1 1
1BHK 42.16 1 1
1BHK 42.58 1 1
1BHK 42.7 1 1
1BHK 43 1 1
1BHK 44.21 1 1
1BHK 44.86 3 3
1BHK 44.88 2 2
1BHK 47.66 1 1
1BHK 47.77 1 1
1BHK 50.19 1 1
1BHK 50.24 1 1
1BHK 57.2 4 4
1BHK 58.3 1 1
1BHK 58.7 1 0
1BHK 58.72 1 1
1RK 23.08 1 1
1RK 24.56 1 1
1RK 29.45 1 1
2BHK 60.75 1 1
2BHK 62 2 2
2BHK 62.99 1 1
2BHK 63.2 1 1
2BHK 63.4 2 2
2BHK 63.53 1 1
2BHK 63.66 1 1
2BHK 64.27 1 1
2BHK 69.33 1 1
2BHK 74.46 5 4
2BHK 74.78 3 2
2BHK 75.42 1 1
2BHK 76.83 1 1
2BHK 76.94 1 1
2BHK 77.73 1 1
3BHK 83.09 1 1
3BHK 83.29 1 1
3BHK 83.77 1 0
3BHK 85.45 1 1
3BHK 86.27 3 1
3BHK 86.88 1 1
3BHK 87.5 1 1
3BHK 97.8 1 1
3BHK 98.13 1 1
3BHK 98.55 3 3
3BHK 98.59 1 1
3BHK 98.88 1 1
5BHK & more 138.86 1 1
5BHK & more 157.76 1 1
5BHK & more 158.97 3 3
Add. Tenant Area 9.78 1 1
Commercial 124.49 1 1
Shop 22.39 1 1
Shop 22.86 1 1
Shop 32.08 1 1
Shop 38.09 1 1
Shop 78.31 1 1

 

There are additions/modifications under Professionals section

Professional Name Professional Type
SK Consultants & Engineers Engineer
RERA Easy Other Professional
Vidya S. Bhure & Co. Chartered Accountant

 

New documents listed below were uploaded to the Documents section:

  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 26 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 1 Disclosure of sold/ booked inventory
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Declaration about Commencement Certificate

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 96
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 94
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
1 Overall Percentage of Completion of the work done For the entire Building /Wing 96.8

 

New documents listed below were uploaded to the Documents section:

  • 3 Commencement Certificates / NA Order for plotted development
  • 25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 3 Building Plan Approval (IOD)
  • 5 Copy of Layout Approval (in case of layout)
  • 4 Copy of Layout Approval (in case of layout)
  • 2 Building Plan Approval (IOD)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
5BHK & more 476.91 3 0

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 0 As per approved plan
Sewerage (Chamber, Lines, Septic Tank , STP) : 70 As per approved plan
Internal Roads & Footpaths : 23 As per approved plan
Water Conservation, Rain water Harvesting : 0 As per approved plan
Fire Protection And Fire Safety Requirements : 80 0
Water Supply : 70 As per approved plan

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) [2]
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [24]
  • Certificates of CA (Form 5) [4]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [23]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Proforma of Allotment letter [10]