Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | Percentage of Work | 25 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 72 |
1 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | Percentage of Work | 80 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 1BHK | 28.14 | Number of Booked Apartment | 7 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 3BHK | 70.46 | Number of Booked Apartment | 4 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | X number of Slabs of Super Structure | Percentage of Work | 40 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 3BHK | 104.49 | Number of Apartment | 10 |
1 | 2BHK | 82.1 | Number of Apartment | 38 |
1 | Shop | 40.3 | Number of Apartment | 6 |
1 | Shop | 21.45 | Number of Apartment | 8 |
1 | 2BHK | 82.23 | Number of Apartment | 11 |
1 | 3BHK | 112.12 | Number of Apartment | 22 |
1 | Shop | 40.3 | Number of Booked Apartment | 3 |
1 | Shop | 21.45 | Number of Booked Apartment | 5 |
1 | 2BHK | 84.66 | Number of Booked Apartment | 40 |
1 | 3BHK | 104.31 | Number of Booked Apartment | 12 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 30.6 |
1 | X number of Slabs of Super Structure | Percentage of Work | 6 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 7 |
1 | Excavation | Percentage of Work | 70 |
Sewerage (Chamber, Lines, Septic Tank , STP) : field under Development work/Amenities progress section updated with new value for Percent as 60.0
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 46.59 | Number of Booked Apartment | 8 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | Percentage of Work | 60 |
1 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | Percentage of Work | 30 |
1 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | Percentage of Work | 70 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 46 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Excavation | Percentage of Work | 97 |
1 | Stilt Floor | Percentage of Work | 65 |
1 | X number of Slabs of Super Structure | Percentage of Work | 35 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 30.2 |
Project details section updated for field(s) as below:
Field updated | New value |
---|---|
Proposed Date of Completion | 12/31/2027 |
Total Number of Proposed Building/Wings (In the Layout/Plot) | 30.0 |
Number of Sanctioned Building out of Above Proposed Count Applied for this Registration | 30.0 |
Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) | 97465.78 |
Permissible Total FSI of Plot (Permissible Built-up Area) | 97465.78 |
Building details/Main section updated for field(s) as below:
Name (Also mention identification of building/wing/other as per approved plan) | Field updated | New value |
---|---|---|
Building B7 | Proposed Date of Completion | 31/12/2027 |
Building B7 | Number of Stilts | 0.0 |
Building B7 | Number of Closed Parking | 0.0 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
21 | Shop | 10 | Number of Apartment | 12 |
21 | Shop | 7.29 | Number of Apartment | 3 |
21 | Shop | 9.13 | Number of Apartment | 1 |
30 | 1BHK | 29.18 | Number of Apartment | 64 |
30 | Shop | 10 | Number of Apartment | 8 |
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 2175.95 | Number of Apartment | 34 |
1 | Shop | 107.45 | Number of Apartment | 4 |
1 | Shop | 107.45 | Number of Booked Apartment | 4 |
MAGESTY BLOSSOM field under Building details/Main section updated with new value for Number of Sanctioned Floors as 7.0
CARNATION B field under Building details/Main section updated with new value for Proposed Date of Completion as 30/06/2021
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 63 | Number of Apartment | 3 |
2 | 2BHK | 63 | Number of Booked Apartment | 40 |
TODI TULSYAN & CO field under Project Professional Information section updated with new value for Professional Type as Chartered Accountant
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 90 |
Building details/Main section updated for field(s) as below:
Name (Also mention identification of building/wing/other as per approved plan) | Field updated | New value |
---|---|---|
Aastha Residency | Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) | 173 |
Aastha Residency | Number of Closed Parking | 0 |
Building details/Progress section updated for field(s) as below:
Bldg. Sr.No. | Tasks / Activity | Field updated | New value |
---|---|---|---|
1 | X number of Podiums | Percentage of Work | 95 |
1 | Overall Percentage of Completion of the work done For the entire Building /Wing | Percentage of Work | 96.5 |
Treatment And Disposal Of Sewage And Sullage Water : field under Development work/Amenities progress section updated with new value for Percent as 95.0
Building details/Apartment section updated for field(s) as below:
Bldg. Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Field updated | New value |
---|---|---|---|---|
1 | 2BHK | 50.26 | Number of Booked Apartment | 2 |