MH
Yavatmal
P51000048632
RERA ID: P51000048632
Project Name: AAMER TOWNSHIP
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-10-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Near Santdham, Kayar Road, Ganeshpur, Wani, Yavatmal-445304

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 1 S.NO 2/4

Boundaries:
SUREY NO 88
SURVEY NO 2 BY 3N SURVEY NO 2 by 5
WE
S
SURVEY NO 3

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 5120 sq.mt.
Sanctioned Built-up Area: 1 sq.mt.
Recreational Open Space: 883 sq.mt.
No. of Buildings sanctioned: 3
No. of Floors sanctioned: 6
No. of Plinths: 3

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Others 653 to 825 sq ft 44 0
Project Developer:
ZAMEER KHAN MAHEBOOB KHAN KHAN c/o MEHEBOOB KHAN AJMER KHAN
Organization Type: Individual

Address: Ward No 4, Mominpura, Wani, Wani (M Cl), Yavatmal-445304

Office Phone: +91 72397 86786


Other Professionals involved:
Professional Name Professional Type
SWAPNIL DAKHANE Architect
SWAPNIL DAKHANE Engineer
NILESH KATARIYA Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing AAMER TOWNSHIP: A Serene Residential Haven in Ganeshpur

Nestled amidst picturesque landscapes in the vibrant village of Ganeshpur, Maharashtra, AAMER TOWNSHIP emerges as a promising new residential project. With its RERA-registered status (P51000048632), this development by esteemed builders offers aspiring homeowners an unparalleled living experience.

Project Highlights

  • Project Name: AAMER TOWNSHIP
  • Project Type: Residential
  • Project Area: 5,120 square meters
  • Number of Buildings: 3
  • Number of Floors: 6
  • Proposed Completion Date: October 31, 2025
  • Status: New Project

Location Advantages

AAMER TOWNSHIP is strategically located in Ganeshpur, providing residents with easy access to essential amenities such as schools, hospitals, and shopping centers. Its proximity to the Kayar Road offers seamless connectivity to the surrounding areas.

Amenities and Infrastructure

This meticulously planned project boasts an array of amenities designed to elevate residents’ lifestyles. The development features a spacious recreational open space, providing ample opportunities for leisure and recreation. The three buildings offer a choice of well-appointed units ranging from 653 to 825 square feet, catering to diverse space requirements.

Promoter and Development Details

AAMER TOWNSHIP is developed by a reputable builder with an unwavering commitment to quality and customer satisfaction. The project is financially supported by the esteemed State Bank of India, ensuring financial stability and transparency.

Conclusion

AAMER TOWNSHIP represents an exceptional opportunity to own a home in a serene and convenient location. Its thoughtfully designed units, modern amenities, and prime location make it an ideal choice for families seeking a peaceful and fulfilling lifestyle. As the project progresses towards completion, we invite you to explore the possibilities and embark on a journey of homeownership.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 40
1 X number of Basement(s) and Plinth 40
1 X number of Slabs of Super Structure 40
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 25.5
2 Excavation 40
2 X number of Basement(s) and Plinth 40
2 X number of Slabs of Super Structure 40
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
2 Overall Percentage of Completion of the work done For the entire Building /Wing 25.5
3 Excavation 40
3 X number of Basement(s) and Plinth 40
3 X number of Slabs of Super Structure 40
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
3 Overall Percentage of Completion of the work done For the entire Building /Wing 25.5

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 2 Disclosure of sold/ booked inventory
  • 1 Disclosure of sold/ booked inventory
  • 3 Disclosure of sold/ booked inventory
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Other – Legal
  • 2 Other – Legal
  • 3 Other – Legal
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 1 Other – Legal
  • 4 Disclosure of sold/ booked inventory

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Supply : 15 WIP
Water Conservation, Rain water Harvesting : 35 WIP
Internal Roads & Footpaths : 25 WIP
Landscaping & Tree Planting : 25 WIP
Street Lighting : 35 WIP

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
ROW HOUSE TYPE B 60.71 4 0
ROW HOUSE TYPE C 62.36 11 0

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Proforma of Agreement for sale [3]
  • Proforma of Allotment letter [2]
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal