MH
Pune
P52100023268
RERA ID: P52100023268
Project Name: Kalpataru Exquisite - Wing 4
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Wakad, Mont Vert Tropez, Mulshi, Pune-411057

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S.No. 255/1,255/1/1,255/1/2,255/1/3, 255/3A/1, 255/3A/2, 255/3B, 256/1/1, 256/2/2, 256/2/1

Boundaries:
Blance Portion of KL Exqusite and SNo 256 P
Blance Portion of KL Exquisite and Wing 3N Blance Portion of KL Exq Nd SNO 255 P Nd SNo 256 P
WE
S
Balance Portion of KL Exquiste and S No 254-1

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 864 sq.mt.
Sanctioned Built-up Area: 0 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 24
No. of Plinths: 1
No. of Podiums: 3
No. of Closed Parking: 594

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 102356 sq ft 132 132
Project Developer:
Kalpataru Retail Ventures Private Limited
Organization Type: Company

Address: 101, Kalpataru Synergy, Vakola, Santacruz East, Opp. Grand Hyatt, Andheri, Mumbai Suburban-400055

Office Phone: +91 22306 45000
Website URL: www.kalpataru.com


Member details:
Member Name Designation
Jayant Chaganlal Oswal Authorized Signatory
Amit Shah Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
Tricon Infra Buildtech Pvt.Ltd Contractor
Abhiyanta Electrical consultantns & Engineers. (Electric Consultant) Other Professional
Engineering Creations Public Health Consultancy Pvt. Ltd (Plumbing Consultant) Other Professional
Landmark Planners (Liaison Architect) Other Professional
Mandviwala Qutub Associates (Design Architect) Other Professional


Projects in the state by this developer:
P51800027059 - Kalpataru Vienta Tower A - Mumbai Suburban
P51800023768 - Kalpataru Vienta Tower B - Mumbai Suburban
P52100023268 - Kalpataru Exquisite - Wing 4 - Pune
P52100018100 - Kalpataru Exquisite - Wing 3 - Pune
P52100016932 - Kalpataru Exquisite - Wing D - Pune
P52100001266 - Kalpataru Exquisite - Wing 2 - Pune
P52100000298 - Kalpataru Exquisite - Wing 1 - Pune
Litigations

Active Litigations related to the project ? Yes

Cases
Court Name Case Number Case Type Petition Name Year Present Status
Civil Judge Senior Division Pune 1292 Civil Suit 2014 Pending
Civil Judge Senior Division Pune 1180 Civil Suit 2019 Pending
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Kalpataru Exquisite - Wing 4: A New Residential Project in Wakad, Pune

Kalpataru Exquisite - Wing 4, a new residential project by Kalpataru Retail Ventures Private Limited, promises a luxurious living experience in the prime location of Wakad, Pune. This project, with RERA ID P52100023268, is currently under development and is expected to be completed by December 30, 2025.

Located within the Mont Vert Tropez area, the project spans across 864 square meters of land (S.No. 255/1, 255/1/1, 255/1/2, 255/1/3, 255/3A/1, 255/3A/2, 255/3B, 256/1/1, 256/2/2, 256/2/1) and boasts a total permissible built-up area of 10500 square meters. This single-wing project consists of 24 sanctioned floors, offering a variety of residential units.

While the project is currently facing some litigation, Kalpataru Exquisite - Wing 4 is designed to provide a sophisticated living experience with its numerous amenities. These include a dedicated parking facility accommodating 594 vehicles, 3 podium levels, and 1 plinth level. The project aims to enhance the quality of life for residents, offering a comfortable and convenient lifestyle within a flourishing community.

Potential investors and homebuyers can find detailed information about the project, including the sanctioned plans, on the Maharashtra Real Estate Regulatory Authority (MahaRERA) website. For any inquiries, one can contact the developer at their registered office address: Kalpataru Synergy, Block 101, Vakola, Santacruz East, Mumbai, Maharashtra 400055 or call them at 2230645000. Further information can also be found on the developer’s website, www.kalpataru.com.

This essay provides a brief overview of Kalpataru Exquisite - Wing 4, highlighting key details relevant to potential investors and buyers. It is crucial to conduct thorough research and consult with relevant authorities before making any investment decisions, considering the ongoing legal disputes associated with the project.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 92
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 58
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 24
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 39
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 19
1 Overall Percentage of Completion of the work done For the entire Building /Wing 43.2

 

New documents listed below were uploaded to the Documents section:

  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Landscaping & Tree Planting : 88 To be done before completion of Whole Project
Internal Roads & Footpaths : 80 To be done before completion of Whole Project

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Types of 3 BHK 9509.23 132 132

 

New documents listed below were uploaded to the Documents section:

  • 4 Disclosure of sold/ booked inventory

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 0
1 X number of Slabs of Super Structure 83
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 38
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 12
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 24
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
1 Overall Percentage of Completion of the work done For the entire Building /Wing 37.1

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Treatment And Disposal Of Sewage And Sullage Water : 100 To be done before completion of Whole Project
Landscaping & Tree Planting : 85 To be done before completion of Whole Project
Internal Roads & Footpaths : 76 To be done before completion of Whole Project
Aggregate area of recreational Open Space : 50 2286.49 Sq.Mt Common for Whole Project

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 594 590 88

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Types of 3 BHK 9509.23 132 132

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Conservation, Rain water Harvesting : 100 To be done before completion of Whole Project
Landscaping & Tree Planting : 77 To be done before completion of Whole Project

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 58
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 14
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 19
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 2
1 Overall Percentage of Completion of the work done For the entire Building /Wing 39.3

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [3]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Disclosure of sold/ booked inventory [2]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20) [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [4]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter [2]