RERA ID: P52600017938
Project Name: Ray Nagar Housing Project
Project Type: Mixed (Plots & Buildings)
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-30
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Kumbhari To Doddi Road, Kumbhari, Solapur South, Solapur-413006

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
722/2/F723,697,707,726,724,725,764,721,845,728,710,755,729/1,978/3,979/1,963/1,963/2,963/3,977/1,981/1,982/1,982/2

Boundaries:
Gat no 711 to 770
Gat no 663 to 402N Kumbhari to Darganhalli Road
WE
S
Kumbhari to Sakhar Karkhana road

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 760018 sq.mt.
Sanctioned Built-up Area: 1201 sq.mt.
Recreational Open Space: 76002 sq.mt.
No. of Buildings sanctioned: 431
No. of Floors sanctioned: 1356
No. of Plinths: 452
No. of Open Parking: 15994

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 294 to 300 sq ft 15994 10980
Project Developer:
Vasant Vihar Realty Pvt Ltd
Organization Type: Company

Address: 157, Sushila Apartment, Vip, Railway Line, Near Kaljapur Maruti Temple, Solapur (M Corp.), Solapur North, Solapur-413001

Office Phone: +91 21723 10442


Member details:
Member Name Designation
Syed Mahtab Alam Authorized Signatory


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Ray Nagar Housing Co-op Societies Federation Ltd Societies Revenue Share


Other Professionals involved:
Professional Name Professional Type
Santosh Mote Architect
Shrinivas Mohalkar Engineer
Pravin Deodhar Architect
Parag Rane Architect
Prakarsh Sangave Engineer


Projects in the state by this developer:
P52600017956 - Ray Nagar Housing Project Phase 2 - Solapur
P52600017938 - Ray Nagar Housing Project - Solapur
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing the Ray Nagar Housing Project: A Thriving Community in Solapur

The Ray Nagar Housing Project, registered under the Maharashtra Real Estate Regulatory Authority (MahaRERA) with ID P52600017938, is a new and exciting development poised to transform the landscape of Solapur. This mixed-use project, encompassing both plots and buildings, promises a vibrant and sustainable living experience for residents.

A Prime Location: Situated in the heart of Solapur, the project strategically boasts a prime location in the Kumbhari village, easily accessible via the Kumbhari to Doddi road. Its proximity to key amenities and its strategic placement within the district of Solapur makes it an attractive proposition for families and individuals alike.

Diverse Housing Options: The project offers a diverse range of housing options, catering to varying needs and preferences. The development plans include the construction of 431 buildings, with a total of 1356 sanctioned floors, ensuring ample space and privacy for its residents. Additionally, the project offers plots for those seeking to build their dream homes.

A Focus on Amenities and Sustainability: Recognizing the importance of a holistic living experience, the Ray Nagar Housing Project boasts an impressive array of amenities. These include a generous open parking space for 15994 vehicles (both four-wheelers and two-wheelers) and a dedicated recreational open space of 76002 square meters, ensuring a green and healthy environment for residents.

Promoter Commitment: Developed by Vasant Vihar Realty Pvt Ltd, a reputable company with a strong track record in real estate, the project is committed to delivering a high-quality and sustainable living experience. Their commitment is further reflected in their adherence to the MahaRERA regulations, ensuring transparency and accountability throughout the project’s lifecycle.

A Promising Future: The Ray Nagar Housing Project, with its prime location, diverse housing options, comprehensive amenities, and a reputable developer, promises a bright future for its residents. This project is set to redefine modern living in Solapur, offering a comfortable and sustainable lifestyle amidst a thriving community. With a projected completion date of December 30th, 2025, the project is poised to become a landmark development in Solapur, attracting residents seeking a fulfilling and prosperous life.

New documents listed below were uploaded to the Documents section:

  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.34 36 35
1BHK 27.94 15958 10945

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 20 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 21 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Architect’s Certificate on Completion of Project (Form 4)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 100 As per ADTP & MHADA rules
Water Conservation, Rain water Harvesting : 100 As per ADTP & MHADA rules
Water Supply : 100 As per ADTP & MHADA rules
Solid Waste Management And Disposal : 100 As per ADTP & SMC rules
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 As per ADTP & MHADA rules
Open Parking : 100 As per ADTP & MHADA rules

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
70 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
70 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
70 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
70 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
70 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
70 Overall Percentage of Completion of the work done For the entire Building /Wing 80
71 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
71 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
71 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
71 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
71 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
71 Overall Percentage of Completion of the work done For the entire Building /Wing 80
234 Excavation 100
234 X number of Basement(s) and Plinth 100
234 X number of Slabs of Super Structure 100
234 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
234 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
234 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
234 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
234 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
234 Overall Percentage of Completion of the work done For the entire Building /Wing 80
235 Excavation 100
235 X number of Basement(s) and Plinth 100
235 X number of Slabs of Super Structure 100
235 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
235 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
235 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
235 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
235 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
235 Overall Percentage of Completion of the work done For the entire Building /Wing 80
236 Excavation 100
236 X number of Basement(s) and Plinth 100
236 X number of Slabs of Super Structure 100
236 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
236 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
236 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
236 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
236 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
236 Overall Percentage of Completion of the work done For the entire Building /Wing 80
237 Excavation 100
237 X number of Basement(s) and Plinth 100
237 X number of Slabs of Super Structure 100
237 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
237 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
237 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
237 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
237 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
237 Overall Percentage of Completion of the work done For the entire Building /Wing 80
238 Excavation 100
238 X number of Basement(s) and Plinth 100
238 X number of Slabs of Super Structure 100
238 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
238 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
238 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
238 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
238 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
238 Overall Percentage of Completion of the work done For the entire Building /Wing 80
239 Excavation 100
239 X number of Basement(s) and Plinth 100
239 X number of Slabs of Super Structure 100
239 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
239 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
239 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
239 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
239 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
239 Overall Percentage of Completion of the work done For the entire Building /Wing 80
240 Excavation 100
240 X number of Basement(s) and Plinth 100
240 X number of Slabs of Super Structure 100
240 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
240 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
240 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
240 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
240 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
240 Overall Percentage of Completion of the work done For the entire Building /Wing 80
241 Excavation 100
241 X number of Basement(s) and Plinth 100
241 X number of Slabs of Super Structure 100
241 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
241 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
241 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
241 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
241 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
241 Overall Percentage of Completion of the work done For the entire Building /Wing 80
242 Excavation 100
242 X number of Basement(s) and Plinth 100
242 X number of Slabs of Super Structure 100
242 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
242 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
242 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
242 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
242 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
242 Overall Percentage of Completion of the work done For the entire Building /Wing 80
243 Excavation 100
243 X number of Basement(s) and Plinth 100
243 X number of Slabs of Super Structure 100
243 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
243 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
243 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
243 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
243 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
243 Overall Percentage of Completion of the work done For the entire Building /Wing 80
244 Excavation 100
244 X number of Basement(s) and Plinth 100
244 X number of Slabs of Super Structure 100
244 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
244 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
244 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
244 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
244 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
244 Overall Percentage of Completion of the work done For the entire Building /Wing 80
245 Excavation 100
245 X number of Basement(s) and Plinth 100
245 X number of Slabs of Super Structure 100
245 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
245 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
245 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
245 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
245 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
245 Overall Percentage of Completion of the work done For the entire Building /Wing 80
246 Excavation 100
246 X number of Basement(s) and Plinth 100
246 X number of Slabs of Super Structure 100
246 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
246 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
246 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
246 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
246 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
246 Overall Percentage of Completion of the work done For the entire Building /Wing 80
247 Excavation 100
247 X number of Basement(s) and Plinth 100
247 X number of Slabs of Super Structure 100
247 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
247 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
247 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
247 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
247 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
247 Overall Percentage of Completion of the work done For the entire Building /Wing 80
248 Excavation 100
248 X number of Basement(s) and Plinth 100
248 X number of Slabs of Super Structure 100
248 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
248 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
248 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
248 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
248 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
248 Overall Percentage of Completion of the work done For the entire Building /Wing 80
249 Excavation 100
249 X number of Basement(s) and Plinth 100
249 X number of Slabs of Super Structure 100
249 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
249 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
249 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
249 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
249 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
249 Overall Percentage of Completion of the work done For the entire Building /Wing 80
250 Excavation 100
250 X number of Basement(s) and Plinth 100
250 X number of Slabs of Super Structure 100
250 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
250 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
250 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
250 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
250 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
250 Overall Percentage of Completion of the work done For the entire Building /Wing 80
251 Excavation 100
251 X number of Basement(s) and Plinth 100
251 X number of Slabs of Super Structure 100
251 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
251 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
251 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
251 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
251 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
251 Overall Percentage of Completion of the work done For the entire Building /Wing 80
252 Excavation 100
252 X number of Basement(s) and Plinth 100
252 X number of Slabs of Super Structure 100
252 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
252 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
252 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
252 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
252 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
252 Overall Percentage of Completion of the work done For the entire Building /Wing 80
253 Excavation 100
253 X number of Basement(s) and Plinth 100
253 X number of Slabs of Super Structure 100
253 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
253 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
253 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
253 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
253 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
253 Overall Percentage of Completion of the work done For the entire Building /Wing 80
254 Excavation 100
254 X number of Basement(s) and Plinth 100
254 X number of Slabs of Super Structure 100
254 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
254 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
254 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
254 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
254 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
254 Overall Percentage of Completion of the work done For the entire Building /Wing 80
255 Excavation 100
255 X number of Basement(s) and Plinth 100
255 X number of Slabs of Super Structure 100
255 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
255 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
255 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
255 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
255 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
255 Overall Percentage of Completion of the work done For the entire Building /Wing 80
256 Excavation 100
256 X number of Basement(s) and Plinth 100
256 X number of Slabs of Super Structure 100
256 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
256 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
256 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
256 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
256 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
256 Overall Percentage of Completion of the work done For the entire Building /Wing 80
257 Excavation 100
257 X number of Basement(s) and Plinth 100
257 X number of Slabs of Super Structure 100
257 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
257 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
257 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
257 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
257 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
257 Overall Percentage of Completion of the work done For the entire Building /Wing 80
258 Excavation 100
258 X number of Basement(s) and Plinth 100
258 X number of Slabs of Super Structure 100
258 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
258 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
258 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
258 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
258 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
258 Overall Percentage of Completion of the work done For the entire Building /Wing 80
259 Excavation 100
259 X number of Basement(s) and Plinth 100
259 X number of Slabs of Super Structure 100
259 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
259 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
259 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
259 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
259 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
259 Overall Percentage of Completion of the work done For the entire Building /Wing 80
260 Excavation 100
260 X number of Basement(s) and Plinth 100
260 X number of Slabs of Super Structure 100
260 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
260 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
260 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
260 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
260 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
260 Overall Percentage of Completion of the work done For the entire Building /Wing 80
261 Excavation 100
261 X number of Basement(s) and Plinth 100
261 X number of Slabs of Super Structure 100
261 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
261 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
261 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
261 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
261 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
261 Overall Percentage of Completion of the work done For the entire Building /Wing 80
262 Excavation 100
262 X number of Basement(s) and Plinth 100
262 X number of Slabs of Super Structure 100
262 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
262 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
262 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
262 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
262 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
262 Overall Percentage of Completion of the work done For the entire Building /Wing 80
263 Excavation 100
263 X number of Basement(s) and Plinth 100
263 X number of Slabs of Super Structure 100
263 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
263 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
263 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
263 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
263 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
263 Overall Percentage of Completion of the work done For the entire Building /Wing 80
264 Excavation 100
264 X number of Basement(s) and Plinth 100
264 X number of Slabs of Super Structure 100
264 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
264 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
264 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
264 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
264 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
264 Overall Percentage of Completion of the work done For the entire Building /Wing 80
265 Excavation 100
265 X number of Basement(s) and Plinth 100
265 X number of Slabs of Super Structure 100
265 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
265 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
265 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
265 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
265 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
265 Overall Percentage of Completion of the work done For the entire Building /Wing 80
266 Excavation 100
266 X number of Basement(s) and Plinth 100
266 X number of Slabs of Super Structure 100
266 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
266 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
266 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
266 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
266 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
266 Overall Percentage of Completion of the work done For the entire Building /Wing 80
267 Excavation 100
267 X number of Basement(s) and Plinth 100
267 X number of Slabs of Super Structure 100
267 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
267 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
267 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
267 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
267 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
267 Overall Percentage of Completion of the work done For the entire Building /Wing 80
268 Excavation 100
268 X number of Basement(s) and Plinth 100
268 X number of Slabs of Super Structure 100
268 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
268 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
268 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
268 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
268 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
268 Overall Percentage of Completion of the work done For the entire Building /Wing 80
269 Excavation 100
269 X number of Basement(s) and Plinth 100
269 X number of Slabs of Super Structure 100
269 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
269 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
269 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
269 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
269 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
269 Overall Percentage of Completion of the work done For the entire Building /Wing 80
270 Excavation 100
270 X number of Basement(s) and Plinth 100
270 X number of Slabs of Super Structure 100
270 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
270 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
270 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
270 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
270 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
270 Overall Percentage of Completion of the work done For the entire Building /Wing 80
271 Excavation 100
271 X number of Basement(s) and Plinth 100
271 X number of Slabs of Super Structure 100
271 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
271 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
271 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
271 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
271 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
271 Overall Percentage of Completion of the work done For the entire Building /Wing 80
272 Excavation 100
272 X number of Basement(s) and Plinth 100
272 X number of Slabs of Super Structure 100
272 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
272 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
272 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
272 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
272 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
272 Overall Percentage of Completion of the work done For the entire Building /Wing 80
273 Excavation 100
273 X number of Basement(s) and Plinth 100
273 X number of Slabs of Super Structure 100
273 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
273 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
273 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
273 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
273 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
273 Overall Percentage of Completion of the work done For the entire Building /Wing 80
274 Excavation 100
274 X number of Basement(s) and Plinth 100
274 X number of Slabs of Super Structure 100
274 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
274 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
274 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
274 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
274 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
274 Overall Percentage of Completion of the work done For the entire Building /Wing 80
275 Excavation 100
275 X number of Basement(s) and Plinth 100
275 X number of Slabs of Super Structure 100
275 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
275 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
275 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
275 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
275 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
275 Overall Percentage of Completion of the work done For the entire Building /Wing 80
276 Excavation 100
276 X number of Basement(s) and Plinth 100
276 X number of Slabs of Super Structure 100
276 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
276 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
276 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
276 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
276 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
276 Overall Percentage of Completion of the work done For the entire Building /Wing 80
277 Excavation 100
277 X number of Basement(s) and Plinth 100
277 X number of Slabs of Super Structure 100
277 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
277 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
277 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
277 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
277 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
277 Overall Percentage of Completion of the work done For the entire Building /Wing 80
278 Excavation 100
278 X number of Basement(s) and Plinth 100
278 X number of Slabs of Super Structure 100
278 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
278 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
278 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
278 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
278 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
278 Overall Percentage of Completion of the work done For the entire Building /Wing 80
279 Excavation 100
279 X number of Basement(s) and Plinth 100
279 X number of Slabs of Super Structure 100
279 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
279 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
279 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
279 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
279 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
279 Overall Percentage of Completion of the work done For the entire Building /Wing 80
280 Excavation 100
280 X number of Basement(s) and Plinth 100
280 X number of Slabs of Super Structure 100
280 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
280 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
280 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
280 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
280 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
280 Overall Percentage of Completion of the work done For the entire Building /Wing 80
281 Excavation 100
281 X number of Basement(s) and Plinth 100
281 X number of Slabs of Super Structure 100
281 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
281 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
281 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
281 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
281 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
281 Overall Percentage of Completion of the work done For the entire Building /Wing 80
282 Excavation 100
282 X number of Basement(s) and Plinth 100
282 X number of Slabs of Super Structure 100
282 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
282 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
282 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
282 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
282 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
282 Overall Percentage of Completion of the work done For the entire Building /Wing 80
283 Excavation 100
283 X number of Basement(s) and Plinth 100
283 X number of Slabs of Super Structure 100
283 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
283 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
283 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
283 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
283 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
283 Overall Percentage of Completion of the work done For the entire Building /Wing 80
284 Excavation 100
284 X number of Basement(s) and Plinth 100
284 X number of Slabs of Super Structure 100
284 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
284 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
284 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
284 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
284 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
284 Overall Percentage of Completion of the work done For the entire Building /Wing 80
285 Excavation 100
285 X number of Basement(s) and Plinth 100
285 X number of Slabs of Super Structure 100
285 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
285 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
285 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
285 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
285 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
285 Overall Percentage of Completion of the work done For the entire Building /Wing 80
286 Excavation 100
286 X number of Basement(s) and Plinth 100
286 X number of Slabs of Super Structure 100
286 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
286 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
286 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
286 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
286 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
286 Overall Percentage of Completion of the work done For the entire Building /Wing 80
287 Excavation 100
287 X number of Basement(s) and Plinth 100
287 X number of Slabs of Super Structure 100
287 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
287 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
287 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
287 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
287 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
287 Overall Percentage of Completion of the work done For the entire Building /Wing 80
288 Excavation 100
288 X number of Basement(s) and Plinth 100
288 X number of Slabs of Super Structure 100
288 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
288 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
288 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
288 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
288 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
288 Overall Percentage of Completion of the work done For the entire Building /Wing 80
289 Excavation 100
289 X number of Basement(s) and Plinth 100
289 X number of Slabs of Super Structure 100
289 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
289 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
289 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
289 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
289 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
289 Overall Percentage of Completion of the work done For the entire Building /Wing 80
290 Excavation 100
290 X number of Basement(s) and Plinth 100
290 X number of Slabs of Super Structure 100
290 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
290 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
290 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
290 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
290 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
290 Overall Percentage of Completion of the work done For the entire Building /Wing 80
291 Excavation 100
291 X number of Basement(s) and Plinth 100
291 X number of Slabs of Super Structure 100
291 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
291 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
291 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
291 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
291 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
291 Overall Percentage of Completion of the work done For the entire Building /Wing 80
292 Excavation 100
292 X number of Basement(s) and Plinth 100
292 X number of Slabs of Super Structure 100
292 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
292 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
292 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
292 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
292 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
292 Overall Percentage of Completion of the work done For the entire Building /Wing 80
293 Excavation 100
293 X number of Basement(s) and Plinth 100
293 X number of Slabs of Super Structure 100
293 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
293 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
293 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
293 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
293 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
293 Overall Percentage of Completion of the work done For the entire Building /Wing 80
294 Excavation 100
294 X number of Basement(s) and Plinth 100
294 X number of Slabs of Super Structure 100
294 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
294 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
294 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
294 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
294 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
294 Overall Percentage of Completion of the work done For the entire Building /Wing 80
295 Excavation 100
295 X number of Basement(s) and Plinth 100
295 X number of Slabs of Super Structure 100
295 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
295 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
295 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
295 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
295 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
295 Overall Percentage of Completion of the work done For the entire Building /Wing 80
296 Excavation 100
296 X number of Basement(s) and Plinth 100
296 X number of Slabs of Super Structure 100
296 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
296 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
296 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
296 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
296 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
296 Overall Percentage of Completion of the work done For the entire Building /Wing 80
297 Excavation 100
297 X number of Basement(s) and Plinth 100
297 X number of Slabs of Super Structure 100
297 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
297 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
297 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
297 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
297 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
297 Overall Percentage of Completion of the work done For the entire Building /Wing 80
298 Excavation 100
298 X number of Basement(s) and Plinth 100
298 X number of Slabs of Super Structure 100
298 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
298 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
298 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
298 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
298 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
298 Overall Percentage of Completion of the work done For the entire Building /Wing 80
299 Excavation 100
299 X number of Basement(s) and Plinth 100
299 X number of Slabs of Super Structure 100
299 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
299 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
299 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
299 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
299 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
299 Overall Percentage of Completion of the work done For the entire Building /Wing 80
300 Excavation 100
300 X number of Basement(s) and Plinth 100
300 X number of Slabs of Super Structure 100
300 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
300 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
300 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
300 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
300 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
300 Overall Percentage of Completion of the work done For the entire Building /Wing 80
301 Excavation 100
301 X number of Basement(s) and Plinth 100
301 X number of Slabs of Super Structure 100
301 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
301 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
301 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
301 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
301 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
301 Overall Percentage of Completion of the work done For the entire Building /Wing 80
302 Excavation 100
302 X number of Basement(s) and Plinth 100
302 X number of Slabs of Super Structure 100
302 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
302 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
302 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
302 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
302 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
302 Overall Percentage of Completion of the work done For the entire Building /Wing 80
303 Excavation 100
303 X number of Basement(s) and Plinth 100
303 X number of Slabs of Super Structure 100
303 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
303 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
303 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
303 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
303 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
303 Overall Percentage of Completion of the work done For the entire Building /Wing 80
304 Excavation 100
304 X number of Basement(s) and Plinth 100
304 X number of Slabs of Super Structure 100
304 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
304 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
304 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
304 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
304 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
304 Overall Percentage of Completion of the work done For the entire Building /Wing 80
305 Excavation 100
305 X number of Basement(s) and Plinth 100
305 X number of Slabs of Super Structure 100
305 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
305 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
305 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
305 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
305 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
305 Overall Percentage of Completion of the work done For the entire Building /Wing 80
306 Excavation 100
306 X number of Basement(s) and Plinth 100
306 X number of Slabs of Super Structure 100
306 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
306 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
306 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
306 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
306 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
306 Overall Percentage of Completion of the work done For the entire Building /Wing 80
307 Excavation 100
307 X number of Basement(s) and Plinth 100
307 X number of Slabs of Super Structure 100
307 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
307 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
307 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
307 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
307 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
307 Overall Percentage of Completion of the work done For the entire Building /Wing 80
308 Excavation 100
308 X number of Basement(s) and Plinth 100
308 X number of Slabs of Super Structure 100
308 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
308 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
308 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
308 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
308 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
308 Overall Percentage of Completion of the work done For the entire Building /Wing 80
309 Excavation 100
309 X number of Basement(s) and Plinth 100
309 X number of Slabs of Super Structure 100
309 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
309 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
309 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
309 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
309 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
309 Overall Percentage of Completion of the work done For the entire Building /Wing 80
310 Excavation 100
310 X number of Basement(s) and Plinth 100
310 X number of Slabs of Super Structure 100
310 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
310 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
310 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
310 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
310 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
310 Overall Percentage of Completion of the work done For the entire Building /Wing 80
311 Excavation 100
311 X number of Basement(s) and Plinth 100
311 X number of Slabs of Super Structure 100
311 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
311 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
311 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
311 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
311 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
311 Overall Percentage of Completion of the work done For the entire Building /Wing 80
312 Excavation 100
312 X number of Basement(s) and Plinth 100
312 Stilt Floor 100
312 X number of Slabs of Super Structure 100
312 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
312 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
312 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
312 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
312 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
312 Overall Percentage of Completion of the work done For the entire Building /Wing 90
313 Excavation 100
313 X number of Basement(s) and Plinth 100
313 X number of Slabs of Super Structure 100
313 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
313 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
313 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
313 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
313 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
313 Overall Percentage of Completion of the work done For the entire Building /Wing 80
314 Excavation 100
314 X number of Basement(s) and Plinth 100
314 X number of Slabs of Super Structure 100
314 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
314 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
314 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
314 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
314 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
314 Overall Percentage of Completion of the work done For the entire Building /Wing 80
315 Excavation 100
315 X number of Basement(s) and Plinth 100
315 X number of Slabs of Super Structure 100
315 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
315 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
315 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
315 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
315 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
315 Overall Percentage of Completion of the work done For the entire Building /Wing 80
316 Excavation 100
316 X number of Basement(s) and Plinth 100
316 X number of Slabs of Super Structure 100
316 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
316 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
316 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
316 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
316 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
316 Overall Percentage of Completion of the work done For the entire Building /Wing 80
317 Excavation 100
317 X number of Basement(s) and Plinth 100
317 X number of Slabs of Super Structure 100
317 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
317 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
317 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
317 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
317 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
317 Overall Percentage of Completion of the work done For the entire Building /Wing 80
318 Excavation 100
318 X number of Basement(s) and Plinth 100
318 X number of Slabs of Super Structure 100
318 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
318 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
318 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
318 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
318 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
318 Overall Percentage of Completion of the work done For the entire Building /Wing 80
319 Excavation 100
319 X number of Basement(s) and Plinth 100
319 X number of Slabs of Super Structure 100
319 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
319 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
319 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
319 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
319 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
319 Overall Percentage of Completion of the work done For the entire Building /Wing 80
320 Excavation 100
320 X number of Basement(s) and Plinth 100
320 X number of Slabs of Super Structure 100
320 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
320 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
320 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
320 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
320 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
320 Overall Percentage of Completion of the work done For the entire Building /Wing 80
321 Excavation 100
321 X number of Basement(s) and Plinth 100
321 X number of Slabs of Super Structure 100
321 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
321 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
321 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
321 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
321 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
321 Overall Percentage of Completion of the work done For the entire Building /Wing 80
322 Excavation 100
322 X number of Basement(s) and Plinth 100
322 X number of Slabs of Super Structure 100
322 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
322 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
322 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
322 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
322 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
322 Overall Percentage of Completion of the work done For the entire Building /Wing 80
323 Excavation 100
323 X number of Basement(s) and Plinth 100
323 X number of Slabs of Super Structure 100
323 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
323 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
323 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
323 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
323 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
323 Overall Percentage of Completion of the work done For the entire Building /Wing 80
324 Excavation 100
324 X number of Basement(s) and Plinth 100
324 X number of Slabs of Super Structure 100
324 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
324 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
324 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
324 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
324 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
324 Overall Percentage of Completion of the work done For the entire Building /Wing 80
325 Excavation 100
325 X number of Basement(s) and Plinth 100
325 X number of Slabs of Super Structure 100
325 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
325 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
325 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
325 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
325 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
325 Overall Percentage of Completion of the work done For the entire Building /Wing 80
326 Excavation 100
326 X number of Basement(s) and Plinth 100
326 X number of Slabs of Super Structure 100
326 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
326 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
326 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
326 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
326 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
326 Overall Percentage of Completion of the work done For the entire Building /Wing 80
327 Excavation 100
327 X number of Basement(s) and Plinth 100
327 X number of Slabs of Super Structure 100
327 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
327 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
327 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
327 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
327 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
327 Overall Percentage of Completion of the work done For the entire Building /Wing 80
328 Excavation 100
328 X number of Basement(s) and Plinth 100
328 X number of Slabs of Super Structure 100
328 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
328 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
328 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
328 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
328 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
328 Overall Percentage of Completion of the work done For the entire Building /Wing 80
329 Excavation 100
329 X number of Basement(s) and Plinth 100
329 X number of Slabs of Super Structure 100
329 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
329 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
329 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
329 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
329 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
329 Overall Percentage of Completion of the work done For the entire Building /Wing 80
330 Excavation 100
330 X number of Basement(s) and Plinth 100
330 X number of Slabs of Super Structure 100
330 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
330 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
330 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
330 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
330 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
330 Overall Percentage of Completion of the work done For the entire Building /Wing 80
331 Excavation 100
331 X number of Basement(s) and Plinth 100
331 X number of Slabs of Super Structure 100
331 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
331 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
331 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
331 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
331 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
331 Overall Percentage of Completion of the work done For the entire Building /Wing 80
332 Excavation 100
332 X number of Basement(s) and Plinth 100
332 X number of Slabs of Super Structure 100
332 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
332 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
332 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
332 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
332 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
332 Overall Percentage of Completion of the work done For the entire Building /Wing 80
333 Excavation 100
333 X number of Basement(s) and Plinth 100
333 X number of Slabs of Super Structure 100
333 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
333 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
333 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
333 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
333 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
333 Overall Percentage of Completion of the work done For the entire Building /Wing 80
334 Excavation 100
334 X number of Basement(s) and Plinth 100
334 X number of Slabs of Super Structure 100
334 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
334 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
334 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
334 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
334 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
334 Overall Percentage of Completion of the work done For the entire Building /Wing 80
335 Excavation 100
335 X number of Basement(s) and Plinth 100
335 X number of Slabs of Super Structure 100
335 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
335 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
335 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
335 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
335 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
335 Overall Percentage of Completion of the work done For the entire Building /Wing 80
336 Excavation 100
336 X number of Basement(s) and Plinth 100
336 X number of Slabs of Super Structure 100
336 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
336 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
336 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
336 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
336 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
336 Overall Percentage of Completion of the work done For the entire Building /Wing 80
337 Excavation 100
337 X number of Basement(s) and Plinth 100
337 X number of Slabs of Super Structure 100
337 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
337 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
337 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
337 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
337 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
337 Overall Percentage of Completion of the work done For the entire Building /Wing 80
338 Excavation 100
338 X number of Basement(s) and Plinth 100
338 X number of Slabs of Super Structure 100
338 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
338 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
338 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
338 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
338 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
338 Overall Percentage of Completion of the work done For the entire Building /Wing 80
339 Excavation 100
339 X number of Basement(s) and Plinth 100
339 X number of Slabs of Super Structure 100
339 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
339 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
339 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
339 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
339 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
339 Overall Percentage of Completion of the work done For the entire Building /Wing 80
340 Excavation 100
340 X number of Basement(s) and Plinth 100
340 X number of Slabs of Super Structure 100
340 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
340 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
340 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
340 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
340 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
340 Overall Percentage of Completion of the work done For the entire Building /Wing 80
341 Excavation 100
341 X number of Basement(s) and Plinth 100
341 X number of Slabs of Super Structure 100
341 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
341 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
341 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
341 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
341 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
341 Overall Percentage of Completion of the work done For the entire Building /Wing 80
342 Excavation 100
342 X number of Basement(s) and Plinth 100
342 X number of Slabs of Super Structure 100
342 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
342 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
342 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
342 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
342 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
342 Overall Percentage of Completion of the work done For the entire Building /Wing 80
343 Excavation 100
343 X number of Basement(s) and Plinth 100
343 X number of Slabs of Super Structure 100
343 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
343 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
343 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
343 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
343 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
343 Overall Percentage of Completion of the work done For the entire Building /Wing 80
344 Excavation 100
344 X number of Basement(s) and Plinth 100
344 X number of Slabs of Super Structure 100
344 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
344 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
344 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
344 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
344 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
344 Overall Percentage of Completion of the work done For the entire Building /Wing 80
345 Excavation 100
345 X number of Basement(s) and Plinth 100
345 X number of Slabs of Super Structure 100
345 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
345 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
345 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
345 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
345 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
345 Overall Percentage of Completion of the work done For the entire Building /Wing 80
346 Excavation 100
346 X number of Basement(s) and Plinth 100
346 X number of Slabs of Super Structure 100
346 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
346 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
346 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
346 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
346 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
346 Overall Percentage of Completion of the work done For the entire Building /Wing 80
347 Excavation 100
347 X number of Basement(s) and Plinth 100
347 X number of Slabs of Super Structure 100
347 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
347 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
347 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
347 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
347 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
347 Overall Percentage of Completion of the work done For the entire Building /Wing 80
348 Excavation 100
348 X number of Basement(s) and Plinth 100
348 X number of Slabs of Super Structure 100
348 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
348 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
348 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
348 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
348 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
348 Overall Percentage of Completion of the work done For the entire Building /Wing 80
349 Excavation 100
349 X number of Basement(s) and Plinth 100
349 X number of Slabs of Super Structure 100
349 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
349 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
349 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
349 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
349 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
349 Overall Percentage of Completion of the work done For the entire Building /Wing 80
350 Excavation 100
350 X number of Basement(s) and Plinth 100
350 X number of Slabs of Super Structure 100
350 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
350 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
350 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
350 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
350 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
350 Overall Percentage of Completion of the work done For the entire Building /Wing 80
351 Excavation 100
351 X number of Basement(s) and Plinth 100
351 X number of Slabs of Super Structure 100
351 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
351 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
351 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
351 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
351 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
351 Overall Percentage of Completion of the work done For the entire Building /Wing 80
352 Excavation 100
352 X number of Basement(s) and Plinth 100
352 X number of Slabs of Super Structure 100
352 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
352 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
352 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
352 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
352 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
352 Overall Percentage of Completion of the work done For the entire Building /Wing 80
353 Excavation 100
353 X number of Basement(s) and Plinth 100
353 X number of Slabs of Super Structure 100
353 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
353 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
353 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
353 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
353 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
353 Overall Percentage of Completion of the work done For the entire Building /Wing 80
354 Excavation 100
354 X number of Basement(s) and Plinth 100
354 X number of Slabs of Super Structure 100
354 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
354 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
354 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
354 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
354 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
354 Overall Percentage of Completion of the work done For the entire Building /Wing 80
355 Excavation 100
355 X number of Basement(s) and Plinth 100
355 X number of Slabs of Super Structure 100
355 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
355 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
355 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
355 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
355 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
355 Overall Percentage of Completion of the work done For the entire Building /Wing 80
356 Excavation 100
356 X number of Basement(s) and Plinth 100
356 X number of Slabs of Super Structure 100
356 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
356 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
356 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
356 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
356 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
356 Overall Percentage of Completion of the work done For the entire Building /Wing 80
357 Excavation 100
357 X number of Basement(s) and Plinth 100
357 X number of Slabs of Super Structure 100
357 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
357 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
357 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
357 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
357 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
357 Overall Percentage of Completion of the work done For the entire Building /Wing 80
358 Excavation 100
358 X number of Basement(s) and Plinth 100
358 X number of Slabs of Super Structure 100
358 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
358 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
358 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
358 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
358 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
358 Overall Percentage of Completion of the work done For the entire Building /Wing 80
359 Excavation 100
359 X number of Basement(s) and Plinth 100
359 X number of Slabs of Super Structure 100
359 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
359 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
359 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
359 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
359 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
359 Overall Percentage of Completion of the work done For the entire Building /Wing 80
360 Excavation 100
360 X number of Basement(s) and Plinth 100
360 X number of Slabs of Super Structure 100
360 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
360 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
360 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
360 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
360 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
360 Overall Percentage of Completion of the work done For the entire Building /Wing 80
361 Excavation 100
361 X number of Basement(s) and Plinth 100
361 X number of Slabs of Super Structure 100
361 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
361 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
361 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
361 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
361 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
361 Overall Percentage of Completion of the work done For the entire Building /Wing 80
362 Excavation 100
362 X number of Basement(s) and Plinth 100
362 X number of Slabs of Super Structure 100
362 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
362 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
362 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
362 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
362 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
362 Overall Percentage of Completion of the work done For the entire Building /Wing 80
363 Excavation 100
363 X number of Basement(s) and Plinth 100
363 X number of Slabs of Super Structure 100
363 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
363 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
363 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
363 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
363 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
363 Overall Percentage of Completion of the work done For the entire Building /Wing 80
364 Excavation 100
364 X number of Basement(s) and Plinth 100
364 X number of Slabs of Super Structure 100
364 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
364 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
364 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
364 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
364 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
364 Overall Percentage of Completion of the work done For the entire Building /Wing 80
365 Excavation 100
365 X number of Basement(s) and Plinth 100
365 X number of Slabs of Super Structure 100
365 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
365 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
365 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
365 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
365 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
365 Overall Percentage of Completion of the work done For the entire Building /Wing 80
366 Excavation 100
366 X number of Basement(s) and Plinth 100
366 X number of Slabs of Super Structure 100
366 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
366 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
366 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
366 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
366 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
366 Overall Percentage of Completion of the work done For the entire Building /Wing 80
367 Excavation 100
367 X number of Basement(s) and Plinth 100
367 X number of Slabs of Super Structure 100
367 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
367 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
367 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
367 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
367 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
367 Overall Percentage of Completion of the work done For the entire Building /Wing 80
368 Excavation 100
368 X number of Basement(s) and Plinth 100
368 X number of Slabs of Super Structure 100
368 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
368 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
368 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
368 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
368 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
368 Overall Percentage of Completion of the work done For the entire Building /Wing 80
369 Excavation 100
369 X number of Basement(s) and Plinth 100
369 X number of Slabs of Super Structure 100
369 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
369 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
369 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
369 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
369 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
369 Overall Percentage of Completion of the work done For the entire Building /Wing 80
370 Excavation 100
370 X number of Basement(s) and Plinth 100
370 X number of Slabs of Super Structure 100
370 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
370 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
370 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
370 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
370 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
370 Overall Percentage of Completion of the work done For the entire Building /Wing 80
371 Excavation 100
371 X number of Basement(s) and Plinth 100
371 X number of Slabs of Super Structure 100
371 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
371 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
371 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
371 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
371 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
371 Overall Percentage of Completion of the work done For the entire Building /Wing 80
372 Excavation 100
372 X number of Basement(s) and Plinth 100
372 X number of Slabs of Super Structure 100
372 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
372 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
372 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
372 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
372 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
372 Overall Percentage of Completion of the work done For the entire Building /Wing 80
373 Excavation 100
373 X number of Basement(s) and Plinth 100
373 X number of Slabs of Super Structure 100
373 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
373 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
373 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
373 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
373 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
373 Overall Percentage of Completion of the work done For the entire Building /Wing 80
374 Excavation 100
374 X number of Basement(s) and Plinth 100
374 X number of Slabs of Super Structure 100
374 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
374 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
374 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
374 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
374 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
374 Overall Percentage of Completion of the work done For the entire Building /Wing 80
375 Excavation 100
375 X number of Basement(s) and Plinth 100
375 X number of Slabs of Super Structure 100
375 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
375 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
375 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
375 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
375 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
375 Overall Percentage of Completion of the work done For the entire Building /Wing 80
376 Excavation 100
376 X number of Basement(s) and Plinth 100
376 X number of Slabs of Super Structure 100
376 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
376 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
376 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
376 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
376 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
376 Overall Percentage of Completion of the work done For the entire Building /Wing 80
377 Excavation 100
377 X number of Basement(s) and Plinth 100
377 X number of Slabs of Super Structure 100
377 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
377 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
377 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
377 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
377 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
377 Overall Percentage of Completion of the work done For the entire Building /Wing 80
378 Excavation 100
378 X number of Basement(s) and Plinth 100
378 X number of Slabs of Super Structure 100
378 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
378 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
378 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
378 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
378 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
378 Overall Percentage of Completion of the work done For the entire Building /Wing 80
379 Excavation 100
379 X number of Basement(s) and Plinth 100
379 X number of Slabs of Super Structure 100
379 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
379 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
379 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
379 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
379 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
379 Overall Percentage of Completion of the work done For the entire Building /Wing 80
380 Excavation 100
380 X number of Basement(s) and Plinth 100
380 X number of Slabs of Super Structure 100
380 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
380 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
380 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
380 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
380 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
380 Overall Percentage of Completion of the work done For the entire Building /Wing 80
381 Excavation 100
381 X number of Basement(s) and Plinth 100
381 X number of Slabs of Super Structure 100
381 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
381 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
381 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
381 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
381 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
381 Overall Percentage of Completion of the work done For the entire Building /Wing 80
382 Excavation 100
382 X number of Basement(s) and Plinth 100
382 X number of Slabs of Super Structure 100
382 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
382 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
382 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
382 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
382 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
382 Overall Percentage of Completion of the work done For the entire Building /Wing 80
383 Excavation 100
383 X number of Basement(s) and Plinth 100
383 X number of Slabs of Super Structure 100
383 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
383 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
383 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
383 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
383 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
383 Overall Percentage of Completion of the work done For the entire Building /Wing 80
384 Excavation 100
384 X number of Basement(s) and Plinth 100
384 X number of Slabs of Super Structure 100
384 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
384 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
384 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
384 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
384 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
384 Overall Percentage of Completion of the work done For the entire Building /Wing 80
385 Excavation 100
385 X number of Basement(s) and Plinth 100
385 X number of Slabs of Super Structure 100
385 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
385 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
385 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
385 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
385 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
385 Overall Percentage of Completion of the work done For the entire Building /Wing 80
386 Excavation 100
386 X number of Basement(s) and Plinth 100
386 X number of Slabs of Super Structure 100
386 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
386 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
386 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
386 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
386 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
386 Overall Percentage of Completion of the work done For the entire Building /Wing 80
387 Excavation 100
387 X number of Basement(s) and Plinth 100
387 X number of Slabs of Super Structure 100
387 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
387 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
387 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
387 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
387 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
387 Overall Percentage of Completion of the work done For the entire Building /Wing 80
388 Excavation 100
388 X number of Basement(s) and Plinth 100
388 X number of Slabs of Super Structure 100
388 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
388 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
388 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
388 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
388 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
388 Overall Percentage of Completion of the work done For the entire Building /Wing 80
391 Excavation 100
391 X number of Basement(s) and Plinth 100
391 X number of Slabs of Super Structure 100
391 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
391 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
391 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
391 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
391 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
391 Overall Percentage of Completion of the work done For the entire Building /Wing 80
392 Excavation 100
392 X number of Basement(s) and Plinth 100
392 X number of Slabs of Super Structure 100
392 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
392 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
392 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
392 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
392 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
392 Overall Percentage of Completion of the work done For the entire Building /Wing 80
393 Excavation 100
393 X number of Basement(s) and Plinth 100
393 X number of Slabs of Super Structure 100
393 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
393 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
393 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
393 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
393 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
393 Overall Percentage of Completion of the work done For the entire Building /Wing 80
394 Excavation 100
394 X number of Basement(s) and Plinth 100
394 X number of Slabs of Super Structure 100
394 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
394 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
394 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
394 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
394 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
394 Overall Percentage of Completion of the work done For the entire Building /Wing 80
395 Excavation 100
395 X number of Basement(s) and Plinth 100
395 X number of Slabs of Super Structure 100
395 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
395 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
395 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
395 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
395 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
395 Overall Percentage of Completion of the work done For the entire Building /Wing 80
396 Excavation 100
396 X number of Basement(s) and Plinth 100
396 X number of Slabs of Super Structure 100
396 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
396 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
396 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
396 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
396 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
396 Overall Percentage of Completion of the work done For the entire Building /Wing 80
397 Excavation 100
397 X number of Basement(s) and Plinth 100
397 X number of Slabs of Super Structure 100
397 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
397 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
397 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
397 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
397 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
397 Overall Percentage of Completion of the work done For the entire Building /Wing 80
398 Excavation 100
398 X number of Basement(s) and Plinth 100
398 X number of Slabs of Super Structure 100
398 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
398 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
398 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
398 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
398 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
398 Overall Percentage of Completion of the work done For the entire Building /Wing 80
399 Excavation 100
399 X number of Basement(s) and Plinth 100
399 X number of Slabs of Super Structure 100
399 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
399 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
399 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
399 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
399 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
399 Overall Percentage of Completion of the work done For the entire Building /Wing 80
400 Excavation 100
400 X number of Basement(s) and Plinth 100
400 X number of Slabs of Super Structure 100
400 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
400 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
400 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
400 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
400 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
400 Overall Percentage of Completion of the work done For the entire Building /Wing 80
401 Excavation 100
401 X number of Basement(s) and Plinth 100
401 X number of Slabs of Super Structure 100
401 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
401 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
401 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
401 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
401 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
401 Overall Percentage of Completion of the work done For the entire Building /Wing 80
402 Excavation 100
402 X number of Basement(s) and Plinth 100
402 X number of Slabs of Super Structure 100
402 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
402 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
402 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
402 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
402 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
402 Overall Percentage of Completion of the work done For the entire Building /Wing 80
403 Excavation 100
403 X number of Basement(s) and Plinth 100
403 X number of Slabs of Super Structure 100
403 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
403 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
403 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
403 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
403 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
403 Overall Percentage of Completion of the work done For the entire Building /Wing 80
404 Excavation 100
404 X number of Basement(s) and Plinth 100
404 X number of Slabs of Super Structure 100
404 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
404 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
404 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
404 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
404 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
404 Overall Percentage of Completion of the work done For the entire Building /Wing 80
405 Excavation 100
405 X number of Basement(s) and Plinth 100
405 X number of Slabs of Super Structure 100
405 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
405 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
405 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
405 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
405 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
405 Overall Percentage of Completion of the work done For the entire Building /Wing 80
406 Excavation 100
406 X number of Basement(s) and Plinth 100
406 X number of Slabs of Super Structure 100
406 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
406 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
406 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
406 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
406 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
406 Overall Percentage of Completion of the work done For the entire Building /Wing 80
407 Excavation 100
407 X number of Basement(s) and Plinth 100
407 X number of Slabs of Super Structure 100
407 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
407 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
407 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
407 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
407 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
407 Overall Percentage of Completion of the work done For the entire Building /Wing 80
408 Excavation 100
408 X number of Basement(s) and Plinth 100
408 X number of Slabs of Super Structure 100
408 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
408 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
408 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
408 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
408 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
408 Overall Percentage of Completion of the work done For the entire Building /Wing 80
409 Excavation 100
409 X number of Basement(s) and Plinth 100
409 X number of Slabs of Super Structure 100
409 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
409 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
409 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
409 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
409 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
409 Overall Percentage of Completion of the work done For the entire Building /Wing 80
410 Excavation 100
410 X number of Basement(s) and Plinth 100
410 X number of Slabs of Super Structure 100
410 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
410 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
410 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
410 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
410 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
410 Overall Percentage of Completion of the work done For the entire Building /Wing 80
411 Excavation 100
411 X number of Basement(s) and Plinth 100
411 X number of Slabs of Super Structure 100
411 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
411 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
411 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
411 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
411 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
411 Overall Percentage of Completion of the work done For the entire Building /Wing 80
412 Excavation 100
412 X number of Basement(s) and Plinth 100
412 X number of Slabs of Super Structure 100
412 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
412 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
412 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
412 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
412 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
412 Overall Percentage of Completion of the work done For the entire Building /Wing 80
413 Excavation 100
413 X number of Basement(s) and Plinth 100
413 X number of Slabs of Super Structure 100
413 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
413 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
413 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
413 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
413 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
413 Overall Percentage of Completion of the work done For the entire Building /Wing 80
414 Excavation 100
414 X number of Basement(s) and Plinth 100
414 X number of Slabs of Super Structure 100
414 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
414 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
414 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
414 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
414 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
414 Overall Percentage of Completion of the work done For the entire Building /Wing 80
415 Excavation 100
415 X number of Basement(s) and Plinth 100
415 X number of Slabs of Super Structure 100
415 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
415 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
415 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
415 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
415 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
415 Overall Percentage of Completion of the work done For the entire Building /Wing 80
416 Excavation 100
416 X number of Basement(s) and Plinth 100
416 X number of Slabs of Super Structure 100
416 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
416 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
416 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
416 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
416 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
416 Overall Percentage of Completion of the work done For the entire Building /Wing 80
417 Excavation 100
417 X number of Basement(s) and Plinth 100
417 X number of Slabs of Super Structure 100
417 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
417 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
417 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
417 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
417 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
417 Overall Percentage of Completion of the work done For the entire Building /Wing 80
418 Excavation 100
418 X number of Basement(s) and Plinth 100
418 X number of Slabs of Super Structure 100
418 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
418 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
418 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
418 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
418 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
418 Overall Percentage of Completion of the work done For the entire Building /Wing 80
419 Excavation 100
419 X number of Basement(s) and Plinth 100
419 X number of Slabs of Super Structure 100
419 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
419 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
419 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
419 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
419 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
419 Overall Percentage of Completion of the work done For the entire Building /Wing 80
420 Excavation 100
420 X number of Basement(s) and Plinth 100
420 X number of Slabs of Super Structure 100
420 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
420 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
420 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
420 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
420 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
420 Overall Percentage of Completion of the work done For the entire Building /Wing 80
421 Excavation 100
421 X number of Basement(s) and Plinth 100
421 X number of Slabs of Super Structure 100
421 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
421 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
421 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
421 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
421 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
421 Overall Percentage of Completion of the work done For the entire Building /Wing 80
422 Excavation 100
422 X number of Basement(s) and Plinth 100
422 X number of Slabs of Super Structure 100
422 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
422 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
422 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
422 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
422 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
422 Overall Percentage of Completion of the work done For the entire Building /Wing 80
423 Excavation 100
423 X number of Basement(s) and Plinth 100
423 X number of Slabs of Super Structure 100
423 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
423 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
423 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
423 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
423 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
423 Overall Percentage of Completion of the work done For the entire Building /Wing 80
424 Excavation 100
424 X number of Basement(s) and Plinth 100
424 X number of Slabs of Super Structure 100
424 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
424 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
424 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
424 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
424 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
424 Overall Percentage of Completion of the work done For the entire Building /Wing 80
425 Excavation 100
425 X number of Basement(s) and Plinth 100
425 X number of Slabs of Super Structure 100
425 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
425 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
425 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
425 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
425 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
425 Overall Percentage of Completion of the work done For the entire Building /Wing 80
426 Excavation 100
426 X number of Basement(s) and Plinth 100
426 X number of Slabs of Super Structure 100
426 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
426 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
426 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
426 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
426 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
426 Overall Percentage of Completion of the work done For the entire Building /Wing 80
427 Excavation 100
427 X number of Basement(s) and Plinth 100
427 X number of Slabs of Super Structure 100
427 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
427 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
427 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
427 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
427 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
427 Overall Percentage of Completion of the work done For the entire Building /Wing 80
428 Excavation 100
428 X number of Basement(s) and Plinth 100
428 X number of Slabs of Super Structure 100
428 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
428 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
428 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
428 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
428 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
428 Overall Percentage of Completion of the work done For the entire Building /Wing 80
429 Excavation 100
429 X number of Basement(s) and Plinth 100
429 X number of Slabs of Super Structure 100
429 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
429 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
429 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
429 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
429 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
429 Overall Percentage of Completion of the work done For the entire Building /Wing 80
430 Excavation 100
430 X number of Basement(s) and Plinth 100
430 X number of Slabs of Super Structure 100
430 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
430 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
430 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
430 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
430 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
430 Overall Percentage of Completion of the work done For the entire Building /Wing 80
431 Excavation 100
431 X number of Basement(s) and Plinth 100
431 X number of Slabs of Super Structure 100
431 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
431 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
431 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
431 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
431 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
431 Overall Percentage of Completion of the work done For the entire Building /Wing 80
432 Excavation 100
432 X number of Basement(s) and Plinth 100
432 X number of Slabs of Super Structure 100
432 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
432 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
432 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
432 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
432 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
432 Overall Percentage of Completion of the work done For the entire Building /Wing 80
433 Excavation 100
433 X number of Basement(s) and Plinth 100
433 X number of Slabs of Super Structure 100
433 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
433 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
433 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
433 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
433 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
433 Overall Percentage of Completion of the work done For the entire Building /Wing 80
434 Excavation 100
434 X number of Basement(s) and Plinth 100
434 X number of Slabs of Super Structure 100
434 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
434 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
434 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
434 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
434 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
434 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.94 15958 10945

 

New documents listed below were uploaded to the Documents section:

  • 21 Building Plan Approval (IOD)
  • 22 Building Plan Approval (IOD)
  • 23 Building Plan Approval (IOD)
  • 24 Building Plan Approval (IOD)
  • 25 Building Plan Approval (IOD)
  • 26 Building Plan Approval (IOD)
  • 27 Building Plan Approval (IOD)
  • 19 Copy of Layout Approval (in case of layout)
  • 1 Other – Legal
  • 1 Other – Finance
  • 13 Copy of Layout Approval (in case of layout)
  • 14 Copy of Layout Approval (in case of layout)
  • 15 Copy of Layout Approval (in case of layout)
  • 16 Copy of Layout Approval (in case of layout)
  • 17 Copy of Layout Approval (in case of layout)
  • 18 Copy of Layout Approval (in case of layout)
  • 31 Commencement Certificates / NA Order for plotted development
  • 32 Commencement Certificates / NA Order for plotted development
  • 33 Commencement Certificates / NA Order for plotted development
  • 30 Commencement Certificates / NA Order for plotted development
  • 29 Commencement Certificates / NA Order for plotted development
  • 28 Commencement Certificates / NA Order for plotted development
  • 27 Commencement Certificates / NA Order for plotted development
  • 24 Commencement Certificates / NA Order for plotted development
  • 25 Commencement Certificates / NA Order for plotted development
  • 26 Commencement Certificates / NA Order for plotted development
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • 1 CERSAI details
  • 3 Disclosure of Interest in Other Real Estate Organizations
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 37 Commencement Certificates / NA Order for plotted development
  • 36 Commencement Certificates / NA Order for plotted development
  • 38 Commencement Certificates / NA Order for plotted development
  • 35 Commencement Certificates / NA Order for plotted development
  • 34 Commencement Certificates / NA Order for plotted development
  • 39 Commencement Certificates / NA Order for plotted development

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Prakarsh Sangave Engineer
Parag Rane Architect

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.94 15958 9348

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.34 36 35
1BHK 27.94 15958 7230

 

Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) field under Building/Plot Details section updated with new value 15994

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Pravin Deodhar Architect

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 80
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
3 Overall Percentage of Completion of the work done For the entire Building /Wing 80
4 Excavation 100
4 X number of Basement(s) and Plinth 100
4 X number of Slabs of Super Structure 100
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
4 Overall Percentage of Completion of the work done For the entire Building /Wing 80
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
5 Overall Percentage of Completion of the work done For the entire Building /Wing 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
6 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
6 Overall Percentage of Completion of the work done For the entire Building /Wing 80
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
7 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
7 Overall Percentage of Completion of the work done For the entire Building /Wing 80
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
8 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
8 Overall Percentage of Completion of the work done For the entire Building /Wing 80
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
9 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
9 Overall Percentage of Completion of the work done For the entire Building /Wing 80
10 X number of Basement(s) and Plinth 100
10 X number of Slabs of Super Structure 100
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
10 Overall Percentage of Completion of the work done For the entire Building /Wing 80
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
11 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
12 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
12 Overall Percentage of Completion of the work done For the entire Building /Wing 80
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
13 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
13 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
13 Overall Percentage of Completion of the work done For the entire Building /Wing 80
14 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
14 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
14 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
14 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
14 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
14 Overall Percentage of Completion of the work done For the entire Building /Wing 80
15 Excavation 100
15 X number of Basement(s) and Plinth 100
15 X number of Slabs of Super Structure 100
15 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
15 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
15 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
15 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
15 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
15 Overall Percentage of Completion of the work done For the entire Building /Wing 80
16 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
16 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
16 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
16 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
16 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
16 Overall Percentage of Completion of the work done For the entire Building /Wing 80
17 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
17 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
17 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
17 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
17 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
17 Overall Percentage of Completion of the work done For the entire Building /Wing 80
18 X number of Basement(s) and Plinth 100
18 X number of Slabs of Super Structure 100
18 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
18 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
18 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
18 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
18 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
18 Overall Percentage of Completion of the work done For the entire Building /Wing 80
19 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
19 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
19 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
19 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
19 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
19 Overall Percentage of Completion of the work done For the entire Building /Wing 80
20 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
20 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
20 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
20 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
20 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
20 Overall Percentage of Completion of the work done For the entire Building /Wing 80
21 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
21 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
21 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
21 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
21 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
21 Overall Percentage of Completion of the work done For the entire Building /Wing 80
22 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
22 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
22 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
22 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
22 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
22 Overall Percentage of Completion of the work done For the entire Building /Wing 80
23 X number of Basement(s) and Plinth 100
23 X number of Slabs of Super Structure 100
23 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
23 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
23 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
23 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
23 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
23 Overall Percentage of Completion of the work done For the entire Building /Wing 80
24 X number of Basement(s) and Plinth 100
24 X number of Slabs of Super Structure 100
24 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
24 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
24 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
24 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
24 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
24 Overall Percentage of Completion of the work done For the entire Building /Wing 80
25 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
25 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
25 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
25 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
25 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
25 Overall Percentage of Completion of the work done For the entire Building /Wing 80
26 Excavation 100
26 X number of Basement(s) and Plinth 100
26 X number of Slabs of Super Structure 100
26 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
26 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
26 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
26 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
26 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
26 Overall Percentage of Completion of the work done For the entire Building /Wing 80
27 Excavation 100
27 X number of Basement(s) and Plinth 100
27 X number of Slabs of Super Structure 100
27 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
27 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
27 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
27 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
27 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
27 Overall Percentage of Completion of the work done For the entire Building /Wing 80
28 Excavation 100
28 X number of Basement(s) and Plinth 100
28 X number of Slabs of Super Structure 100
28 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
28 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
28 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
28 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
28 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
28 Overall Percentage of Completion of the work done For the entire Building /Wing 80
29 Excavation 100
29 X number of Basement(s) and Plinth 100
29 X number of Slabs of Super Structure 100
29 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
29 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
29 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
29 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
29 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
29 Overall Percentage of Completion of the work done For the entire Building /Wing 80
30 Excavation 100
30 X number of Basement(s) and Plinth 100
30 X number of Slabs of Super Structure 100
30 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
30 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
30 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
30 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
30 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
30 Overall Percentage of Completion of the work done For the entire Building /Wing 80
31 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
31 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
31 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
31 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
31 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
31 Overall Percentage of Completion of the work done For the entire Building /Wing 80
32 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
32 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
32 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
32 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
32 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
32 Overall Percentage of Completion of the work done For the entire Building /Wing 80
33 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
33 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
33 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
33 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
33 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
33 Overall Percentage of Completion of the work done For the entire Building /Wing 80
34 Excavation 100
34 X number of Basement(s) and Plinth 100
34 X number of Slabs of Super Structure 100
34 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
34 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
34 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
34 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
34 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
34 Overall Percentage of Completion of the work done For the entire Building /Wing 80
35 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
35 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
35 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
35 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
35 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
35 Overall Percentage of Completion of the work done For the entire Building /Wing 80
36 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
36 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
36 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
36 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
36 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
36 Overall Percentage of Completion of the work done For the entire Building /Wing 80
37 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
37 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
37 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
37 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
37 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
37 Overall Percentage of Completion of the work done For the entire Building /Wing 80
38 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
38 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
38 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
38 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
38 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
38 Overall Percentage of Completion of the work done For the entire Building /Wing 80
39 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
39 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
39 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
39 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
39 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
39 Overall Percentage of Completion of the work done For the entire Building /Wing 80
40 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
40 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
40 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
40 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
40 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
40 Overall Percentage of Completion of the work done For the entire Building /Wing 80
41 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
41 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
41 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
41 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
41 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
41 Overall Percentage of Completion of the work done For the entire Building /Wing 80
42 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
42 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
42 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
42 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
42 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
42 Overall Percentage of Completion of the work done For the entire Building /Wing 80
43 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
43 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
43 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
43 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
43 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
43 Overall Percentage of Completion of the work done For the entire Building /Wing 80
44 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
44 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
44 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
44 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
44 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
44 Overall Percentage of Completion of the work done For the entire Building /Wing 80
45 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
45 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
45 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
45 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
45 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
45 Overall Percentage of Completion of the work done For the entire Building /Wing 80
46 X number of Slabs of Super Structure 100
46 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
46 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
46 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
46 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
46 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
46 Overall Percentage of Completion of the work done For the entire Building /Wing 80
47 X number of Slabs of Super Structure 100
47 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
47 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
47 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
47 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
47 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
47 Overall Percentage of Completion of the work done For the entire Building /Wing 80
48 X number of Slabs of Super Structure 100
48 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
48 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
48 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
48 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
48 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
48 Overall Percentage of Completion of the work done For the entire Building /Wing 80
49 X number of Slabs of Super Structure 100
49 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
49 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
49 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
49 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
49 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
49 Overall Percentage of Completion of the work done For the entire Building /Wing 80
50 X number of Slabs of Super Structure 100
50 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
50 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
50 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
50 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
50 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
50 Overall Percentage of Completion of the work done For the entire Building /Wing 80
51 X number of Slabs of Super Structure 100
51 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
51 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
51 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
51 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
51 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
51 Overall Percentage of Completion of the work done For the entire Building /Wing 80
52 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
52 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
52 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
52 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
52 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
52 Overall Percentage of Completion of the work done For the entire Building /Wing 80
53 Excavation 100
53 X number of Basement(s) and Plinth 100
53 X number of Slabs of Super Structure 100
53 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
53 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
53 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
53 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
53 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
53 Overall Percentage of Completion of the work done For the entire Building /Wing 80
54 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
54 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
54 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
54 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
54 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
54 Overall Percentage of Completion of the work done For the entire Building /Wing 80
55 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
55 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
55 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
55 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
55 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
55 Overall Percentage of Completion of the work done For the entire Building /Wing 80
56 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
56 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
56 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
56 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
56 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
56 Overall Percentage of Completion of the work done For the entire Building /Wing 80
57 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
57 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
57 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
57 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
57 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
57 Overall Percentage of Completion of the work done For the entire Building /Wing 80
58 X number of Slabs of Super Structure 100
58 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
58 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
58 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
58 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
58 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
58 Overall Percentage of Completion of the work done For the entire Building /Wing 80
59 Excavation 100
59 X number of Basement(s) and Plinth 100
59 X number of Slabs of Super Structure 100
59 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
59 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
59 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
59 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
59 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
59 Overall Percentage of Completion of the work done For the entire Building /Wing 80
60 X number of Slabs of Super Structure 100
60 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
60 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
60 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
60 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
60 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
60 Overall Percentage of Completion of the work done For the entire Building /Wing 80
61 X number of Slabs of Super Structure 100
61 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
61 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
61 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
61 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
61 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
61 Overall Percentage of Completion of the work done For the entire Building /Wing 80
62 X number of Slabs of Super Structure 100
62 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
62 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
62 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
62 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
62 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
62 Overall Percentage of Completion of the work done For the entire Building /Wing 80
63 X number of Slabs of Super Structure 100
63 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
63 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
63 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
63 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
63 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
63 Overall Percentage of Completion of the work done For the entire Building /Wing 80
64 X number of Slabs of Super Structure 100
64 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
64 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
64 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
64 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
64 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
64 Overall Percentage of Completion of the work done For the entire Building /Wing 80
65 X number of Slabs of Super Structure 100
65 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
65 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
65 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
65 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
65 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
65 Overall Percentage of Completion of the work done For the entire Building /Wing 80
66 X number of Slabs of Super Structure 100
66 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
66 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
66 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
66 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
66 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
66 Overall Percentage of Completion of the work done For the entire Building /Wing 80
67 X number of Slabs of Super Structure 100
67 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
67 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
67 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
67 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
67 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
67 Overall Percentage of Completion of the work done For the entire Building /Wing 80
68 X number of Slabs of Super Structure 100
68 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
68 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
68 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
68 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
68 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
68 Overall Percentage of Completion of the work done For the entire Building /Wing 80
69 X number of Slabs of Super Structure 100
69 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
69 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
69 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
69 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
69 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
69 Overall Percentage of Completion of the work done For the entire Building /Wing 80
72 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
72 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
72 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
72 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
72 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
72 Overall Percentage of Completion of the work done For the entire Building /Wing 80
73 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
73 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
73 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
73 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
73 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
73 Overall Percentage of Completion of the work done For the entire Building /Wing 80
74 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
74 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
74 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
74 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
74 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
74 Overall Percentage of Completion of the work done For the entire Building /Wing 80
75 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
75 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
75 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
75 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
75 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
75 Overall Percentage of Completion of the work done For the entire Building /Wing 80
76 X number of Slabs of Super Structure 100
76 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
76 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
76 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
76 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
76 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
76 Overall Percentage of Completion of the work done For the entire Building /Wing 80
77 X number of Slabs of Super Structure 100
77 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
77 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
77 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
77 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
77 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
77 Overall Percentage of Completion of the work done For the entire Building /Wing 80
78 X number of Slabs of Super Structure 100
78 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
78 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
78 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
78 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
78 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
78 Overall Percentage of Completion of the work done For the entire Building /Wing 80
79 Excavation 100
79 X number of Basement(s) and Plinth 100
79 X number of Slabs of Super Structure 100
79 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
79 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
79 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
79 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
79 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
79 Overall Percentage of Completion of the work done For the entire Building /Wing 80
80 Excavation 100
80 X number of Basement(s) and Plinth 100
80 X number of Slabs of Super Structure 100
80 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
80 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
80 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
80 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
80 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
80 Overall Percentage of Completion of the work done For the entire Building /Wing 80
81 Excavation 100
81 X number of Basement(s) and Plinth 100
81 X number of Slabs of Super Structure 100
81 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
81 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
81 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
81 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
81 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
81 Overall Percentage of Completion of the work done For the entire Building /Wing 80
82 Excavation 100
82 X number of Basement(s) and Plinth 100
82 X number of Slabs of Super Structure 100
82 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
82 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
82 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
82 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
82 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
82 Overall Percentage of Completion of the work done For the entire Building /Wing 80
83 Excavation 100
83 X number of Basement(s) and Plinth 100
83 X number of Slabs of Super Structure 100
83 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
83 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
83 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
83 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
83 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
83 Overall Percentage of Completion of the work done For the entire Building /Wing 80
84 Excavation 100
84 X number of Basement(s) and Plinth 100
84 X number of Slabs of Super Structure 100
84 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
84 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
84 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
84 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
84 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
84 Overall Percentage of Completion of the work done For the entire Building /Wing 80
85 Excavation 100
85 X number of Basement(s) and Plinth 100
85 X number of Slabs of Super Structure 100
85 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
85 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
85 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
85 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
85 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
85 Overall Percentage of Completion of the work done For the entire Building /Wing 80
86 Excavation 100
86 X number of Basement(s) and Plinth 100
86 X number of Slabs of Super Structure 100
86 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
86 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
86 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
86 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
86 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
86 Overall Percentage of Completion of the work done For the entire Building /Wing 80
87 Excavation 100
87 X number of Basement(s) and Plinth 100
87 X number of Slabs of Super Structure 100
87 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
87 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
87 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
87 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
87 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
87 Overall Percentage of Completion of the work done For the entire Building /Wing 80
88 Excavation 100
88 X number of Basement(s) and Plinth 100
88 X number of Slabs of Super Structure 100
88 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
88 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
88 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
88 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
88 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
88 Overall Percentage of Completion of the work done For the entire Building /Wing 80
89 Excavation 100
89 X number of Basement(s) and Plinth 100
89 X number of Slabs of Super Structure 100
89 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
89 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
89 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
89 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
89 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
89 Overall Percentage of Completion of the work done For the entire Building /Wing 80
90 Excavation 100
90 X number of Basement(s) and Plinth 100
90 X number of Slabs of Super Structure 100
90 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
90 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
90 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
90 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
90 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
90 Overall Percentage of Completion of the work done For the entire Building /Wing 80
91 X number of Slabs of Super Structure 100
91 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
91 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
91 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
91 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
91 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
91 Overall Percentage of Completion of the work done For the entire Building /Wing 80
92 X number of Slabs of Super Structure 100
92 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
92 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
92 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
92 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
92 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
92 Overall Percentage of Completion of the work done For the entire Building /Wing 80
93 X number of Slabs of Super Structure 100
93 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
93 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
93 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
93 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
93 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
93 Overall Percentage of Completion of the work done For the entire Building /Wing 80
94 X number of Slabs of Super Structure 100
94 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
94 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
94 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
94 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
94 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
94 Overall Percentage of Completion of the work done For the entire Building /Wing 80
95 X number of Slabs of Super Structure 100
95 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
95 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
95 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
95 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
95 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
95 Overall Percentage of Completion of the work done For the entire Building /Wing 80
96 X number of Slabs of Super Structure 100
96 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
96 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
96 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
96 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
96 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
96 Overall Percentage of Completion of the work done For the entire Building /Wing 80
97 X number of Slabs of Super Structure 100
97 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
97 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
97 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
97 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
97 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
97 Overall Percentage of Completion of the work done For the entire Building /Wing 80
98 X number of Slabs of Super Structure 100
98 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
98 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
98 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
98 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
98 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
98 Overall Percentage of Completion of the work done For the entire Building /Wing 80
99 X number of Slabs of Super Structure 100
99 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
99 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
99 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
99 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
99 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
99 Overall Percentage of Completion of the work done For the entire Building /Wing 80
100 X number of Slabs of Super Structure 100
100 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
100 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
100 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
100 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
100 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
100 Overall Percentage of Completion of the work done For the entire Building /Wing 80
101 X number of Slabs of Super Structure 100
101 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
101 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
101 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
101 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
101 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
101 Overall Percentage of Completion of the work done For the entire Building /Wing 80
102 X number of Slabs of Super Structure 100
102 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
102 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
102 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
102 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
102 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
102 Overall Percentage of Completion of the work done For the entire Building /Wing 80
103 X number of Slabs of Super Structure 100
103 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
103 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
103 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
103 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
103 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
103 Overall Percentage of Completion of the work done For the entire Building /Wing 80
104 X number of Slabs of Super Structure 100
104 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
104 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
104 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
104 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
104 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
104 Overall Percentage of Completion of the work done For the entire Building /Wing 80
105 X number of Slabs of Super Structure 100
105 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
105 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
105 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
105 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
105 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
105 Overall Percentage of Completion of the work done For the entire Building /Wing 80
106 X number of Slabs of Super Structure 100
106 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
106 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
106 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
106 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
106 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
106 Overall Percentage of Completion of the work done For the entire Building /Wing 80
107 X number of Slabs of Super Structure 100
107 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
107 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
107 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
107 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
107 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
107 Overall Percentage of Completion of the work done For the entire Building /Wing 80
108 X number of Slabs of Super Structure 100
108 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
108 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
108 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
108 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
108 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
108 Overall Percentage of Completion of the work done For the entire Building /Wing 80
109 X number of Slabs of Super Structure 100
109 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
109 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
109 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
109 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
109 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
109 Overall Percentage of Completion of the work done For the entire Building /Wing 80
110 X number of Slabs of Super Structure 100
110 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
110 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
110 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
110 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
110 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
110 Overall Percentage of Completion of the work done For the entire Building /Wing 80
111 X number of Slabs of Super Structure 100
111 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
111 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
111 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
111 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
111 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
111 Overall Percentage of Completion of the work done For the entire Building /Wing 80
112 X number of Slabs of Super Structure 100
112 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
112 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
112 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
112 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
112 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
112 Overall Percentage of Completion of the work done For the entire Building /Wing 80
113 X number of Slabs of Super Structure 100
113 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
113 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
113 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
113 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
113 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
113 Overall Percentage of Completion of the work done For the entire Building /Wing 80
114 X number of Slabs of Super Structure 100
114 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
114 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
114 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
114 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
114 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
114 Overall Percentage of Completion of the work done For the entire Building /Wing 80
115 Excavation 100
115 X number of Basement(s) and Plinth 100
115 X number of Slabs of Super Structure 100
115 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
115 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
115 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
115 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
115 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
115 Overall Percentage of Completion of the work done For the entire Building /Wing 80
116 Excavation 100
116 X number of Basement(s) and Plinth 100
116 X number of Slabs of Super Structure 100
116 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
116 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
116 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
116 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
116 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
116 Overall Percentage of Completion of the work done For the entire Building /Wing 80
117 X number of Slabs of Super Structure 100
117 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
117 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
117 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
117 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
117 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
117 Overall Percentage of Completion of the work done For the entire Building /Wing 80
118 X number of Slabs of Super Structure 100
118 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
118 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
118 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
118 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
118 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
118 Overall Percentage of Completion of the work done For the entire Building /Wing 80
119 X number of Slabs of Super Structure 100
119 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
119 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
119 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
119 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
119 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
119 Overall Percentage of Completion of the work done For the entire Building /Wing 80
120 X number of Slabs of Super Structure 100
120 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
120 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
120 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
120 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
120 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
120 Overall Percentage of Completion of the work done For the entire Building /Wing 80
121 X number of Slabs of Super Structure 100
121 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
121 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
121 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
121 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
121 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
121 Overall Percentage of Completion of the work done For the entire Building /Wing 80
122 X number of Slabs of Super Structure 100
122 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
122 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
122 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
122 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
122 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
122 Overall Percentage of Completion of the work done For the entire Building /Wing 80
123 X number of Slabs of Super Structure 100
123 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
123 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
123 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
123 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
123 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
123 Overall Percentage of Completion of the work done For the entire Building /Wing 80
124 X number of Slabs of Super Structure 100
124 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
124 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
124 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
124 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
124 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
124 Overall Percentage of Completion of the work done For the entire Building /Wing 80
125 X number of Slabs of Super Structure 100
125 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
125 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
125 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
125 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
125 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
125 Overall Percentage of Completion of the work done For the entire Building /Wing 80
126 X number of Slabs of Super Structure 100
126 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
126 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
126 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
126 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
126 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
126 Overall Percentage of Completion of the work done For the entire Building /Wing 80
127 X number of Slabs of Super Structure 100
127 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
127 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
127 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
127 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
127 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
127 Overall Percentage of Completion of the work done For the entire Building /Wing 80
128 Excavation 100
128 X number of Basement(s) and Plinth 100
128 X number of Slabs of Super Structure 100
128 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
128 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
128 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
128 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
128 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
128 Overall Percentage of Completion of the work done For the entire Building /Wing 80
129 X number of Slabs of Super Structure 100
129 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
129 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
129 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
129 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
129 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
129 Overall Percentage of Completion of the work done For the entire Building /Wing 80
130 X number of Slabs of Super Structure 100
130 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
130 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
130 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
130 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
130 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
130 Overall Percentage of Completion of the work done For the entire Building /Wing 80
131 X number of Slabs of Super Structure 100
131 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
131 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
131 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
131 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
131 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
131 Overall Percentage of Completion of the work done For the entire Building /Wing 80
132 X number of Slabs of Super Structure 100
132 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
132 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
132 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
132 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
132 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
132 Overall Percentage of Completion of the work done For the entire Building /Wing 80
133 X number of Slabs of Super Structure 100
133 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
133 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
133 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
133 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
133 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
133 Overall Percentage of Completion of the work done For the entire Building /Wing 80
134 X number of Slabs of Super Structure 100
134 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
134 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
134 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
134 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
134 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
134 Overall Percentage of Completion of the work done For the entire Building /Wing 80
135 X number of Slabs of Super Structure 100
135 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
135 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
135 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
135 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
135 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
135 Overall Percentage of Completion of the work done For the entire Building /Wing 80
136 X number of Slabs of Super Structure 100
136 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
136 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
136 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
136 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
136 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
136 Overall Percentage of Completion of the work done For the entire Building /Wing 80
137 X number of Slabs of Super Structure 100
137 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
137 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
137 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
137 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
137 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
137 Overall Percentage of Completion of the work done For the entire Building /Wing 80
138 X number of Slabs of Super Structure 100
138 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
138 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
138 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
138 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
138 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
138 Overall Percentage of Completion of the work done For the entire Building /Wing 80
139 X number of Slabs of Super Structure 100
139 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
139 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
139 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
139 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
139 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
139 Overall Percentage of Completion of the work done For the entire Building /Wing 80
140 X number of Slabs of Super Structure 100
140 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
140 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
140 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
140 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
140 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
140 Overall Percentage of Completion of the work done For the entire Building /Wing 80
141 X number of Slabs of Super Structure 100
141 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
141 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
141 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
141 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
141 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
141 Overall Percentage of Completion of the work done For the entire Building /Wing 80
142 X number of Slabs of Super Structure 100
142 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
142 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
142 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
142 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
142 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
142 Overall Percentage of Completion of the work done For the entire Building /Wing 80
143 X number of Slabs of Super Structure 100
143 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
143 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
143 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
143 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
143 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
143 Overall Percentage of Completion of the work done For the entire Building /Wing 80
144 X number of Slabs of Super Structure 100
144 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
144 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
144 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
144 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
144 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
144 Overall Percentage of Completion of the work done For the entire Building /Wing 80
145 X number of Slabs of Super Structure 100
145 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
145 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
145 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
145 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
145 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
145 Overall Percentage of Completion of the work done For the entire Building /Wing 80
146 X number of Slabs of Super Structure 100
146 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
146 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
146 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
146 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
146 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
146 Overall Percentage of Completion of the work done For the entire Building /Wing 80
147 X number of Slabs of Super Structure 100
147 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
147 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
147 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
147 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
147 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
147 Overall Percentage of Completion of the work done For the entire Building /Wing 80
148 X number of Slabs of Super Structure 100
148 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
148 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
148 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
148 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
148 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
148 Overall Percentage of Completion of the work done For the entire Building /Wing 80
149 X number of Slabs of Super Structure 100
149 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
149 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
149 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
149 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
149 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
149 Overall Percentage of Completion of the work done For the entire Building /Wing 80
150 Excavation 100
150 X number of Basement(s) and Plinth 100
150 X number of Slabs of Super Structure 100
150 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
150 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
150 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
150 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
150 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
150 Overall Percentage of Completion of the work done For the entire Building /Wing 80
151 X number of Slabs of Super Structure 100
151 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
151 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
151 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
151 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
151 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
151 Overall Percentage of Completion of the work done For the entire Building /Wing 80
152 Excavation 100
152 X number of Basement(s) and Plinth 100
152 X number of Slabs of Super Structure 100
152 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
152 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
152 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
152 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
152 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
152 Overall Percentage of Completion of the work done For the entire Building /Wing 80
153 X number of Slabs of Super Structure 100
153 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
153 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
153 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
153 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
153 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
153 Overall Percentage of Completion of the work done For the entire Building /Wing 80
154 X number of Slabs of Super Structure 100
154 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
154 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
154 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
154 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
154 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
154 Overall Percentage of Completion of the work done For the entire Building /Wing 80
155 X number of Slabs of Super Structure 100
155 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
155 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
155 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
155 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
155 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
155 Overall Percentage of Completion of the work done For the entire Building /Wing 80
156 Excavation 100
156 X number of Basement(s) and Plinth 100
156 X number of Slabs of Super Structure 100
156 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
156 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
156 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
156 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
156 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
156 Overall Percentage of Completion of the work done For the entire Building /Wing 80
157 Excavation 100
157 X number of Basement(s) and Plinth 100
157 X number of Slabs of Super Structure 100
157 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
157 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
157 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
157 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
157 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
157 Overall Percentage of Completion of the work done For the entire Building /Wing 80
158 X number of Basement(s) and Plinth 100
158 X number of Slabs of Super Structure 100
158 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
158 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
158 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
158 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
158 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
158 Overall Percentage of Completion of the work done For the entire Building /Wing 80
159 X number of Basement(s) and Plinth 100
159 X number of Slabs of Super Structure 100
159 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
159 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
159 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
159 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
159 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
159 Overall Percentage of Completion of the work done For the entire Building /Wing 80
160 Excavation 100
160 X number of Basement(s) and Plinth 100
160 X number of Slabs of Super Structure 100
160 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
160 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
160 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
160 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
160 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
160 Overall Percentage of Completion of the work done For the entire Building /Wing 80
161 X number of Basement(s) and Plinth 100
161 X number of Slabs of Super Structure 100
161 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
161 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
161 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
161 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
161 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
161 Overall Percentage of Completion of the work done For the entire Building /Wing 80
162 X number of Basement(s) and Plinth 100
162 X number of Slabs of Super Structure 100
162 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
162 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
162 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
162 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
162 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
162 Overall Percentage of Completion of the work done For the entire Building /Wing 80
163 X number of Basement(s) and Plinth 100
163 X number of Slabs of Super Structure 100
163 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
163 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
163 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
163 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
163 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
163 Overall Percentage of Completion of the work done For the entire Building /Wing 80
164 X number of Basement(s) and Plinth 100
164 X number of Slabs of Super Structure 100
164 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
164 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
164 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
164 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
164 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
164 Overall Percentage of Completion of the work done For the entire Building /Wing 80
165 X number of Basement(s) and Plinth 100
165 X number of Slabs of Super Structure 100
165 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
165 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
165 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
165 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
165 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
165 Overall Percentage of Completion of the work done For the entire Building /Wing 80
166 X number of Slabs of Super Structure 100
166 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
166 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
166 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
166 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
166 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
166 Overall Percentage of Completion of the work done For the entire Building /Wing 80
167 X number of Slabs of Super Structure 100
167 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
167 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
167 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
167 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
167 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
167 Overall Percentage of Completion of the work done For the entire Building /Wing 80
168 X number of Basement(s) and Plinth 100
168 X number of Slabs of Super Structure 100
168 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
168 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
168 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
168 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
168 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
168 Overall Percentage of Completion of the work done For the entire Building /Wing 80
169 X number of Basement(s) and Plinth 100
169 X number of Slabs of Super Structure 100
169 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
169 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
169 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
169 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
169 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
169 Overall Percentage of Completion of the work done For the entire Building /Wing 80
170 X number of Slabs of Super Structure 100
170 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
170 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
170 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
170 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
170 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
170 Overall Percentage of Completion of the work done For the entire Building /Wing 80
171 X number of Slabs of Super Structure 100
171 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
171 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
171 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
171 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
171 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
171 Overall Percentage of Completion of the work done For the entire Building /Wing 80
172 Excavation 100
172 X number of Basement(s) and Plinth 100
172 X number of Slabs of Super Structure 100
172 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
172 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
172 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
172 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
172 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
172 Overall Percentage of Completion of the work done For the entire Building /Wing 80
173 X number of Slabs of Super Structure 100
173 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
173 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
173 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
173 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
173 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
173 Overall Percentage of Completion of the work done For the entire Building /Wing 80
174 X number of Slabs of Super Structure 100
174 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
174 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
174 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
174 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
174 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
174 Overall Percentage of Completion of the work done For the entire Building /Wing 80
175 Excavation 100
175 X number of Basement(s) and Plinth 100
175 X number of Slabs of Super Structure 100
175 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
175 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
175 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
175 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
175 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
175 Overall Percentage of Completion of the work done For the entire Building /Wing 80
176 X number of Slabs of Super Structure 100
176 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
176 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
176 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
176 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
176 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
176 Overall Percentage of Completion of the work done For the entire Building /Wing 80
177 X number of Slabs of Super Structure 100
177 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
177 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
177 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
177 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
177 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
177 Overall Percentage of Completion of the work done For the entire Building /Wing 80
178 X number of Slabs of Super Structure 100
178 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
178 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
178 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
178 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
178 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
178 Overall Percentage of Completion of the work done For the entire Building /Wing 80
179 X number of Slabs of Super Structure 100
179 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
179 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
179 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
179 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
179 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
179 Overall Percentage of Completion of the work done For the entire Building /Wing 80
180 Excavation 100
180 X number of Basement(s) and Plinth 100
180 X number of Slabs of Super Structure 100
180 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
180 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
180 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
180 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
180 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
180 Overall Percentage of Completion of the work done For the entire Building /Wing 80
181 Excavation 100
181 X number of Basement(s) and Plinth 100
181 X number of Slabs of Super Structure 100
181 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
181 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
181 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
181 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
181 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
181 Overall Percentage of Completion of the work done For the entire Building /Wing 80
182 X number of Basement(s) and Plinth 100
182 X number of Slabs of Super Structure 100
182 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
182 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
182 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
182 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
182 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
182 Overall Percentage of Completion of the work done For the entire Building /Wing 80
183 X number of Basement(s) and Plinth 100
183 X number of Slabs of Super Structure 100
183 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
183 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
183 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
183 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
183 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
183 Overall Percentage of Completion of the work done For the entire Building /Wing 80
184 X number of Basement(s) and Plinth 100
184 X number of Slabs of Super Structure 100
184 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
184 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
184 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
184 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
184 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
184 Overall Percentage of Completion of the work done For the entire Building /Wing 80
185 X number of Basement(s) and Plinth 100
185 X number of Slabs of Super Structure 100
185 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
185 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
185 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
185 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
185 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
185 Overall Percentage of Completion of the work done For the entire Building /Wing 80
186 X number of Slabs of Super Structure 100
186 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
186 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
186 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
186 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
186 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
186 Overall Percentage of Completion of the work done For the entire Building /Wing 80
187 X number of Basement(s) and Plinth 100
187 X number of Slabs of Super Structure 100
187 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
187 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
187 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
187 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
187 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
187 Overall Percentage of Completion of the work done For the entire Building /Wing 80
188 X number of Basement(s) and Plinth 100
188 X number of Slabs of Super Structure 100
188 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
188 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
188 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
188 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
188 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
188 Overall Percentage of Completion of the work done For the entire Building /Wing 80
189 X number of Basement(s) and Plinth 100
189 X number of Slabs of Super Structure 100
189 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
189 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
189 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
189 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
189 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
189 Overall Percentage of Completion of the work done For the entire Building /Wing 80
190 X number of Slabs of Super Structure 100
190 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
190 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
190 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
190 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
190 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
190 Overall Percentage of Completion of the work done For the entire Building /Wing 80
191 X number of Slabs of Super Structure 100
191 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
191 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
191 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
191 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
191 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
191 Overall Percentage of Completion of the work done For the entire Building /Wing 80
192 X number of Slabs of Super Structure 100
192 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
192 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
192 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
192 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
192 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
192 Overall Percentage of Completion of the work done For the entire Building /Wing 80
193 X number of Slabs of Super Structure 100
193 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
193 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
193 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
193 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
193 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
193 Overall Percentage of Completion of the work done For the entire Building /Wing 80
194 X number of Slabs of Super Structure 100
194 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
194 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
194 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
194 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
194 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
194 Overall Percentage of Completion of the work done For the entire Building /Wing 80
195 X number of Slabs of Super Structure 100
195 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
195 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
195 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
195 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
195 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
195 Overall Percentage of Completion of the work done For the entire Building /Wing 80
196 Excavation 100
196 X number of Basement(s) and Plinth 100
196 X number of Slabs of Super Structure 100
196 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
196 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
196 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
196 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
196 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
196 Overall Percentage of Completion of the work done For the entire Building /Wing 80
197 X number of Slabs of Super Structure 100
197 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
197 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
197 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
197 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
197 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
197 Overall Percentage of Completion of the work done For the entire Building /Wing 80
198 X number of Slabs of Super Structure 100
198 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
198 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
198 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
198 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
198 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
198 Overall Percentage of Completion of the work done For the entire Building /Wing 80
199 X number of Slabs of Super Structure 100
199 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
199 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
199 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
199 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
199 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
199 Overall Percentage of Completion of the work done For the entire Building /Wing 80
200 X number of Slabs of Super Structure 100
200 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
200 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
200 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
200 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
200 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
200 Overall Percentage of Completion of the work done For the entire Building /Wing 80
201 X number of Slabs of Super Structure 100
201 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
201 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
201 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
201 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
201 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
201 Overall Percentage of Completion of the work done For the entire Building /Wing 80
202 X number of Slabs of Super Structure 100
202 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
202 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
202 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
202 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
202 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
202 Overall Percentage of Completion of the work done For the entire Building /Wing 80
203 X number of Slabs of Super Structure 100
203 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
203 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
203 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
203 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
203 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
203 Overall Percentage of Completion of the work done For the entire Building /Wing 80
204 X number of Slabs of Super Structure 100
204 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
204 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
204 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
204 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
204 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
204 Overall Percentage of Completion of the work done For the entire Building /Wing 80
205 X number of Slabs of Super Structure 100
205 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
205 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
205 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
205 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
205 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
205 Overall Percentage of Completion of the work done For the entire Building /Wing 80
206 X number of Slabs of Super Structure 100
206 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
206 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
206 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
206 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
206 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
206 Overall Percentage of Completion of the work done For the entire Building /Wing 80
207 X number of Slabs of Super Structure 100
207 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
207 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
207 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
207 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
207 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
207 Overall Percentage of Completion of the work done For the entire Building /Wing 80
208 X number of Slabs of Super Structure 100
208 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
208 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
208 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
208 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
208 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
208 Overall Percentage of Completion of the work done For the entire Building /Wing 80
209 X number of Slabs of Super Structure 100
209 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
209 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
209 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
209 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
209 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
209 Overall Percentage of Completion of the work done For the entire Building /Wing 80
210 X number of Slabs of Super Structure 100
210 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
210 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
210 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
210 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
210 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
210 Overall Percentage of Completion of the work done For the entire Building /Wing 80
211 Excavation 100
211 X number of Basement(s) and Plinth 100
211 X number of Slabs of Super Structure 100
211 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
211 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
211 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
211 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
211 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
211 Overall Percentage of Completion of the work done For the entire Building /Wing 80
212 X number of Slabs of Super Structure 100
212 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
212 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
212 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
212 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
212 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
212 Overall Percentage of Completion of the work done For the entire Building /Wing 80
213 Excavation 100
213 X number of Basement(s) and Plinth 100
213 X number of Slabs of Super Structure 100
213 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
213 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
213 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
213 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
213 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
213 Overall Percentage of Completion of the work done For the entire Building /Wing 80
214 X number of Slabs of Super Structure 100
214 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
214 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
214 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
214 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
214 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
214 Overall Percentage of Completion of the work done For the entire Building /Wing 80
215 X number of Slabs of Super Structure 100
215 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
215 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
215 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
215 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
215 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
215 Overall Percentage of Completion of the work done For the entire Building /Wing 80
216 X number of Slabs of Super Structure 100
216 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
216 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
216 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
216 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
216 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
216 Overall Percentage of Completion of the work done For the entire Building /Wing 80
217 X number of Slabs of Super Structure 100
217 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
217 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
217 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
217 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
217 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
217 Overall Percentage of Completion of the work done For the entire Building /Wing 80
218 X number of Slabs of Super Structure 100
218 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
218 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
218 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
218 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
218 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
218 Overall Percentage of Completion of the work done For the entire Building /Wing 80
219 X number of Slabs of Super Structure 100
219 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
219 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
219 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
219 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
219 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
219 Overall Percentage of Completion of the work done For the entire Building /Wing 80
220 X number of Slabs of Super Structure 100
220 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
220 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
220 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
220 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
220 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
220 Overall Percentage of Completion of the work done For the entire Building /Wing 80
221 X number of Slabs of Super Structure 100
221 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
221 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
221 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
221 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
221 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
221 Overall Percentage of Completion of the work done For the entire Building /Wing 80
222 X number of Slabs of Super Structure 100
222 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
222 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
222 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
222 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
222 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
222 Overall Percentage of Completion of the work done For the entire Building /Wing 80
223 X number of Slabs of Super Structure 100
223 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
223 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
223 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
223 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
223 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
223 Overall Percentage of Completion of the work done For the entire Building /Wing 80
224 X number of Slabs of Super Structure 100
224 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
224 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
224 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
224 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
224 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
224 Overall Percentage of Completion of the work done For the entire Building /Wing 80
225 X number of Slabs of Super Structure 100
225 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
225 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
225 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
225 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
225 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
225 Overall Percentage of Completion of the work done For the entire Building /Wing 80
226 X number of Slabs of Super Structure 100
226 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
226 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
226 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
226 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
226 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
226 Overall Percentage of Completion of the work done For the entire Building /Wing 80
227 X number of Slabs of Super Structure 100
227 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
227 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
227 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
227 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
227 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
227 Overall Percentage of Completion of the work done For the entire Building /Wing 80
228 X number of Slabs of Super Structure 100
228 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
228 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
228 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
228 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
228 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
228 Overall Percentage of Completion of the work done For the entire Building /Wing 80
229 X number of Slabs of Super Structure 100
229 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
229 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
229 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
229 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
229 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
229 Overall Percentage of Completion of the work done For the entire Building /Wing 80
230 X number of Slabs of Super Structure 100
230 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
230 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
230 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
230 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
230 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
230 Overall Percentage of Completion of the work done For the entire Building /Wing 80
231 X number of Slabs of Super Structure 100
231 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
231 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
231 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
231 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
231 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
231 Overall Percentage of Completion of the work done For the entire Building /Wing 80
232 X number of Slabs of Super Structure 100
232 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
232 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
232 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
232 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
232 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
232 Overall Percentage of Completion of the work done For the entire Building /Wing 80
233 Excavation 100
233 X number of Basement(s) and Plinth 100
233 X number of Slabs of Super Structure 100
233 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
233 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
233 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
233 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
233 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
233 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.94 15840 0

 

Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) field under Building/Plot Details section updated with new value 15936

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.94 15804 0

 

New documents listed below were uploaded to the Documents section:

  • 16 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 17 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 18 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 19 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 15 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 14 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 12 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 3 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 4 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 5 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 6 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 7 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 8 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 9 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 10 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 11 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 13 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Building Plan Approval (IOD) [20]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [3]
  • Commencement Certificates / NA Order for plotted development [23]
  • Copy of Layout Approval (in case of layout) [12]
  • Copy of the legal title report [17]
  • Declaration about Commencement Certificate
  • Declaration in FORM B [2]
  • Details of encumbrances [2]
  • Disclosure of Interest in Other Real Estate Organizations [2]
  • Disclosure of sold/ booked inventory [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Other – Technical [7]
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.)
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal