MH
Raigarh
P52000047020
RERA ID: P52000047020
Project Name: Jindal Park
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Panvel, Akurli, Raigarh-410206

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
G No 9/A & 10

Boundaries:
G No 8
G No 9BN G No 4
WE
S
G No 16

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 3060 sq.mt.
Sanctioned Built-up Area: 3056 sq.mt.
Recreational Open Space: 308 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 8
No. of Plinths: 2
No. of Stilts: 2
No. of Open Parking: 11
No. of Closed Parking: 16

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 271 to 301 sq ft 74 30
1RK 196 sq ft 1 0
2BHK 387 to 406 sq ft 9 2
Project Developer:
Simran Enterprises
Organization Type: Partnership

Address: Room No.16, Daria Building, Dr.Dadabhai Navroji Rd, Flora Fountain, Mumbai, Mumbai City-400023

Office Phone: +91 22278 11295


Member details:
Member Name Designation
Sachin Omprakash Agarwal Partner
Sagar Sachin Agarwal Authorized Signatory
Sagar Sachin Agarwal Partner
Akash Sachin Agarwal Partner


Other Professionals involved:
Professional Name Professional Type
CONTRUXUS Contractor
AN Arch Neha Jain Architect
Adharshila Consultants (Mr.Samarth Agarwal) Engineer
Mr. Vallabh Joshi Chartered Accountant


Projects in the state by this developer:
P52000047020 - Jindal Park - Raigarh
P52000024151 - Building No.3,Uptown Avenue - Raigarh
P52000023509 - Sakasi Greens - Raigarh
P52000016037 - Building no. 1 , Uptown Avenue - Raigarh
P51900001068 - Building No. 2, Uptown Avenue - Raigarh
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Jindal Park: A Residential Oasis in Panvel

Embark on a luxurious residential experience with Jindal Park, a new and promising project registered under RERA ID: P52000047020. This prestigious development, brought to you by Simran Enterprises, is meticulously designed to offer an unparalleled living space in the heart of Panvel.

Nestled amidst the serene lands of Akurli, Jindal Park sprawls over a substantial 3060 square meters. With two stately buildings gracing the skyline, the project boasts 83 meticulously planned units. Ranging from compact 1RKs to spacious 2BHKs, each apartment is thoughtfully crafted to meet the diverse needs of discerning homebuyers.

The development exudes sophistication with its elegant facade and contemporary interiors. Its meticulously designed layout maximizes natural light and ventilation, creating a vibrant and airy ambiance. Each unit is adorned with premium finishes, including vitrified tiles, granite countertops, and high-quality sanitary fittings.

Beyond its luxurious abodes, Jindal Park offers a plethora of amenities to elevate your lifestyle. Take a refreshing dip in the sparkling swimming pool, stay fit at the state-of-the-art gym, or indulge in social gatherings at the designated community hall. For your convenience, ample parking spaces are available, both open and enclosed, ensuring seamless access to your vehicles.

The project’s location in Panvel is a testament to its strategic accessibility. Situated in close proximity to major highways, schools, hospitals, and shopping malls, Jindal Park provides a seamless blend of urban convenience and suburban tranquility.

Scheduled for completion in March 2025, Jindal Park is a testament to Simran Enterprises’ commitment to excellence. With no pending litigations and a clear title, you can rest assured that your investment in this project is secure and promising.

Indulge in the exceptional living experience offered by Jindal Park. Whether you seek a spacious family home or a cozy retreat, this project offers a myriad of options to match your aspirations. Elevate your lifestyle and embrace the future in this remarkable residential haven.

New documents listed below were uploaded to the Documents section:

  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 78
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
2 Overall Percentage of Completion of the work done For the entire Building /Wing 78

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Landscaping & Tree Planting : 100
Sewerage (Chamber, Lines, Septic Tank , STP) : 80
Water Supply : 100 Boring Installed
Aggregate area of recreational Open Space : 100
Electrical Meter Room, Sub-Station, Receiving Station : 100
Water Conservation, Rain water Harvesting : 100 Rain Water Harvesting Pit
Internal Roads & Footpaths : 80

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.5 30 13
1BHK 27 2 2
1BHK 27.25 8 2
1BHK 27.5 4 3

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 71
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 71

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.25 14 8
1BHK 26.5 30 10
1BHK 27 2 1
1BHK 27 3 0
1BHK 27.25 8 1
1BHK 27.5 4 2

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
1 Overall Percentage of Completion of the work done For the entire Building /Wing 56.5
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 56.5

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 26.25 14 7
1BHK 26.5 30 7
1BHK 26.75 6 1
2BHK 36 4 1

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 16 2 0

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [4]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement [2]
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal