RERA ID: P52100000902
Project Name: BELLINA PHASE 3
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2020-09-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2019-03-31).
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
, Lohgaon, Haveli, Pune-411047

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S.NO. 282/2/3/2, 282/2/3/3

Boundaries:
9 MTR WIDE ROAD
S NO 282 PARTN PLOT NO 1
WE
S
S NO 281

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 2758 sq.mt.
Sanctioned Built-up Area: 3026 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 525 to 810 sq ft 24 24
Others 426 to 890 sq ft 25 25
Project Developer:
Gini Construction Pvt Ltd
Organization Type: Company

Address: 3D C Wing, Gulmohar Apartment, Gen Thimmaya Road, East Street, Above Sbi, Pune (Cb), Pune City, Pune-411001

Office Phone: +91 20668 74444
Website URL: http://giniconstructions.com


Member details:
Member Name Designation
Deeapk Vishwanath Harlalka Managing Director
SACHIN SHANTARAM RAUT Authorized Signatory
Manish Vinod Harlalka Managing Director
Gautam Vinod Harlalka Managing Director


Other Professionals involved:
Professional Name Professional Type
Parvez Jamadar Architect


Projects in the state by this developer:
P52100054760 - GINI ARIA - PHASE 2 - Pune
P52100031664 - GINI ARIA MHADA WING - Pune
P52100013814 - GINI ARIA - PHASE I - Pune
P52100001305 - BELLINA PHASE 2 - COMMERCIAL - Pune
P52100000902 - BELLINA PHASE 3 - Pune
Litigations

Litigations related to the project ? No

New documents listed below were uploaded to the Documents section:

  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Architect’s Certificate on Completion of Project (Form 4)
  • Building Plan Approval (IOD) [3]
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • Certificates of CA (Form 5)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development [2]
  • Other
  • Proforma of Allotment letter [2]