MH
Palghar
P99000031256
RERA ID: P99000031256
Project Name: Joyville Virar Phase 6
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Virar, Bolinj, Virar, Vasai-Virar City (M Corp), Vasai, Palghar-401303

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Part and Parcel of 297/2, 298/6, 390B

Boundaries:
390B
297N 315
WE
S
295

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 3151 sq.mt.
Sanctioned Built-up Area: 32298 sq.mt.
Recreational Open Space: 4660 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 45
No. of Podiums: 3
No. of Stilts: 2
No. of Closed Parking: 309

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 289 to 437 sq ft 472 211
2BHK 644 sq ft 92 13
Shop 137 to 371 sq ft 12 11
Project Developer:
Joyville Shapoorji Housing Private Limited
Organization Type: Company

Address: 41/44, Sp Centre, Minoo Desai Marg, Colaba, Radio Club, Mumbai City-400005

Office Phone: +91 22674 90101


Member details:
Member Name Designation
Ranjana Agarwal Director
Subrata Dutta Gupta Director
Sandeep Awasthi Director
Anuj Puri Director
Venkatesh Gopalkrishnan Chairperson
Sriram Mahadevan Managing Director
Ashish Singh Director


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Siddharth Thakur and 3 other ( VIVA Holdings ) Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
EN CON Project Consultants Architect
Harshad Doshi Chartered Accountant
EN CON Project Consultants Engineer
B R Nagda & Co Chartered Accountant


Projects in the state by this developer:
P52100076945 - Joyville Celestia Phase 5 - Pune
P52100055524 - Joyville Celestia Phase 3 - Pune
P52100054174 - Joyville Hadapsar Annexe Phase 17 - Pune
P52100053165 - Joyville Celestia Phase 1 - Pune
P52100053159 - Joyville Celestia Phase 2 - Pune
P52100049970 - Joyville Hadapsar Annexe Phase 16 - Pune
P52100049547 - SENSORIUM, PHASE VII - Pune
P52100048377 - Joyville Hadapsar Annexe Phase 20 - Pune
P52100048338 - Joyville Hadapsar Sky-Luxe - Pune
P52100048314 - Joyville Hadapsar Annexe Phase 18 - Pune
…and 34 more
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
SDO Vasai 0 Civil Appeal 2020 Pre Admission
The High Court of Judicature at Bombay 10475 Others Other 2021 Pre Admission
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Joyville Virar Phase 6: A Vision of Urban Harmony

Nestled in the heart of Virar, the bustling suburb of Mumbai, Joyville Virar Phase 6 is a premium residential development that sets a new standard for urban living. This meticulously planned project by Joyville Shapoorji Housing Private Limited, a renowned real estate developer with decades of experience, promises to be a sanctuary of comfort and convenience.

Project Overview

With a RERA ID of P99000031256, Joyville Virar Phase 6 is a new project slated for completion by March 2025. Spanning an expansive 3151 square meters, the development comprises two residential towers, each showcasing an impressive 45 floors. A testament to the project’s commitment to sustainability, 4660 square meters of recreational open space will be available for the residents’ enjoyment.

Exceptional Amenities

Joyville Virar Phase 6 offers an unparalleled range of amenities designed to enhance the lives of its residents. These include:

  • Three Podiums: Providing elevated spaces for social interaction and relaxation.
  • 309 Closed Parking Spaces: Ensuring safe and convenient parking for all residents.
  • State-of-the-art Elevators: Guaranteeing seamless and efficient movement within the towers.
  • 24/7 Security: Providing peace of mind and ensuring safety for the residents.

Diverse Unit Options

To cater to a wide range of needs and preferences, Joyville Virar Phase 6 offers a selection of thoughtfully designed unit types:

  • 1BHK: Ranging in size from 289 to 437 square feet, these units are ideal for first-time homebuyers or those seeking cozy accommodations.
  • 2BHK: Measuring 644 square feet, these spacious units offer ample room for families and individuals searching for comfort.
  • Shop: With sizes varying from 137 to 371 square feet, these units provide the perfect opportunity for entrepreneurs to establish their businesses amidst a vibrant community.

Strategic Location

Joyville Virar Phase 6 enjoys an enviable location in Virar, close to major transportation hubs and civic amenities. Its proximity to Mumbai ensures easy access to the city’s vibrant culture, employment opportunities, and entertainment options.

Investment Potential

Not only is Joyville Virar Phase 6 a desirable residential destination, but it also presents a lucrative investment opportunity. Its prime location, exceptional amenities, and competitive pricing make it an attractive investment for both individuals and investors.

In conclusion, Joyville Virar Phase 6 is a meticulously planned and thoughtfully executed residential development that promises to redefine urban living. Its diverse unit options, exceptional amenities, strategic location, and investment potential make it an irresistible choice for those seeking a home or an investment in one of Mumbai’s most promising suburbs.

New documents listed below were uploaded to the Documents section:

  • 23 Disclosure of sold/ booked inventory
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 98
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 45
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 68.3
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 75
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 45
2 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 401 310 60

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Landscaping & Tree Planting : 80
Street Lighting : 75
Storm Water Drains : 90
Water Supply : 60
Water Conservation, Rain water Harvesting : 90
Fire Protection And Fire Safety Requirements : 80
Electrical Meter Room, Sub-Station, Receiving Station : 65
Covered Parking : 60 Podium parking shared between phases

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 22 Disclosure of sold/ booked inventory
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 37.1 152 57
1BHK 37.25 152 72
1BHK 40.63 92 43
Shop 13.87 2 2
Shop 21.32 2 2
Shop 34.48 1 0

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Conservation, Rain water Harvesting : 80

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 95
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
1 Overall Percentage of Completion of the work done For the entire Building /Wing 63
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 55

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 401 164 50

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 401 122 50

 

New documents listed below were uploaded to the Documents section:

  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 21 Disclosure of sold/ booked inventory
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Slabs of Super Structure 92
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 69
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 31
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
2 Overall Percentage of Completion of the work done For the entire Building /Wing 46.2

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.88 19 9
1BHK 37.1 152 48
1BHK 37.25 152 66
1BHK 37.79 38 15

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Open Parking : 40
Fire Protection And Fire Safety Requirements : 70

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [8]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development [3]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [4]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [20]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20) [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [2]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [9]
  • Proforma of Allotment letter [2]