RERA ID: P51500050902
Project Name: PATEL PALMS PHASE lll
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-11-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Aurangabad, Gut No-306/2/Part, Harsool, Aurangabad (M Corp.)-431001

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
GUT NO 306/2/PART HARSOOL

Boundaries:
Land of Gut No 306
Land of Gut No 306N Survey No 06
WE
S
Drainage Line

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1962 sq.mt.
Sanctioned Built-up Area: 1577 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 2
No. of Plinths: 1
No. of Closed Parking: 32

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 771 sq ft 20 7
Project Developer:
PATEL PROPERTIES
Organization Type: Partnership

Address: Plot No 92 And 93, Patel Plaza, 2Nd Floor, Roza Bagh, N-12, Aurangabad (M Corp.), Aurangabad-431001

Office Phone: +91 12345 67892


Member details:
Member Name Designation
ABDUL WAJID ABDUL SAMI PATEL Partner
ABDUL WAJID ABDUL SAMI PATEL Authorized Signatory
ABDULMAJED NIjAM PATHAN Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
SHAIKH ZAKIR SIKANDAR PATEL Individual Area Share


Other Professionals involved:
Professional Name Professional Type
MP Construction Contractor
Impact Design Associates Architect
ICON Consultants Engineer
Yash Nagar Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Patel Palms Phase III: A New Residential Project in Aurangabad

Patel Palms Phase III, a new residential project by Patel Properties, is set to redefine luxury living in Aurangabad. This exciting venture, registered with MahaRERA under ID P51500050902, promises to deliver modern and comfortable homes in a prime location.

A Prime Location in the Heart of the City

Located in the bustling locality of Aurangabad, Patel Palms Phase III occupies a strategic plot spanning 1962 sqmts within Gut No 306/2/PART, Harsool. The project enjoys proximity to essential amenities like schools, hospitals, and shopping centers, ensuring convenience and ease for residents.

A Focus on Quality and Comfort

Patel Palms Phase III features a single building comprising two sanctioned floors, offering a total of 20 meticulously designed 3BHK apartments, each spanning 771 sq ft. The project has been granted an FSI of 1577, allowing for ample space within each unit and maximizing the overall living experience.

Uncompromising Amenities

Patel Properties is committed to providing residents with a holistic living experience. The project offers convenient amenities such as closed parking for 32 vehicles, ensuring safe and secure parking for all residents.

A Reliable and Reputable Developer

Patel Properties, a reputable partnership firm, has a proven track record of delivering high-quality real estate projects. Their commitment to transparency and customer satisfaction is evident in the meticulous planning and execution of Patel Palms Phase III.

Investment Opportunity

Patel Palms Phase III presents an excellent opportunity for homebuyers seeking a modern and comfortable living space in a prime location. With its strategic location, well-planned amenities, and commitment to quality, this project promises to provide a high return on investment.

Looking Ahead

With construction slated for completion by November 30, 2025, Patel Palms Phase III is poised to become a sought-after address in Aurangabad. The project’s focus on quality, comfort, and strategic location makes it an attractive option for discerning homebuyers and investors alike.

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 75
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
1 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Electrical Meter Room, Sub-Station, Receiving Station : 20 AS PER APPROVED PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 70 AS PER APPROVED PLAN
Storm Water Drains : 25 AS PER APPROVED PLAN
Street Lighting : 50 AS PER APPROVED PLAN

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3 BHK ROW HOUSE 71.7 20 7

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 95
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
1 Overall Percentage of Completion of the work done For the entire Building /Wing 43

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Disclosure of sold/ booked inventory

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 50 AS PER APPROVED PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 50 AS PER APPROVED PLAN
Water Supply : 50 AS PER APPROVED PLAN
Electrical Meter Room, Sub-Station, Receiving Station : 25 AS PER APPROVED PLAN
Street Lighting : 70 AS PER APPROVED PLAN
Water Conservation, Rain water Harvesting : 0 AS PER APPROVED PLAN
Internal Roads & Footpaths : 50 AS PER APPROVED PLAN

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3 BHK ROW HOUSE 71.7 20 5

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 87
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 41.2

 

New documents listed below were uploaded to the Documents section:

  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Disclosure of sold/ booked inventory
  • 3 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development [3]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other – Technical
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal