RERA ID: P52100049970
Project Name: Joyville Hadapsar Annexe Phase 16
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Shewalewadi, Off Pune Solapur Highway, Haveli, Pune-412307

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
6/7/9/10/6 Part

Boundaries:
6 7 9 10 6 Part
6 7 9 10 6 PartN 6 7 9 10 6 Part
WE
S
6 7 9 10 6 Part

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 1818 sq.mt.
Sanctioned Built-up Area: 15616 sq.mt.
Recreational Open Space: 540 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 42
No. of basements: 2
No. of Stilts: 2
No. of Closed Parking: 2

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 347 to 534 sq ft 49 45
2BHK 537 to 608 sq ft 161 140
3BHK 746 sq ft 42 30
Project Developer:
Joyville Shapoorji Housing Private Limited
Organization Type: Company

Address: 41/44, Sp Centre, Minoo Desai Marg, Colaba, Radio Club, Mumbai City-400005

Office Phone: +91 22674 90101


Member details:
Member Name Designation
Ranjana Agarwal Director
Subrata Dutta Gupta Director
Sandeep Awasthi Director
Anuj Puri Director
Venkatesh Gopalkrishnan Chairperson
Sriram Mahadevan Managing Director
Ashish Singh Director


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Manjri Horse Breeders’ Farms Pvt. Ltd. Company Revenue Share


Other Professionals involved:
Professional Name Professional Type
MSK Architects And Associates Architect
Mr Akshay Lalit Kasar Engineer
CA Bhavesh Nagda Chartered Accountant


Projects in the state by this developer:
P52100076945 - Joyville Celestia Phase 5 - Pune
P52100055524 - Joyville Celestia Phase 3 - Pune
P52100054174 - Joyville Hadapsar Annexe Phase 17 - Pune
P52100053165 - Joyville Celestia Phase 1 - Pune
P52100053159 - Joyville Celestia Phase 2 - Pune
P52100049970 - Joyville Hadapsar Annexe Phase 16 - Pune
P52100049547 - SENSORIUM, PHASE VII - Pune
P52100048377 - Joyville Hadapsar Annexe Phase 20 - Pune
P52100048338 - Joyville Hadapsar Sky-Luxe - Pune
P52100048314 - Joyville Hadapsar Annexe Phase 18 - Pune
…and 34 more
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
Court of Civil Judge Senior Division Pune 32 Civil Suit 2009 Evidence Stage
Bombay High Court WP No 1311 2019 Civil Writ Petition 2019 Pre Admission
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Joyville Hadapsar Annexe: A Haven of Luxury and Convenience

In the vibrant metropolis of Pune, nestled within the serene embrace of Shewalewadi, unfolds a transformative real estate masterpiece – Joyville Hadapsar Annexe Phase 16. This prestigious project, meticulously planned and executed by Joyville Shapoorji Housing Private Limited, is designed to redefine urban living, offering its discerning residents an unparalleled blend of luxury, comfort, and convenience.

Exceptional Location and Connectivity

Joyville Hadapsar Annexe enjoys an enviable location off Pune Solapur Highway, providing seamless connectivity to key business hubs, educational institutions, and recreational destinations. Its proximity to the proposed metro station and well-developed infrastructure ensures effortless commuting and accessibility.

Architectural Masterpiece

The project boasts an impressive layout, meticulously designed to maximize natural light and ventilation. The two towering buildings, each comprising 42 floors resting atop elegant stilts, create a striking architectural landmark. With a total built-up area of 15616 square meters, Joyville Hadapsar Annexe offers an exclusive collection of well-appointed apartments.

Spacious and Luxurious Homes

Residents can choose from a range of meticulously crafted 1BHK, 2BHK, and 3BHK apartments, each thoughtfully designed to provide ample living space and unparalleled comfort. The homes feature spacious balconies, inviting residents to embrace the outdoors and enjoy stunning views of the cityscape.

World-Class Amenities

At Joyville Hadapsar Annexe, residents are indulged with a plethora of world-class amenities that cater to their every need. The project boasts two spacious basements, ensuring ample covered parking for vehicles. The lush recreational open space, spanning 540 square meters, offers a tranquil oasis for relaxation and rejuvenation.

Trust and Reliability

Joyville Shapoorji Housing Private Limited, the renowned developer behind Joyville Hadapsar Annexe, is committed to impeccable quality, innovation, and customer satisfaction. With a proven track record of delivering exceptional projects, the company has earned the trust of discerning homebuyers across the country.

Investment Potential

Joyville Hadapsar Annexe presents a compelling investment opportunity, offering a combination of high rental yield and long-term appreciation potential. The project’s strategic location and exceptional amenities make it an attractive proposition for both investors and end-users alike.

Set to be completed in December 2026, Joyville Hadapsar Annexe is an extraordinary real estate project that promises to deliver a lifestyle of unparalleled comfort, convenience, and investment value. As a beacon of luxury and innovation, this landmark development invites you to experience urban living at its finest.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 38.9 3 2
2BHK 49.94 80 79
2BHK 56.49 80 60
3BHK 69.36 42 30

 

New documents listed below were uploaded to the Documents section:

  • 5 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 232 201 68

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 30
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 3
1 Overall Percentage of Completion of the work done For the entire Building /Wing 33.3

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Club House : 90 Phasewise Development
Covered Parking : 68 Basement common for all phases

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Disclosure of sold/ booked inventory
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 38.9 3 2
2BHK 49.94 80 63
2BHK 56.49 80 53
3BHK 69.36 42 24

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 232 171 55

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Electrical Meter Room, Sub-Station, Receiving Station : 25 Phasewise Development
Sewerage (Chamber, Lines, Septic Tank , STP) : 20 Common for all phases
Water Supply : 20 Common for all phases
Club House : 75 Phasewise Development
Fire Protection And Fire Safety Requirements : 40 As per CFO NOC
Energy management : 40 As per MOEF submission
Water Conservation, Rain water Harvesting : 15 Common for all phases
Solid Waste Management And Disposal : 15 Phasewise Development
Treatment And Disposal Of Sewage And Sullage Water : 15 common for all
Landscaping & Tree Planting : 35 Common for all phases
Storm Water Drains : 20 Common for all phases
Internal Roads & Footpaths : 10 Common for all phases

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5
2 X number of Basement(s) and Plinth 100
2 Stilt Floor 100
2 X number of Slabs of Super Structure 25
2 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 32.29 41 41
1BHK 32.43 1 1
1BHK 38.9 3 0
1BHK 42.92 3 1
1BHK 49.7 1 0
2BHK 49.94 80 60
2BHK 49.99 1 0
2BHK 56.49 80 49
3BHK 69.36 42 22

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 232 160 0

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 32.29 41 41
2BHK 49.94 80 60
2BHK 49.99 1 0
2BHK 56.49 80 49
3BHK 69.36 42 22

 

New documents listed below were uploaded to the Documents section:

  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 3 Disclosure of sold/ booked inventory
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 Stilt Floor 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 30

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [4]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [4]
  • Other – Legal [3]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]