MH
Pune
P52100001305
RERA ID: P52100001305
Project Name: BELLINA PHASE 2 - COMMERCIAL
Project Type: Commercial
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2018-09-30
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2018-03-31, 2018-03-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
, Lohgaon, Haveli, Pune-411047

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S.NO. 282 2 3 2, 282 2 3 3

Boundaries:
9 MTR WIDE ROAD
S NO 282 PARTN PLOT NO 1
WE
S
S NO 281

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 761 sq.mt.
Sanctioned Built-up Area: 1068 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 5
No. of Plinths: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Office 111 to 247 sq ft 30 6
Shop 544 sq ft 1 1
Project Developer:
Gini Construction Pvt Ltd
Organization Type: Company

Address: 3D C Wing, Gulmohar Apartment, Gen Thimmaya Road, East Street, Above Sbi, Pune (Cb), Pune City, Pune-411001

Office Phone: +91 20668 74444
Website URL: http://giniconstructions.com


Member details:
Member Name Designation
Deeapk Vishwanath Harlalka Managing Director
SACHIN SHANTARAM RAUT Authorized Signatory
Manish Vinod Harlalka Managing Director
Gautam Vinod Harlalka Managing Director


Other Professionals involved:
Professional Name Professional Type
PARVEZ JAMADAR AND ASSOCIATES Architect


Projects in the state by this developer:
P52100054760 - GINI ARIA - PHASE 2 - Pune
P52100031664 - GINI ARIA MHADA WING - Pune
P52100013814 - GINI ARIA - PHASE I - Pune
P52100001305 - BELLINA PHASE 2 - COMMERCIAL - Pune
P52100000902 - BELLINA PHASE 3 - Pune
Litigations

Litigations related to the project ? No

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • Certificates of Architect (Form 4) [3]
  • Certificates of CA (Form 5)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development [2]
  • Other
  • Proforma of Allotment letter [2]