MH
Satara
P52700033846
RERA ID: P52700033846
Project Name: MONITA PARK B BUILDING
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Near Sajai Garden, Near Vinchurni Road, Jadhavwadi (563279), Phaltan, Satara-415523

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S.NO. 53/1B PLOT NO. 2

Boundaries:
S NO 53 PART 1A PLOT NO 7
STREAMN ROAD
WE
S
S NO 53 PART 1B PLOT NO 1

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 978 sq.mt.
Sanctioned Built-up Area: 2192 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Open Parking: 34

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 378 to 394 sq ft 24 15
2BHK 580 sq ft 12 9
Project Developer:
UNITY DEVELOPERS
Organization Type: Partnership

Address: Shinganapur Road, Near Ladies Hostel, Phaltan, Phaltan (M Cl), Satara-415523

Office Phone: +91 98224 30599


Member details:
Member Name Designation
SANJAY SHRIRANG MOHOLKAR Partner
JAVID MAHAMUD TAMBOLI Partner
PRAMOD SUBHASHRAO NIMBALKAR Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
NETAJI TATYABA CHORAMALE Individual Revenue Share
NANA HARI CHORAMALE Individual Revenue Share
RAHUL RAMCHANDRA CHORAMALE Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
Mahendra Jadhav Architect
Rajendra Bhaskar Thorat Engineer
Rahul Jadhav Chartered Accountant


Projects in the state by this developer:
P52700033846 - MONITA PARK B BUILDING - Satara
P99000032753 - SHREE VASTU COMPLEX - Palghar
P53100027432 - UNITY ICON - Sangli
P53000026990 - LAXMI NARAYAN SANKUL - Kolhapur
P52700018337 - MONITA PARADISE - Satara
P52700015941 - MONITA PARK A BUILDING - Satara
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing the Monita Park B Building: A Residential Retreat in Pastoral Serenity

In the tranquil surroundings of Jadhavwadi, Satara District, a new residential project is taking shape—the Monita Park B Building. Nestled amidst verdant landscapes and flowing streams, this development promises a harmonious blend of modern living and serene tranquility.

Undertaken by UNITY DEVELOPERS, a reputable partnership firm, this project holds RERA ID P52700033846. Its construction is scheduled to be completed by December 31, 2025, ensuring timely delivery for homebuyers.

Spanning an expansive plot measuring 978 square meters, the Monita Park B Building comprises a single residential tower with seven sanctioned floors. The project offers a diverse range of apartments, including 24 spacious 1BHK units ranging from 378 to 394 square feet and 12 comfortable 2BHK units measuring 580 square feet.

The development boasts an impressive array of amenities to enhance the comfort and convenience of its residents. These include a total of 34 open parking spaces, ensuring ample room for vehicles. The project has been thoughtfully designed to maximize natural light and ventilation, creating a bright and airy living environment.

Located in close proximity to local amenities such as the Vinchurini Road and the serene Sajai Garden, the Monita Park B Building offers unparalleled connectivity and accessibility. Its verdant surroundings provide a welcome respite from the hustle and bustle of urban life, offering tranquility and peace of mind.

With its prime location, modern amenities, and competitive pricing, the Monita Park B Building presents an exceptional investment opportunity for discerning homebuyers. Whether you seek a serene retreat or a lucrative investment, this project is designed to meet your every need. Join us as we embark on this extraordinary journey of creating a residential haven in the heart of Jadhavwadi.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 35.15 12 8
1BHK 36.63 12 7
2BHK 53.94 12 9

 

New documents listed below were uploaded to the Documents section:

  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Conservation, Rain water Harvesting : 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : 100 Completed
Open Parking : 100 Completed
Water Supply : 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 Completed
Landscaping & Tree Planting : 100 Completed

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 36.63 12 7

 

New documents listed below were uploaded to the Documents section:

  • 3 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 80

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 35.15 12 8
1BHK 36.63 12 6
2BHK 53.94 12 9

 

New documents listed below were uploaded to the Documents section:

  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Electrical Meter Room, Sub-Station, Receiving Station : 100 After Completion of Building
Open Parking : 100 -
Water Supply : 100 At present Bore Well
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 Only Septic Tank Built
Landscaping & Tree Planting : 100 Only Tree Plantation
Water Conservation, Rain water Harvesting : 100 -

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [3]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development [2]