MH
Mumbai Suburban
P51800027059
RERA ID: P51800027059
Project Name: Kalpataru Vienta Tower A
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-06-30
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Kandivali East, Ashok Nagar Main Road, Borivali, Mumbai Suburban-400101

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
CTS no - 94C PT,94B PT of village wadhavan

Boundaries:
CTS no- 94B PT 94C PT of village wadhavan
CTS no - 94B PT 94C PT of village wadhavanN CTS No- 94C PT of Village Wadhavan
WE
S
CTS no- 94B PT 94C PT of village wadhavan

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 1119 sq.mt.
Sanctioned Built-up Area: 21094 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 39
No. of basements: 2
No. of Plinths: 2
No. of Podiums: 4
No. of Stilts: 1
No. of Closed Parking: 416

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 52890 sq ft 71 70
3BHK 107325 sq ft 105 89
Others 1564 to 32217 sq ft 33 32
Shop 5592 sq ft 8 0
Project Developer:
Kalpataru Retail Ventures Private Limited
Organization Type: Company

Address: 101, Kalpataru Synergy, Vakola, Santacruz East, Opp. Grand Hyatt, Andheri, Mumbai Suburban-400055

Office Phone: +91 22306 45000
Website URL: www.kalpataru.com


Member details:
Member Name Designation
Jayant Chaganlal Oswal Authorized Signatory
Amit Shah Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
M/S JP Enterprises Contractor
Nandkumar V Jethe Architect
Vikram Panchal Engineer
Khimji Kunverji & Co (Statutory Auditor - Form 5) Chartered Accountant
C R Mohnot & Co ( CA Certificate-Form 3) Chartered Accountant
Design Architect-Mandviwala Qutub & Associate Other Professional
Structural Consultant-RECI Engineering Pvt. Ltd. Other Professional
MEP Consultant-S.N.Joshi Consultants Pvt.Ltd. Other Professional
Project Architect-Atul Gulati Gala Other Professional


Projects in the state by this developer:
P51800027059 - Kalpataru Vienta Tower A - Mumbai Suburban
P51800023768 - Kalpataru Vienta Tower B - Mumbai Suburban
P52100023268 - Kalpataru Exquisite - Wing 4 - Pune
P52100018100 - Kalpataru Exquisite - Wing 3 - Pune
P52100016932 - Kalpataru Exquisite - Wing D - Pune
P52100001266 - Kalpataru Exquisite - Wing 2 - Pune
P52100000298 - Kalpataru Exquisite - Wing 1 - Pune
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Unveiling Kalpataru Vienta Tower A: A New Era of Luxury Living in Kandivali East

Kalpataru Vienta Tower A, a prestigious residential project by Kalpataru Retail Ventures Private Limited, is set to redefine luxury living in the bustling neighborhood of Kandivali East, Mumbai. With its strategic location on Ashok Nagar Main Road and a RERA ID of P51800027059, this new project promises a lifestyle of unparalleled comfort and convenience.

Sited on a sprawling plot of 1119 square meters, Kalpataru Vienta Tower A boasts a single, majestic building rising to an impressive 39 floors. The project is designed to maximize space and natural light, offering a range of meticulously crafted residences that cater to diverse needs and preferences. The building’s unique architectural design and thoughtfully planned amenities ensure residents enjoy a harmonious blend of privacy and communal living.

A Prime Location at the Heart of Kandivali East

Kalpataru Vienta Tower A benefits from its prime location in Kandivali East, a thriving neighborhood known for its excellent connectivity, renowned schools, and vibrant social life. With easy access to major arterial roads and public transportation, residents can seamlessly navigate the city. The project’s close proximity to renowned shopping malls, entertainment hubs, and healthcare facilities ensures a fulfilling lifestyle for its residents.

Amenities Designed to Elevate Everyday Living

Kalpataru Vienta Tower A is meticulously designed to cater to the modern lifestyle. The project boasts a comprehensive range of amenities, including:

  • Spacious and Secure Parking: With 416 closed parking spaces, residents can rest assured knowing their vehicles are safe and secure.
  • Multi-Level Living: The project features two basements, two plinths, and four podium levels, providing ample space for diverse amenities and communal areas.
  • Unparalleled Comfort and Convenience: Kalpataru Vienta Tower A offers an array of amenities designed to enhance residents’ well-being, ensuring a fulfilling and enjoyable living experience.

A Trusted Developer with a Legacy of Excellence

Kalpataru Retail Ventures Private Limited, a reputable and established name in the real estate industry, brings decades of experience and commitment to quality to this project. Their unwavering dedication to delivering exceptional projects and building enduring communities is evident in every aspect of Kalpataru Vienta Tower A.

Investment Opportunity with a Promising Future

Kalpataru Vienta Tower A presents an exceptional investment opportunity. With its prime location, world-class amenities, and the renowned developer’s commitment to excellence, this project offers a promising future for residents and investors alike. The project is scheduled for completion in June 2027, providing ample time to plan and secure your dream home.

Join the Kalpataru Vienta Tower A Community

For those seeking a luxurious lifestyle in a vibrant and well-connected community, Kalpataru Vienta Tower A presents an unparalleled opportunity. Experience the future of living in Kandivali East and embark on a journey of comfort, convenience, and fulfillment.

New documents listed below were uploaded to the Documents section:

  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 71
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 26
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 8
1 Overall Percentage of Completion of the work done For the entire Building /Wing 62.8

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 9970.85 105 89

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 416 310 87

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 8 To be done before completion of Whole Project
Water Supply : 54 To be done before completion of Whole Project
Fitness Centre, swimming Pool & Other recreation areas : 34 Proposed Common Amenities as per AFS
Electrical Meter Room, Sub-Station, Receiving Station : 40 Electrical Meter Room and Sub station only
Fire Protection And Fire Safety Requirements : 30 To be done before completion of Whole Project

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 6 Disclosure of sold/ booked inventory

 

Number of Sanctioned Floors field under Building/Plot Details section updated with new value 39

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 6 To be done before completion of Whole Project
Fitness Centre, swimming Pool & Other recreation areas : 26 Proposed Common Amenities as per AFS
Water Conservation, Rain water Harvesting : 40 To be done before completion of Whole Project

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3.5BHK 2993.14 29 29
3.5BHKDuplex 145.31 1 1
3BHK 9970.85 105 85

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 63
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 24
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 3
1 Overall Percentage of Completion of the work done For the entire Building /Wing 59.5

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 416 302 84

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 4913.73 71 70
3BHK 9970.85 105 75

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 48
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 2
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 18
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.1

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 416 278 75

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [3]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [4]
  • Copy of Layout Approval (in case of layout) [4]
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate [4]
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [4]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Proforma of Allotment letter
  • Status of Formation of Legal Entity (Society/Co Op etc.)