2027-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Makai Gate Road, Aurangabad, Cts No.2172/2, Makai Gate Road, Near Ghati, Aurangabad (M Corp.), Aurangabad-431001

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS No.2172/2, Makai Gate Road, Near Ghati,

Boundaries:
CTS NO 2151 CTS NO 2153
HOUSE OF RAMESH GAIKWADN CTS NO 21721 and CTS NO 21723
WE
S
24 MTR ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 694 sq.mt.
Sanctioned Built-up Area: 2555 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 6
No. of basements: 1
No. of Plinths: 1
No. of Closed Parking: 73

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 557 to 651 sq ft 30 9
Shop 77 to 227 sq ft 8 0
Store 77 to 227 sq ft 8 2
Project Developer:
ABK REALTY
Organization Type: Partnership

Address: Flat No 2, 1St Floor, Taha Heights Tower, Opp Maulana Azad College, Rauza Bagh, Aurangabad (M Corp.), Aurangabad-431001

Office Phone: +91 97675 36188


Member details:
Member Name Designation
ABDUL RAHMAN JAVED KHAN Partner
SYED BILAL MOHIUDDIN QUADRI Partner
ABDUL RAHMAN JAVED KHAN Authorized Signatory
JAVED AHMED KHAN Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
SHAUKAT ALI KHAN SHABBIR ALI KHAN Individual Area Share


Other Professionals involved:
Professional Name Professional Type
KHAN RAFEY Contractor
Md. Nazeeruddin Architect
KHAN SOHEL Engineer
YASH NAGAR Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A New Landmark in Aurangabad: Introducing ABK Jagirdar Town Plaza

ABK Realty, a renowned partnership firm in Aurangabad, is proud to present its latest venture, ABK Jagirdar Town Plaza, a new development promising a unique blend of modern living and convenient location. Registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under the ID P51500047019, this project is poised to become a sought-after address in the city.

Located in the heart of Aurangabad, on CTS No. 2172/2, Makai Gate Road, Near Ghati, ABK Jagirdar Town Plaza offers excellent connectivity and easy access to various amenities. The project boasts a strategic location, bordered by CTS NO 21721 and CTS NO 21723 to the east, the House of Ramesh Gaikwad to the west, CTS NO 2151 and CTS NO 2153 to the north, and a 24-meter road to the south.

This new development is meticulously planned on a plot spanning 694 sqmts. The project encompasses 1 sanctioned building with a total of 6 floors, including 1 basement and 1 plinth floor. The project’s sanctioned FSI stands at 2555, ensuring ample built-up space for its residents.

ABK Jagirdar Town Plaza is designed to cater to the modern lifestyle, offering 73 closed parking spaces for residents and guests. While the project currently lacks any recreational open space, its prime location provides easy access to various green spaces and recreational facilities in the vicinity.

ABK Realty has a strong commitment to transparency and ethical practices. The project is free of any litigations, ensuring a hassle-free investment experience. The developers have partnered with HDFC Bank Limited (IFSC Code: HDFC0000713), offering residents convenient financial solutions for their investment.

With its strategic location, well-planned design, and focus on modern amenities, ABK Jagirdar Town Plaza promises to be an exceptional investment opportunity in Aurangabad.

Interested individuals are encouraged to contact ABK Realty at 9767536188 for further information and to explore the various residential options available in this exciting new development.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 55.51 6 1
2BHK 60.2 6 3
2BHK 60.51 6 3
STORE 13.23 1 1
STORE 17.82 2 0
STORE 18.06 2 0
STORE 21.12 2 1
STORE 7.2 1 0
Shop 7.2 1 0

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Disclosure of sold/ booked inventory
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 82

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 4 Disclosure of sold/ booked inventory

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 25
1 Overall Percentage of Completion of the work done For the entire Building /Wing 77

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 51.75 6 0
2BHK 53.08 6 2
2BHK 55.51 6 1
2BHK 60.2 6 3
2BHK 60.51 6 3
STORE 7.2 1 0
STORE 13.23 1 1
STORE 17.82 2 0
STORE 18.06 2 0
STORE 21.12 2 1
Shop 7.2 1 0
Shop 13.23 1 0
Shop 17.82 2 0
Shop 18.06 2 0
Shop 21.12 2 0

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 53.08 6 2

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 25
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 69.5

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [2]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of sold/ booked inventory [2]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Proforma of Allotment letter [2]
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal