MH
Aurangabad
P51500016122
RERA ID: P51500016122
Project Name: SARA PARIVARTAN SECTOR B - PH 2
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2023-04-20
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2022-04-21).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Sawangi, Naygaon Road, Aurangabad-431007

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
GUT NO. 234/2, HARSUL, SAWANGI, AURANGABAD

Boundaries:
9 MTR WIDE INTERNAL ROAD
12 MTR WIDE INTERNAL ROADN OTHER PROPERTY
WE
S
OTHER PROPERTY

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 3135 sq.mt.
Sanctioned Built-up Area: 6660 sq.mt.
Recreational Open Space: 1437 sq.mt.
No. of Buildings sanctioned: 4
No. of Floors sanctioned: 32
No. of Plinths: 4
No. of Stilts: 4
No. of Closed Parking: 44

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 308 to 322 sq ft 70 70
2BHK 450 to 493 sq ft 80 67
Shop 81 to 185 sq ft 13 11
Project Developer:
SARA PROPERTIES
Organization Type: Partnership

Address: 11, A-Wing, 1St Floor, Narayan Plaza, Cannaught Place, Cidco, Opp. Cannaught Garden, Aurangabad (M Corp.), Aurangabad-431003

Office Phone: +91 24024 81519
Website URL: www.sarabuilders.com


Member details:
Member Name Designation
SITARAM RATANLAL AGRAWAL Partner
RUPESH SITARAM AGRAWAL Partner
NILESH SITARAM AGRAWAL Authorized Signatory
NILESH SITARAM AGRAWAL Partner


Other Professionals involved:
Professional Name Professional Type
KOHINOOR CONSTRUCTIONS Contractor
ANAND DESHPANDE Architect
NAMDEV G KARKHANE Engineer
AMOL KSHIRSAGAR Other Professional


Projects in the state by this developer:
P51500053144 - RENUKA RESIDENCY - Aurangabad
P51500047831 - SARA SAMRUDDHI PHASE II - Aurangabad
P51500046066 - SARA SAMRUDDHI RH NO 29 TO 36, 77 TO 80 AND 111 TO 114 - Aurangabad
P51500034773 - SARA PARIVARTAN-AMENITY BUILDING-A - Aurangabad
P51500029499 - SARA PARIVARTAN G - 12, 13, 14 type building - Aurangabad
P51500016167 - SARA PARIVARTAN SECTOR A - Aurangabad
P51500016122 - SARA PARIVARTAN SECTOR B - PH 2 - Aurangabad
P51500013783 - SARA SAMRUDDHI - PHASE 1 - Aurangabad
P51500001468 - SARA PARIVARTAN - SECTOR B - PHASE 1 - Aurangabad
Litigations

Litigations related to the project ? No

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD) [4]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • Certificates of CA (Form 5)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Other
  • Proforma of Allotment letter [2]