RERA ID: P99000016104
Project Name: NIRVANA ECO HOME
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2024-12-30
Revised Proposed Date of Completion
The project missed completion date 1 time(s) earlier (2023-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Alyalee, Palghar Road, Palghar-401404

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
268

Boundaries:
GUT NO189
GUT NO 189N OPEN SPACE
WE
S
12M DP ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 2144 sq.mt.
Sanctioned Built-up Area: 4853 sq.mt.
Recreational Open Space: 1038 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 5
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 10
No. of Closed Parking: 4

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 276 to 314 sq ft 72 32
1RK 221 to 229 sq ft 30 24
2BHK 383 to 408 sq ft 18 18
Project Developer:
Shree Krishna Developers
Organization Type: Partnership

Address: Gut No. 268, Nirvana Eco Homes, Building No-1, High Tech Ind. Road, Palghar, High Tech Ind.-401404

Office Phone: +91 91814 999240


Member details:
Member Name Designation
MUKESH GOPAL SHETTY Partner
Virendra Takhatsinh Solanki Authorized Signatory
NISHEETH RAMESH TAUNK Partner
MOHAMMED FAROOQUE HANIF JATU Partner
RAJEEV PHOOLCHAND SINGH Partner
ISRAR AHAMAD KHAN Partner
BHIKU PURU PAWAR Partner
KAMLESH RATILAL THAKKAR Partner
AJAY RANVIJAY SINGH Partner
SALIM HUSAINALI HEMANI Partner
KAMAL KISHOR SHARMA Partner
PRAKASH NIMBA PATIL Partner
ANKISH HARESH THAKKAR Partner
ABDUL INDAZALIALIRAZAQALI KALAM Partner
BRIJESH HARESH THAKKAR Partner
KIRTISH SURESH DAVE Partner
HARESH FULCHAND THAKKAR Partner
KRUNAL HARISH KAKAIYA Partner
YOGESH GHANARAM AHIRAWAL Partner
BHAVIN MAHENDRA PAREKH Partner
ROHIDAS BANSIDHAR KASMIWAL Partner


Other Professionals involved:
Professional Name Professional Type
SQUAREONE ARCHITECT Architect


Projects in the state by this developer:
P99000016104 - NIRVANA ECO HOME - Palghar
P52000013742 - Gokul Niwas - Raigarh
P51800006422 - SUNFLOWER - Mumbai Suburban
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Nirvana Eco Home: An Oasis of Affordable Urban Living

Introducing Nirvana Eco Home, an esteemed residential project poised to transform the real estate landscape of Palghar. This RERA-registered project, meticulously crafted by Shree Krishna Developers, embodies the epitome of modern living, offering a sanctuary of comfort and convenience within an idyllic setting.

The project encompasses an expansive plot of 2144 square meters, offering ample space for a vibrant community to thrive. The meticulously designed layout features a single residential building, boasting five well-appointed floors with a total built-up area of 4853 square meters. The building seamlessly blends contemporary architecture with modern amenities, ensuring a harmonious living experience for its residents.

Nirvana Eco Home proudly presents a diverse range of units to cater to the needs of discerning homebuyers. Choose from a cozy 1RK (221-229 sq ft) to a spacious 2BHK (383-408 sq ft), each meticulously designed to optimize space and comfort. The project also boasts 72 well-proportioned 1BHK units (276-314 sq ft), offering a perfect balance of affordability and comfort.

Beyond its meticulously crafted living spaces, Nirvana Eco Home boasts an array of amenities designed to enhance the quality of life for its residents. The project features a generous recreational open space of 1038 square meters, providing ample opportunities for leisure and recreation. Conveniently located parking spaces, both open and closed, ensure hassle-free vehicle storage for residents.

Nestled in the picturesque town of Palghar, Nirvana Eco Home enjoys a prime location with easy access to essential amenities. Situated in the sought-after locality of Alyalee, the project offers a tranquil retreat from the bustling city while still providing convenient proximity to schools, hospitals, and shopping centers.

Committed to transparency and reliability, Shree Krishna Developers have ensured that Nirvana Eco Home complies with all regulatory requirements. The project holds a valid RERA ID (P99000016104) and is progressing smoothly towards its revised completion date of December 31, 2024. With its exceptional amenities, prime location, and unwavering commitment to quality, Nirvana Eco Home stands as a testament to exceptional value and urban living.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 25.7 4 1

 

New documents listed below were uploaded to the Documents section:

  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Disclosure of sold/ booked inventory

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 100 DEVLOPED
Storm Water Drains : 0 As per Approved
Landscaping & Tree Planting : 0 As per Approved
Electrical Meter Room, Sub-Station, Receiving Station : 0 Electric work as per MSEDCL

 

New documents listed below were uploaded to the Documents section:

  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Disclosure of sold/ booked inventory
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80.5

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.03 40 12
1RK 21.1 6 4
2BHK 35.65 1 1
2BHK 35.89 9 9

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.31 2 0
1BHK 26.45 16 12
1BHK 29.18 10 7
1RK 20.58 20 16
1RK 21.2 2 2
2BHK 35.89 8 8

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 75
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 55
1 Overall Percentage of Completion of the work done For the entire Building /Wing 74

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval (IOD) [6]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Proforma of Allotment letter