RERA ID: P52600026127
Project Name: MANALI PLAZA
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2023-07-17
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Isbavi, Pune Pandharpur Road, Pandharpur, Solapur-413304

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 3, GAT NO 13 1 2 3 4 5 6

Boundaries:
GAT NO 11
OPEN SPACE FOR GARDENN PLOT NO 4
WE
S
12 METER WIDE ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 962 sq.mt.
Sanctioned Built-up Area: 1171 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 4
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 1
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 353 to 387 sq ft 35 21
Project Developer:
GLOBAL INFRASTRUCTURE
Organization Type: Partnership

Address: Gat No13/1/2/3/4/5/6, Plo No3, Pune Pandharpur Road, Isbavi, Malape Vada, Pandharpur, Solapur-413304

Office Phone: +91 73503 30265


Member details:
Member Name Designation
ATUL BHASKAR MORE Partner
ATUL BHASKAR MORE Authorized Signatory
MAHESH DNYANDEO DAMALE Partner
PRAMOD VINOD GULECHA Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
ANKUSH DNYANOBA MALAPE/ SANJEEVANI ANKUSH MALAPE Individual Area Share
MRS SANJIVINI ANKUSH MALAPE Individual Area Share
MR AKSHAY ANKUSH MALAPE Individual Area Share
MRS POOJA VIVEK GAIKWAD Individual Area Share


Other Professionals involved:
Professional Name Professional Type
R B & ASSOCIATES Architect
PRADEEPMOTE &ASSO Engineer
A B BHALERAO & CO Chartered Accountant


Projects in the state by this developer:
P50500047734 - SAHASTRABAHU NAGAR - Nagpur
P52600026127 - MANALI PLAZA - Solapur
P49900013989 - KRISHNA CITY - Jalgaon
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing MANALI PLAZA: A New Residential Project in Isbavi, Solapur

This essay introduces MANALI PLAZA, a new residential project located in the picturesque village of Isbavi, Solapur, Maharashtra. Developed by GLOBAL INFRASTRUCTURE, a partnership firm, this project offers a unique opportunity to own a comfortable and modern home in a serene environment.

MANALI PLAZA, registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under the ID P52600026127, is currently under construction and is expected to be completed by July 17th, 2023. The project occupies a spacious 962 square meters plot (PLOT NO 3, GAT NO 13 1 2 3 4 5 6) and boasts a single, well-planned building with four floors and a stilt level.

A Tranquil Setting with Convenient Access:

The project is strategically located on Pune Pandharpur Road in Isbavi, offering a peaceful and serene living environment. The property is bordered by a 12-meter wide road to the south, a garden area to the west, and PLOT NO 4 to the east. With its proximity to the main road, residents can enjoy convenient access to various amenities and facilities.

Spacious and Affordable 1BHK Units:

MANALI PLAZA offers a limited number of 1BHK units, ranging from 353 to 387 square feet. These thoughtfully designed apartments are ideal for individuals, couples, or small families looking for a comfortable and affordable home.

Key Features & Amenities:

The project boasts several amenities, including:

  • Open Parking: The project offers one open parking space for both four-wheelers and two-wheelers.
  • Closed Parking: One closed parking space is also available for added convenience.

Project Details at a Glance:

  • Project Type: Residential
  • Project Status: New Project
  • Proposed Date of Completion: July 17th, 2023
  • Total Plot Area: 962 sqmts
  • Sanctioned FSI: 1171
  • Units on offer: 1BHK (353 to 387 sq ft) - 35 Nos
  • Promoter: GLOBAL INFRASTRUCTURE

Invest in your Future:

MANALI PLAZA presents an excellent opportunity for those seeking a comfortable and affordable home in a peaceful location. With its convenient location, well-designed units, and limited availability, this project is sure to attract discerning buyers looking for a fulfilling and tranquil lifestyle.

For more information, please contact GLOBAL INFRASTRUCTURE at 7350330265.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 100
Water Supply : 100
Open Parking : 100
Electrical Meter Room, Sub-Station, Receiving Station : 100
Water Conservation, Rain water Harvesting : 100

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 1 0 100

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Electrical Meter Room, Sub-Station, Receiving Station : 0
Water Supply : 50
Sewerage (Chamber, Lines, Septic Tank , STP) : 90

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 32.83 1 1
1BHK 32.95 2 1
1BHK 33.21 3 2
1BHK 33.65 2 2
1BHK 33.71 2 2
1BHK 33.82 5 4
1BHK 34.09 3 1
1BHK 34.36 3 1
1BHK 34.94 2 1
1BHK 35.84 3 2
1BHK 35.93 3 2
1BHK 35.98 3 2

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 77.5

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other [7]
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.)