MH
Raigarh
P52000013742
RERA ID: P52000013742
Project Name: Gokul Niwas
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2020-09-30
Revised Proposed Date of Completion
The project missed completion date 1 time(s) earlier (2019-12-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
, New Panvel, Panvel, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Plot No - 20

Boundaries:
Plot No - 20A
Plot No - 17N Road
WE
S
Plot No - 19

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 200 sq.mt.
Sanctioned Built-up Area: 298 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 5
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Others 178 to 293 sq ft 13 0
Project Developer:
Shree Krishna Developers
Organization Type: Partnership

Address: 02-2, Type - A, Sector - 13, New Panvel, Near Ayappa Temple, Panvel, Raigarh-410206

Office Phone: +91 98209 49266


Member details:
Member Name Designation
Suraj Uday Khopkar Authorized Signatory
Vinod Devshi Patel Partner
Devshi Hansraj Patel Partner
Chandulal DevshiJ Patel Partner
Mohanlal Devshi Patel Partner


Other Professionals involved:
Professional Name Professional Type
Atul Patel Architects Architect


Projects in the state by this developer:
P99000016104 - NIRVANA ECO HOME - Palghar
P52000013742 - Gokul Niwas - Raigarh
P51800006422 - SUNFLOWER - Mumbai Suburban
Litigations

Litigations related to the project ? No

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate on Completion of Project (Form 4)
  • Building Plan Approval (IOD) [2]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [2]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Proforma of Allotment letter [3]