RERA ID: P99000020393
Project Name: SPRING FIELD
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-01-31
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2025-02-28).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Kaman, Vasai-Virar City (M Corp), Vasai, Palghar-401208

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
S NO 116

Boundaries:
ADJACENT BUILDING
ADJACENT BUILDINGN ADJACENT BUILDING
WE
S
ADJACENT BUILDING

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 27169 sq.mt.
Sanctioned Built-up Area: 6918 sq.mt.
Recreational Open Space: 3500 sq.mt.
No. of Buildings sanctioned: 13
No. of Floors sanctioned: 51
No. of Plinths: 23
No. of Stilts: 51
No. of Closed Parking: 51

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 372 sq ft 31 30
2BHK 548 sq ft 16 4
Others 234 to 548 sq ft 128 13
Residential 155 to 3599 sq ft 102 0
Project Developer:
SHantee Homes Realty LLP
Organization Type: Partnership

Address: Ground Floor, House No 904, Sai Sharaddha Bunglow, S No 21/C And S No 21/C/1, Revenue Village Navghar, Shastri Nagar, Vasai West, Behind Gopal Building, Vasai-Virar City (M Corp), Vasai, Palghar-401202

Office Phone: +91 25023 31171


Member details:
Member Name Designation
Raaz Abdulsamad Pathan Authorized Signatory
Niyaz Abdulsamad Pathan Partner


Other Professionals involved:
Professional Name Professional Type
SANJAY MALOO AND ASSOCIATES Architect
MOHAMMED SHOEB BHATI Engineer
MUFADDAL MERCHANT Architect


Projects in the state by this developer:
P99000076607 - SHALIMAR RESIDENCY - Palghar
P99000030553 - SUNSHINE GREEN PARK PHASE V - Palghar
P99000030524 - SUNSHINE ENCLAVE - Palghar
P99000020998 - SHAMROCK RESIDENCY - Palghar
P99000020393 - SPRING FIELD - Palghar
P99000017859 - SUNSHINE GREEN PARK PHASE -3 - Palghar
P99000001370 - SUNSHINE GREEN PARK PHASE I - Palghar
P99000001294 - SUNSHINE GREEN PARK PHASE 2 - Palghar
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing SPRING FIELD: A New Residential Development in Vasai-Virar

SPRING FIELD is an upcoming residential project in the bustling city of Vasai-Virar, Maharashtra. Developed by SHantee Homes Realty LLP, this new project boasts a prime location in Kaman, Vasai-Virar City (M Corp) and promises to offer modern living spaces to suit diverse needs.

With a total plot area of 27,169 sq mtrs, SPRING FIELD is designed to include 23 buildings, of which 13 are currently under construction and awaiting registration under RERA with the ID P99000020393. The project encompasses a total sanctioned built-up area of 6918 sq mtrs, with plans for an additional 12,000 sq mtrs of built-up area, once approved.

The project is strategically located on S NO 116, Kaman, with surrounding boundaries encompassing adjacent buildings. The development is well-connected to the city’s infrastructure and offers easy access to various amenities like schools, hospitals, and commercial hubs.

SPRING FIELD offers a range of residential options, catering to varied preferences. These include 31 units of 1BHK (372 sq ft), 16 units of 2BHK (548 sq ft) and a total of 128 units ranging from 234 to 548 sq ft. In total, the project will offer 102 residential units with sizes ranging from 155 to 3599 sq ft, ensuring a diverse selection for potential buyers.

The project also boasts an impressive array of amenities, including a generous 3500 sq mtrs of recreational open space, 51 stilts, 51 closed parking spaces, and 51 sanctioned floors across 23 plinth areas.

SPRING FIELD is set to be completed by January 31st, 2026, offering residents a comfortable and modern living experience in the heart of Vasai-Virar. The project is backed by the financial support of THE COSMOS CO-OP BANK LTD (IFSC Code: COSB0000116), further strengthening its credibility and commitment to delivering a quality project.

SHantee Homes Realty LLP is a reputable partnership firm with a strong commitment to delivering high-quality residential projects. Their established presence in the Vasai-Virar region coupled with their dedication to client satisfaction makes SPRING FIELD a compelling investment opportunity for individuals seeking a comfortable and well-planned living space.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 34.63 31 30
2BHK 50.98 16 4
RESI ROW HOUSE 22.48 100 12
RESI ROW HOUSE 22.5 7 0
Resi Row House 22.48 11 0
Residential 15.39 32 0
Residential 18 17 0

 

New documents listed below were uploaded to the Documents section:

  • 6 Disclosure of sold/ booked inventory
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
1 Overall Percentage of Completion of the work done For the entire Building /Wing 83.8
5 X number of Slabs of Super Structure 0
5 Overall Percentage of Completion of the work done For the entire Building /Wing 28
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
9 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
9 Overall Percentage of Completion of the work done For the entire Building /Wing 71.5
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
10 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
11 Overall Percentage of Completion of the work done For the entire Building /Wing 66.5
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
12 Overall Percentage of Completion of the work done For the entire Building /Wing 66.5
13 Stilt Floor 0
13 X number of Slabs of Super Structure 0
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 0
13 Overall Percentage of Completion of the work done For the entire Building /Wing 19

 

A correction has been made to the Developer’s address. The complete address is now: Ground Floor, House No 904, Sai Sharaddha Bunglow, S No 21/C And S No 21/C/1, Revenue Village Navghar, Shastri Nagar, Vasai West, Behind Gopal Building, Vasai-Virar City (M Corp), Vasai, Palghar-401202

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 78.8
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
10 Overall Percentage of Completion of the work done For the entire Building /Wing 67.5
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
12 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
13 Overall Percentage of Completion of the work done For the entire Building /Wing 55

 

New documents listed below were uploaded to the Documents section:

  • 5 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 2 Copy of Layout Approval (in case of layout)
  • 1 CERSAI details
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 3 Copy of Layout Approval (in case of layout)
  • 2 Building Plan Approval (IOD)
  • 3 Building Plan Approval (IOD)
  • 4 Building Plan Approval (IOD)
  • 5 Building Plan Approval (IOD)
  • 6 Building Plan Approval (IOD)
  • 7 Building Plan Approval (IOD)
  • 8 Building Plan Approval (IOD)
  • 1 Declaration about Commencement Certificate

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2026-01-31

 

New documents listed below were uploaded to the Documents section:

  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
1 Overall Percentage of Completion of the work done For the entire Building /Wing 71.8
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
9 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
9 Overall Percentage of Completion of the work done For the entire Building /Wing 62.5
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
10 Overall Percentage of Completion of the work done For the entire Building /Wing 64.5
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
12 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
13 Overall Percentage of Completion of the work done For the entire Building /Wing 54

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project) [4]
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project) [3]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [4]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [5]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Form 2A [3]
  • Other
  • Proforma of Allotment letter