RERA ID: P99000005905
Project Name: Navkar City Phase II Part-4
Project Type: Residential
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2024-12-29
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2023-12-30, 2018-12-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Naigaon, Naigaon East, Vasai-Virar City (M Corp), Vasai, Palghar-401208

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Survey No332 Hissa No7 8 , Survey No.333, Hissa No.1, 2

Boundaries:
Survey No335
Survey No311N B Type Bldg
WE
S
Survey No331

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 5017 sq.mt.
Sanctioned Built-up Area: 4147 sq.mt.
Recreational Open Space: 1744 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Stilts: 1
No. of Open Parking: 26
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 259 to 301 sq ft 140 140
Project Developer:
Navkar Estate and Homes Pvt Ltd
Organization Type: Company

Address: Survey No.332/7, Navkar City, Don Bosco High School, Naigaon-East, Near Don Bosco School, Vasai-Virar City (M Corp), Vasai, Palghar-401208

Office Phone: +91 88796 88487


Member details:
Member Name Designation
Laxman Bhikaji Khedkar Managing Director
Suresh Bhavarlal Jain Authorized Signatory
Naresh Chandmal Jain Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Rajesh R.C Architect
Himesh Gupta & Associates Architect
CSE Consultanant Engineer
Prashant Kumar Other Professional
Newarch Landscapes LLP Other Professional
Sheetal environs (I) Pvt.Ltd. Other Professional
Rahul Engginers Pvt Ltd. Other Professional


Projects in the state by this developer:
P99000011999 - NAVKAR CITY PHASE I PART 1 - Palghar
P99000011641 - Navkar City Phase III Part 1 - Palghar
P99000009437 - NAVKAR CITY PHASE II PART I - Palghar
P99000007525 - Navkar Tower Part 1 - Palghar
P99000005905 - Navkar City Phase II Part-4 - Palghar
P99000004423 - Navkar City Phase II Part 2 - Palghar
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Nestled in the vibrant locality of Naigaon, Vasai-Virar City (M Corp), Maharashtra, Navkar City Phase II Part-4 presents a compelling opportunity for those seeking a well-planned residential haven. This RERA-registered project, identified by the unique ID P99000005905, is developed by Navkar Estate and Homes Pvt Ltd, a reputable developer with a commitment to quality and timely completion.

A Vision of Modern Living: The project encompasses a sprawling plot of 5017 sq. meters, featuring a single, well-designed building with a sanctioned FSI of 4147 sq. meters. The building boasts a total of 7 floors, including a stilt level, and offers a range of amenities to enhance the quality of life for its residents.

A Harmonious Blend of Comfort and Convenience: The project boasts 26 open parking spaces to accommodate your vehicles, ensuring a hassle-free experience. The presence of a single closed parking space provides additional security and convenience.

A Serene Setting: The project is strategically located near the renowned Don Bosco High School, offering a tranquil environment amidst the bustling city life. The project is also conveniently situated near Naigaon-East, providing easy access to essential amenities like schools, hospitals, shopping malls, and other facilities.

Beyond the Basics: Navkar City Phase II Part-4 goes beyond the basic amenities, offering 1744 sq. meters of recreational open space within its boundaries. This dedicated space provides residents with opportunities to relax, unwind, and connect with nature.

A Commitment to Excellence: While the initial proposed date of completion was set for December 31st, 2018, the project has been extended to December 29th, 2024, ensuring a timely delivery. The absence of any reported litigations related to the project reinforces the developer’s commitment to transparency and ethical practices.

Invest in a Brighter Future: Navkar City Phase II Part-4 promises a fulfilling lifestyle in a vibrant and well-connected neighborhood. The project’s well-designed layout, emphasis on open spaces, and proximity to key amenities make it an attractive choice for discerning homebuyers seeking a comfortable and convenient living experience.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 24.15 18 18
1BHK 24.26 18 18
1BHK 27.41 20 20
1BHK 27.83 7 7
1BHK 27.92 13 13
1BHK 27.93 13 13
1BHK 28.01 11 11

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 98
1 Overall Percentage of Completion of the work done For the entire Building /Wing 88.8

 

New documents listed below were uploaded to the Documents section:

  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of Interest in Other Real Estate Organizations
  • 2 Disclosure of Interest in Other Real Estate Organizations
  • 1 CERSAI details
  • 1 Disclosure of sold/ booked inventory
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 b Details of encumbrances concerned to Legal
  • 1 Deviation Report with respect to Allotment letter
  • 1 Deviation Report with respect to model copy of Agreement
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 2 a Details of encumbrances concerned to Finance

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 98
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 98
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 98
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 98
1 Overall Percentage of Completion of the work done For the entire Building /Wing 89

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2024-12-29

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 95 Work in Progress
Electrical Meter Room, Sub-Station, Receiving Station : 95 Work in Progress
Water Conservation, Rain water Harvesting : 95 Work in Progress
Internal Roads & Footpaths : 98 Work in Progress
Street Lighting : 95 Work in Progress
Landscaping & Tree Planting : 98 Work in Progress
Community Buildings : 98 Work in Progress
Open Gymnasium : 100 Work in Progress
multipurpose Court : 95 Work in Progress
Compound Wall of Layout : 85 Work in Progress
Land Development Filling and Leveling : 80 Work Completed
Storm Water Drains : 98 Work in Progress
Outdoor Playing Area With Playing Equipment : 80 Work in Progress
Swimming Pool : 95 Work in Progress
Sewerage (Chamber, Lines, Septic Tank , STP) : 98 Work in Progress
Water Supply : 98 Work in Progress
Aggregate area of recreational Open Space : 95 Work in Progress
Open Parking : 95 Work in Progress

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 24.15 14 14
1BHK 24.26 14 14
1BHK 27.41 12 10
1BHK 27.48 14 14
1BHK 27.61 7 7
1BHK 27.83 6 5
1BHK 27.85 8 8
1BHK 27.89 11 11
1BHK 27.92 8 6
1BHK 27.93 12 11
1BHK 28.01 6 5

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • 2 Declaration in FORM B

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD) [2]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [13]
  • Certificates of CA (Form 5) [6]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [21]
  • Commencement Certificates / NA Order for plotted development [7]
  • Copy of Layout Approval (in case of layout) [3]
  • Copy of the legal title report [4]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Other [5]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter [6]
  • Status of Formation of Legal Entity (Society/Co Op etc.)