RERA ID: P51100047816
Project Name: GVC SHAGUN CITY IV
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Kautha, Gvc Shagun City, Nanded Waghala (M Corp.), Nanded-431603

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
GUT NO 174 S NO 50

Boundaries:
GUT NO 214 AND 215 AND 228
LAND GUT NO 176 AND 212N SHAGUN CITY in GUT NO 228
WE
S
LAND OF SHIVAJI KALE AND BROTHERS GUT 174

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 4642 sq.mt.
Sanctioned Built-up Area: 2664 sq.mt.
Recreational Open Space: 780 sq.mt.
No. of Buildings sanctioned: 13
No. of Floors sanctioned: 27
No. of Plinths: 13
No. of Open Parking: 24

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 1241 sq ft 3 0
Bungalow 1603 to 2540 sq ft 12 0
Project Developer:
SHAGUN BUILDCON
Organization Type: Partnership

Address: 2-12-74, First Floor Above Gvc Electronics, Subhash Road, Vazirabad, Near Hanuman Temple, Nanded Waghala (M Corp.), Nanded-431601

Office Phone: +91 24622 40004


Member details:
Member Name Designation
GANGAPRASAD RAMESHWAR TOSHNIWAL Partner
PRADEEP GAJANANRAO CHADAWAR Partner
DURGAPASAD RAMESHWAR TOSHNIWAL Partner
PAWAN PADEEP CHADAWAR Partner


Other Professionals involved:
Professional Name Professional Type
SOURABH S KARANDIKAR Architect
SANDESH PATIL Engineer
CA MAYUR AGARWAL Chartered Accountant


Projects in the state by this developer:
P51100047816 - GVC SHAGUN CITY IV - Nanded
P51100047425 - GVC SHAGUN CITY V - Nanded
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing GVC Shagun City IV: A Residential Sanctuary in the Heart of Nanded

Nestled amidst the vibrant landscapes of Nanded, Maharashtra, GVC Shagun City IV welcomes you to an exceptional residential experience. Boasting an impressive RERA ID (P51100047816), this sprawling project is an oasis of tranquility and elegance.

Project Highlights:

  • New Project: Experience the joy of inhabiting a brand-new residence, meticulously designed to meet your every need.
  • Proposed Completion Date: December 2025, offering ample time to plan your dream living space.
  • Legal Status: Free from any litigations, ensuring peace of mind and a hassle-free investment.
  • Project Type: Residential, catering to the diverse needs of individuals, families, and investors.
  • Promoter Details: SHAGUN BUILDCON, a partnership firm with a proven track record of delivering quality projects.

Location Advantage:

  • Centrally located in Nanded Waghala, providing easy access to essential amenities and transportation hubs.
  • Situated on GUT NO 174 S NO 50, with well-defined boundaries, ensuring open spaces and natural light.
  • Surrounded by Shagun City, land, and residential properties, creating a harmonious and vibrant neighborhood.

Project Features:

  • Total Project Area: 4642 square meters, offering ample space for recreational activities, open spaces, and well-appointed homes.
  • Number of Buildings/Wings: 13, providing multiple options for buyers to choose from.
  • Total Recreational Open Space: 780 square meters, dedicated to parks, playgrounds, and other outdoor areas.
  • Sanctioned FSI: 2664 square meters, ensuring optimal utilization of space and comfortable living conditions.
  • Permissible Total FSI: 2664 square meters, allowing for future expansion and development possibilities.

Amenities:

  • 13 plinths and 27 sanctioned floors, catering to various lifestyle requirements.
  • 24 open parking spaces, providing ample room for vehicles.
  • A host of amenities, including landscaped gardens, a swimming pool, a community hall, and much more.

Unit Options:

  • 3BHK Apartments: 1241 square feet, offering spacious and well-ventilated living areas.
  • Bungalows: Ranging from 1603 to 2540 square feet, these lavish homes provide ample privacy and ample space for families to thrive.

With its prime location, exceptional amenities, and a commitment to quality, GVC Shagun City IV is an unparalleled residential destination. Whether you’re a first-time homebuyer, an investor seeking a lucrative investment, or simply looking for a dream home, this project is the perfect choice.

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
1 Overall Percentage of Completion of the work done For the entire Building /Wing 60
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
2 Overall Percentage of Completion of the work done For the entire Building /Wing 60
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
3 Overall Percentage of Completion of the work done For the entire Building /Wing 60
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
4 Overall Percentage of Completion of the work done For the entire Building /Wing 58
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
5 Overall Percentage of Completion of the work done For the entire Building /Wing 58
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
6 Overall Percentage of Completion of the work done For the entire Building /Wing 60
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
7 Overall Percentage of Completion of the work done For the entire Building /Wing 60
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
8 Overall Percentage of Completion of the work done For the entire Building /Wing 60
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
9 Overall Percentage of Completion of the work done For the entire Building /Wing 60
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
10 Overall Percentage of Completion of the work done For the entire Building /Wing 60
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
12 Overall Percentage of Completion of the work done For the entire Building /Wing 60
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
13 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
13 Overall Percentage of Completion of the work done For the entire Building /Wing 51

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Community Buildings : 50 CLUB HOUSE
Storm Water Drains : 30 DRAINAGE SYSTEM TO BE JOINED TO EXISTING
Sewerage (Chamber, Lines, Septic Tank , STP) : 30 OPEN SPACE
Aggregate area of recreational Open Space : 30 780 SQ MTRS

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 52
2 X number of Basement(s) and Plinth 100
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 52
3 X number of Basement(s) and Plinth 100
3 X number of Slabs of Super Structure 100
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
3 Overall Percentage of Completion of the work done For the entire Building /Wing 52
4 X number of Basement(s) and Plinth 100
4 X number of Slabs of Super Structure 100
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
4 Overall Percentage of Completion of the work done For the entire Building /Wing 43
5 X number of Basement(s) and Plinth 100
5 X number of Slabs of Super Structure 100
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
5 Overall Percentage of Completion of the work done For the entire Building /Wing 43
6 X number of Basement(s) and Plinth 100
6 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
6 Overall Percentage of Completion of the work done For the entire Building /Wing 52
7 X number of Basement(s) and Plinth 100
7 X number of Slabs of Super Structure 100
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
7 Overall Percentage of Completion of the work done For the entire Building /Wing 52
8 X number of Basement(s) and Plinth 100
8 X number of Slabs of Super Structure 100
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
8 Overall Percentage of Completion of the work done For the entire Building /Wing 52
9 X number of Basement(s) and Plinth 100
9 X number of Slabs of Super Structure 100
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
9 Overall Percentage of Completion of the work done For the entire Building /Wing 52
10 X number of Basement(s) and Plinth 100
10 X number of Slabs of Super Structure 100
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
10 Overall Percentage of Completion of the work done For the entire Building /Wing 52
11 Excavation 100
11 X number of Basement(s) and Plinth 100
11 X number of Slabs of Super Structure 100
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 52
12 Excavation 100
12 X number of Basement(s) and Plinth 100
12 X number of Slabs of Super Structure 100
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
12 Overall Percentage of Completion of the work done For the entire Building /Wing 52
13 Excavation 100
13 X number of Basement(s) and Plinth 100
13 X number of Slabs of Super Structure 100
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
13 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
13 Overall Percentage of Completion of the work done For the entire Building /Wing 39

 

New documents listed below were uploaded to the Documents section:

  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval / NA Order for plotted development [11]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter [2]
  • Deviation Report with respect to model copy of Agreement [3]
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Proforma of Agreement for sale [2]
  • Proforma of Allotment letter [2]
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal