MH
Palghar
P99000053269
RERA ID: P99000053269
Project Name: SERENO
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-12-30
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2026-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Vasai, Gokhiware, Vasai-Virar City (M Corp), Palghar-401208

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
SURVEY NO 76, SURVEY NO 82, HISSA NO 1,2,3/3,8/1,10

Boundaries:
12 M W ROAD
20 M W ROADN SEC III BLDG NO 3 A-WING
WE
S
SEC II BLDG NO 2 D-WING

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1462 sq.mt.
Sanctioned Built-up Area: 28636 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 44
No. of Plinths: 2
No. of Podiums: 4
No. of Stilts: 2
No. of Open Parking: 14
No. of Closed Parking: 2

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 298 to 514 sq ft 249 42
2BHK 321 to 533 sq ft 183 49
Shop 102 to 240 sq ft 17 11
Project Developer:
TRIO INFRASTRUCTURE PRIVATE LIMITED
Organization Type: Company

Address: Shop No 8, Gokul Regency-Ii, Thakur Complex, Asha Nagar, Nr Videocon Tower, Kandivali, Borivali, Mumbai Suburban-400101

Office Phone: +91 22287 00358


Member details:
Member Name Designation
BALAJI RAGHAVAN Director
MANOJSHANKAR AMBIKAPRASAD TRIPATHI Director


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Anil Ramchandra Gupta Individual Revenue Share
Devendra Rajanikant Ladhani Individual Revenue Share
Mukesh Shivdas Sonar Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
SEWRI ENGINEERING COMPANY PVT LTD Contractor
MUKESH KUMAR Engineer
SANAT MEHTA & ASSOCIATES Architect
S C SHAH & COMPANY Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Sereno: A New Residential Development in Vasai

Sereno, a new residential project by Trio Infrastructure Private Limited, is poised to transform the landscape of Vasai, Maharashtra. Approved under RERA with ID P99000053269, this project promises a contemporary living experience in a prime location.

Location: Nestled in the heart of Vasai, Sereno enjoys a strategic location at Gokhiware, Vasai, with easy access to essential amenities and key infrastructure. Situated between the well-established SEC III Building and a 20-meter wide road, the project benefits from excellent connectivity and a peaceful environment.

Project Overview: Sereno is designed as a two-building complex spread across a spacious 1462 square meters. The project has been sanctioned for 44 floors, including 2 stilts and 2 podiums, offering a wide range of meticulously planned 1BHK and 2BHK apartments. The project boasts a total sanctioned built-up area of 28636 square meters and includes 17 retail shops, providing convenience and a sense of community.

Apartment Options:

  • 1BHK: A wide selection of 1BHK apartments, ranging from 298 to 514 square feet, caters to different preferences and budgets.
  • 2BHK: Sereno also offers spacious 2BHK apartments ranging from 321 to 533 square feet, ideal for growing families.

Amenities and Infrastructure:

  • Parking: The project provides 14 open parking spaces and 2 closed parking spaces for residents’ convenience.
  • Open Spaces: Though the project doesn’t offer dedicated recreational open spaces as per the sanctioned plan, the location itself benefits from proximity to green spaces and well-maintained roads.

Completion Timeline:
The project is currently under construction and is expected to be completed by December 31, 2026. However, an extended completion date has been set for December 30, 2027, providing assurance to potential buyers.

Transparency and Trust:
Trio Infrastructure Private Limited is a reputable developer with a proven track record. The project is registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA), ensuring transparency and adherence to regulations. The project is also backed by ICICI Bank, further solidifying its financial stability.

Sereno promises an ideal blend of modern living and convenient connectivity. With its thoughtfully designed apartments, strategic location, and reputable developer, the project offers an excellent investment opportunity for those seeking a comfortable and well-connected lifestyle in Vasai.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 27.71 18 6
1BHK 27.85 17 5
1BHK 28.25 18 0
1BHK 28.63 18 0
1BHK 28.64 87 11
1BHK 29.32 45 14
1BHK 29.87 44 4
1BHK 47.82 2 2
2BHK 29.87 1 0
2BHK 37.39 4 0
2BHK 37.94 4 4
2BHK 47.82 43 12
2BHK 48.08 44 18
2BHK 49.4 43 3
2BHK 49.58 44 12
Shop 10.22 1 1
Shop 10.4 1 1
Shop 11.24 2 2
Shop 11.41 1 1
Shop 13.56 2 1
Shop 16.22 2 2
Shop 16.57 1 1
Shop 17.1 1 0
Shop 17.62 1 0
Shop 17.9 2 1
Shop 21.21 1 0
Shop 22.33 1 1
Shop 9.5 1 0

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Excavation 70
2 Overall Percentage of Completion of the work done For the entire Building /Wing 7

 

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Building/Plot Details section updated for field(s) as below:

Field updated New value
Number of Podium’s 4
Number of Sanctioned Floors 44

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Excavation 50
2 Overall Percentage of Completion of the work done For the entire Building /Wing 5

 

New documents listed below were uploaded to the Documents section:

  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Disclosure of sold/ booked inventory

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-12-30

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development [6]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [3]
  • b Details of encumbrances concerned to Legal [3]