RERA ID: P51500015899
Project Name: MY WORLD PLOT NO 3
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-12-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Chikalthana, Jalna Road, Aurangabad (M Corp.), Aurangabad-431210

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 3 GUT NO 708 CHIKALTHANA AURANGABAD

Boundaries:
12 MTR ROAD
OPEN SPACEN PART of GUT NO 708
WE
S
12 MTR ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 9376 sq.mt.
Sanctioned Built-up Area: 32054 sq.mt.
Recreational Open Space: 1545 sq.mt.
No. of Buildings sanctioned: 9
No. of Floors sanctioned: 76
No. of basements: 9
No. of Plinths: 9
No. of Podiums: 7
No. of Stilts: 9
No. of Closed Parking: 288

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 1308 to 1350 sq ft 18 9
4BHK 1725 to 1847 sq ft 18 12
Others 0 to 2658 sq ft 56 24
Shop 574 sq ft 1 0
Showroom 304 to 413 sq ft 5 0
Project Developer:
SIMAR PRIDE VENTURES LLP
Organization Type: Partnership

Address: Office No. 101, Sai Trade Center, Rto Office Road Aurangabad, Beside Mayor Bunglow, Behind Sales Tax Office, Aurangabad (M Corp.), Aurangabad-431005

Office Phone: +91 24023 45016


Member details:
Member Name Designation
NAVIN HANUMANPRASAD BAGADIYA Authorized Signatory
NITIN VENUPRASAD BAGADIYA Partner
RAJENDRA SING DHARAM SINGH RAJPAL Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
HIRAMAN RAMCHANDRA RITHE Individual Revenue Share
YAMAJI RAMCHANDRA RITHE Individual Revenue Share
SHANTILAL BABAN RITHE Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
AKW ASSOCIATES Architect


Projects in the state by this developer:
P51500050146 - One World Phase I - Aurangabad
P51500019553 - My Home - Aurangabad
P51500015899 - MY WORLD PLOT NO 3 - Aurangabad
P51500015862 - MY WORLD PLOT NO 2 BUILDING D1 TO D6 - Aurangabad
P51500015842 - MY WORLD BUILDING B7-B8-B9 - Aurangabad
P51500015814 - MY WORLD BUILDING B4-B5-B6 - Aurangabad
P51500015790 - MY WORLD BUILDING A3 - Aurangabad
P51500015785 - MY WORLD BUILDING A1-A2 - Aurangabad
P51500015775 - MY WORLD BUILDING A4 - Aurangabad
P51500015772 - MY WORLD BUILDING B1-B2-B3 - Aurangabad
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
Ninth Civil Judge Senior division Aurangabad Mr Rajendra Tuwar RCS 128/2020 Civil Suit 2020 Pending
Civil Judge Senior division 486/2020 Civil Suit 2020 Pending
Civil Judge Senior Division 38/2021 Civil Other 2021 Disposed
Civil Judge Senior division Aurangabad RCS/538/2020 Civil Suit 2020 Disposed
Civil Judge Senior division Aurangabad RCS/729/2020 Civil Suit 2020 Disposed
Civil Judge Senior Division RCS-546/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-550/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-847/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-1596/2022 Civil Suit 2022 Pending
Sub Division Officer Aurangabad 90/2021 Civil Appeal 2021 Pending
Honourable High Court of Bombay Auranagabad 7171/2020 Civil Writ Petition 2020 Pending
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A Glimpse into “MY WORLD PLOT NO 3”: A New Real Estate Development in Aurangabad

“MY WORLD PLOT NO 3,” registered under RERA ID P51500015899, is a new real estate project located in the heart of Chikalthana, Aurangabad. Developed by Simar Pride Ventures LLP, this project promises to be a unique addition to the city’s skyline, offering a range of residential and commercial units with a focus on modern living and convenience.

The project, currently under construction and slated for completion by December 2026, is situated on a plot spanning 9376 square meters, strategically located on Jalna Road. It encompasses nine buildings, each reaching a height of seven floors, with a total sanctioned built-up area of 32054 square meters. While the project boasts a significant recreational open space of 1545 square meters, it is important to note that it currently faces litigation, which potential investors should be aware of.

“MY WORLD PLOT NO 3” offers a diverse selection of units catering to varied needs. Residents can choose from 3BHK and 4BHK apartments ranging from 1308 to 1847 square feet, providing spacious and well-designed living spaces. The project also includes a number of “Others” units, ranging from 0 to 2658 square feet, offering flexibility for various purposes. Commercial units are also available, with a single shop of 574 square feet and five showrooms ranging from 304 to 413 square feet.

The project features a well-planned infrastructure with nine basements, nine plinths, seven podiums, and nine stilts, providing ample parking space and modern amenities. A total of 288 closed parking spaces are available within the complex.

While “MY WORLD PLOT NO 3” holds the promise of a luxurious and well-equipped residential and commercial space, potential investors need to be cognizant of the existing litigation surrounding the project. Further investigation into the nature and impact of these legal issues is essential before making any investment decisions.

This comprehensive introduction provides a foundation for understanding “MY WORLD PLOT NO 3,” encouraging further research and due diligence before considering an investment. It is critical to obtain all relevant information and evaluate the project’s potential risks and benefits carefully.

New documents listed below were uploaded to the Documents section:

  • 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

There are modifications under Cases section

Court Name Case Number Case Type Petition Name Year Present Status
Civil Judge Senior Division 38/2021 Civil Other 2021 Disposed

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 X number of Podiums 100
1 Stilt Floor 100
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
1 Overall Percentage of Completion of the work done For the entire Building /Wing 94
2 X number of Basement(s) and Plinth 100
2 X number of Podiums 100
2 Stilt Floor 100
2 X number of Slabs of Super Structure 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
2 Overall Percentage of Completion of the work done For the entire Building /Wing 94
3 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
3 Stilt Floor 100
3 X number of Slabs of Super Structure 100
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
3 Overall Percentage of Completion of the work done For the entire Building /Wing 94
4 X number of Basement(s) and Plinth 100
4 X number of Podiums 100
4 Stilt Floor 100
4 X number of Slabs of Super Structure 100
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
4 Overall Percentage of Completion of the work done For the entire Building /Wing 94
5 X number of Basement(s) and Plinth 100
5 X number of Podiums 100
5 Stilt Floor 100
5 X number of Slabs of Super Structure 100
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
5 Overall Percentage of Completion of the work done For the entire Building /Wing 94

 

There are modifications under Cases section

Court Name Case Number Case Type Petition Name Year Present Status
Civil Judge Senior Division RCS-550/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-546/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-847/2021 Civil Suit 2021 Pending
Civil Judge Senior Division RCS-1596/2022 Civil Suit 2022 Pending

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 121.58 9 6
3BHK 125.42 9 3
4BHK 160.27 1 0
4BHK 162.96 1 0
4BHK 168.92 8 5
4BHK 171.61 8 7
5BHK & more 0 0 0
5BHK & more 225.42 4 2
5BHK & more 227.27 9 7
5BHK & more 234.64 8 1
5BHK & more 219.16 1 1
5BHK & more 226.35 8 3
5BHK & more 227.27 9 8
5BHK & more 225.73 3 1
5BHK & more 247.01 8 1
5BHK & more 218.63 1 0
5BHK & more 226.25 1 0
5BHK & more 227.31 1 0
5BHK & more 239.68 1 0
Business Center 33.12 1 0
Coffee Shop 53.37 1 0
Parlour 109.62 1 0
Showroom 28.27 1 0
Showroom 37.99 1 0
Showroom 38.43 3 0

 

New documents listed below were uploaded to the Documents section:

  • 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

New documents listed below were uploaded to the Documents section:

  • 23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 12 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD) [61]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [22]
  • Certificates of CA (Form 5)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [23]
  • Commencement Certificates / NA Order for plotted development [3]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [11]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) [4]
  • Form 2A [13]
  • Other [3]
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.)