RERA ID: P99000051639
Project Name: YASHWANT CIRCLE
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-12-31
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2025-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Virar West, Y K Road, Vasai-Virar City (M Corp), Vasai, Palghar-401303

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Survey No.327/E/1 of Village Virar,Taluka Vasai,Dist Palghar

Boundaries:
illage dongare boundary
irar byepass roadN Survey No 327 H No 1
WE
S
S no 327 B

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1625 sq.mt.
Sanctioned Built-up Area: 7854 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 19
No. of Plinths: 1
No. of Open Parking: 175
No. of Closed Parking: 90

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 577 sq ft 3 0
2BHK 738 to 807 sq ft 48 0
3BHK 1005 sq ft 17 0
Shop 4555 to 4651 sq ft 2 2
Project Developer:
RAJ ENTERPRISES
Organization Type: Partnership

Address: 102, New Khokhani Bhavan, Station Road Navghar, Vasai West, Opp.Mansarovar Sweets., Vasai-Virar City (M Corp), Vasai, Palghar-401202

Office Phone: +91 88550 39879
Website URL: https://www.ykandsons.in


Member details:
Member Name Designation
AJAY YASHWANT PATIL Partner
SANDEEP VISHNU SANKHE Authorized Signatory
BIPIN NAVINCHANDRA KHOKHANI Partner
KUNDAN JAYANTILAL BHATT Partner


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
YK AND SONS PROJECTS LLP Partnership Area Share


Other Professionals involved:
Professional Name Professional Type
ABHAY RAUT Architect
JYOTIBA D PATIL Engineer
JAY KISHOR DOSHI Chartered Accountant
PALLAVI P BARAPATRE Chartered Accountant


Projects in the state by this developer:
P99000053585 - YASHWANT PRESTIGE - Palghar
P99000051639 - YASHWANT CIRCLE - Palghar
P52000034839 - SAI BLISS - Raigarh
P52000017820 - SHIV GANGOTRI - Raigarh
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Yashwant Circle: A New Residential Development in Virar West

Yashwant Circle, a new residential project by RAJ ENTERPRISES, is poised to redefine luxury living in Virar West, Maharashtra. This project, registered with MahaRERA under ID P99000051639, offers a unique blend of modern amenities and strategic location, making it an attractive investment opportunity.

Situated on Survey No. 327/E/1 of Village Virar, Taluka Vasai, Dist Palghar, the project enjoys prime location advantages. Its proximity to the Virar bypass road ensures easy accessibility, while its location in Virar West provides access to a vibrant urban lifestyle.

Yashwant Circle, spread across a sprawling 1625 sq.m. plot, will house a single, 19-storey building, offering a range of residential options including 1BHK, 2BHK, and 3BHK apartments, alongside two spacious shop units. The project boasts a total sanctioned FSI of 7854, promising ample living space and comfortable dwelling for all residents.

The project is meticulously designed to cater to modern living needs, with a focus on open and closed parking facilities. The sanctioned plan accommodates 175 open parking spaces for both four-wheelers and two-wheelers, along with an additional 90 closed parking spaces, ensuring convenience and security for all residents.

Yashwant Circle, with its strategic location, comprehensive amenities, and variety of unit configurations, offers a compelling proposition for individuals and families seeking a comfortable and well-connected lifestyle in Virar West. The project, with its anticipated completion date of December 31st, 2025, promises to deliver a modern and fulfilling living experience.

For those interested in exploring this exciting new development further, details on the project, including unit sizes and pricing, can be accessed through the official website of RAJ ENTERPRISES, https://www.ykandsons.in.

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 22

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-12-31

 

Firm Details section updated for field(s) as below:

Field updated New value
Office Number 8855039879.0
Website URL https://www.ykandsons.in

 

New documents listed below were uploaded to the Documents section:

  • 2 Disclosure of sold/ booked inventory
  • 2 Declaration in FORM B
  • 2 Declaration about Commencement Certificate

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 21

 

New documents listed below were uploaded to the Documents section:

  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

New documents listed below were uploaded to the Documents section:

  • 5 Copy of Layout Approval (in case of layout)
  • 11 Building Plan Approval / NA Order for plotted development
  • 10 Building Plan Approval / NA Order for plotted development
  • 5 Commencement Certificates / NA Order for plotted development
  • 13 Building Plan Approval / NA Order for plotted development
  • 12 Building Plan Approval / NA Order for plotted development

 

Please note that the field “Project Type” has been modified. The new type is: Residential

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 7854.5

 

There are additions/modifications under Professionals section

Professional Name Professional Type
PALLAVI P BARAPATRE Chartered Accountant

 

New documents listed below were uploaded to the Documents section:

  • 2 Other – Technical
  • 2 Proforma of Agreement for sale
  • 4 Commencement Certificates / NA Order for plotted development

 

New documents listed below were uploaded to the Documents section:

  • 4 Copy of Layout Approval (in case of layout)
  • 6 Building Plan Approval / NA Order for plotted development
  • 7 Building Plan Approval / NA Order for plotted development
  • 8 Building Plan Approval / NA Order for plotted development
  • 9 Building Plan Approval / NA Order for plotted development

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Shop 423.21 1 1
Shop 432.15 1 1

 

New documents listed below were uploaded to the Documents section:

  • 3 Commencement Certificates / NA Order for plotted development
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 3 Copy of Layout Approval (in case of layout)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • Building Plan Approval / NA Order for plotted development [5]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report [3]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • Other – Technical
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]