RERA ID: P99000005759
Project Name: RITU GARDENIA PHASE 2
Project Type: Others
Project Status: On-Going Project *
* Projects that were already under development in May 2017, when RERA was implemented.
2027-12-31
Extended Date of Completion
The project missed completion date 2 time(s) earlier (2023-12-30, 2021-12-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
, Vasai-Virar City (M Corp), Vasai, Palghar-401202

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
SURVEY NO 319,HISSA NO B1,B2,B3,B4 SURVEY NO 327B, PLOT NO 1,2,7,8,9

Boundaries:
S NO 315 317
S NO 310N S NO 317
WE
S
20 MTR D P ROAD

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 7087 sq.mt.
Sanctioned Built-up Area: 669 sq.mt.
Recreational Open Space: 678 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 15
No. of Plinths: 1
No. of Podiums: 1
No. of Stilts: 1
No. of Open Parking: 10
No. of Closed Parking: 36

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 396 to 561 sq ft 112 4
1RK 279 sq ft 4 0
2BHK 547 to 656 sq ft 52 2
Shop 110 to 173 sq ft 20 17
Project Developer:
RITU BUILDERS AND DEVELOPERS
Organization Type: Partnership

Address: Shop No 23/24, Pushpa Niketan, Temba Hospital Road, Bhayander West, Behind Maxus Mall, Bhayandar, Thane-401101

Office Phone: +91 22281 93828


Member details:
Member Name Designation
RAJARAM NEKARAM BHATI Partner
NIRMAL MADANLAL TATER Partner
RAJMAL HASTIMAL GOKHARU Partner
DINESH RAJARAM BHATI Partner
RATANLAL SUNDERLAL MEHTA Partner
KANCHANDEVI RATANLAL MEHTA Partner
RAJARAM NEKARAM BHATI Authorized Signatory
RAJMAL HASTIMAL GOKHARU Authorized Signatory
RITU INFRASTRUCTURE PRIVATE LIMITED Partner
RATANLAL SUNDERLAL MEHTA Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
EN CON Architect
SANJAY NARANG Engineer
R D LUKAD Chartered Accountant
ProtechConsultants Engineer


Projects in the state by this developer:
P51700052604 - OM SHIV ANGAN CHS - Thane
P99000011391 - RITU GARDENIA PHASE 1 - Palghar
P99000005759 - RITU GARDENIA PHASE 2 - Palghar
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Ritu Gardenia Phase 2: A Comprehensive Residential Development in Vasai

Ritu Gardenia Phase 2, a project developed by Ritu Builders and Developers, is an ongoing residential project located in the bustling city of Vasai-Virar, Maharashtra. With a RERA ID of P99000005759, this project promises to deliver a vibrant and comfortable living experience with a diverse range of units, ranging from compact 1RKs to spacious 2BHKs, along with a limited number of retail shops.

Spread across a sprawling 7087 sqmts of land, Ritu Gardenia Phase 2 comprises a single building with 15 sanctioned floors, including a stilt floor and a podium level. The project boasts a total of 112 1BHK units, 4 1RK units, 52 2BHK units, and 20 shop units, catering to a wide range of individual and family needs. The project also features a total of 46 parking spaces, including 10 open parking spaces and 36 closed parking spaces, ensuring convenient and secure parking for residents.

Located in Survey No 319, Hisssa No B1, B2, B3, B4, Survey No 327B, Plot No 1, 2, 7, 8, 9, Vasai-Virar City (M Corp), Ritu Gardenia Phase 2 enjoys a strategic location. It is bordered by S NO 317 to the east, S NO 310 to the west, S NO 315 & 317 to the north, and a 20 meter DP road to the south, ensuring good connectivity and accessibility.

Despite facing some delays, the project is still ongoing with an extended completion date of December 31st, 2027. Ritu Builders and Developers have assured that the project is free from any legal disputes or litigations, providing potential buyers with peace of mind.

The project design incorporates various amenities and features aimed at enhancing residents’ quality of life. The developer has incorporated a significant amount of recreational open space, covering 678 sqmts, providing a serene environment for relaxation and recreation.

Ritu Gardenia Phase 2 presents an enticing opportunity for those seeking a well-planned, modern residential development in Vasai. With its diverse range of units, convenient location, and thoughtfully designed amenities, the project promises a comfortable and fulfilling lifestyle for its residents.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 36.96 54 3
2BHK 50.91 11 1
Shop 12 2 2
Shop 15.29 2 2

 

New documents listed below were uploaded to the Documents section:

  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 0
1 X number of Slabs of Super Structure 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 29

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

New documents listed below were uploaded to the Documents section:

  • 2 Declaration in FORM B

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-12-31

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Podiums 90
1 Stilt Floor 80
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
1 Overall Percentage of Completion of the work done For the entire Building /Wing 37.8

 

New documents listed below were uploaded to the Documents section:

  • 2 Building Plan Approval (IOD)
  • 3 Copy of Layout Approval (in case of layout)
  • 3 Building Plan Approval (IOD)
  • 3 Commencement Certificates / NA Order for plotted development
  • 1 Declaration about Commencement Certificate
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 2 Disclosure of sold/ booked inventory
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)

 

There are additions/modifications under Professionals section

Professional Name Professional Type
R D LUKAD Chartered Accountant
ProtechConsultants Engineer

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 36.82 2 0
1BHK 36.96 54 2
1BHK 37.23 2 0
1BHK 38.5 28 1
1BHK 38.58 11 0
1BHK 38.99 11 0
1BHK WITH TERRACE 50.11 2 0
1BHK WITH TERRACE 51.73 1 0
1BHK WITH TERRACE 52.14 1 0
1RK 25.98 4 0
2BHK 50.91 11 0
2BHK 50.99 14 0
2BHK 51.04 14 0
2BHK 52.29 11 1
2BHK WITH TERRACE 60.95 2 0
Shop 10.25 2 2
Shop 10.55 4 3
Shop 11.95 2 2
Shop 12 2 2
Shop 13.43 2 2
Shop 14.52 4 2
Shop 15.29 2 1
Shop 16.13 2 2

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval (IOD)
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report [2]
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Other
  • Proforma of Allotment letter