MH
Nandurbar
P49700029921
RERA ID: P49700029921
Project Name: THE GOLDEN HERITAGE
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Nandurbar, Hol Turfe Haveli, Hol T. Haveli-425412

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO 3 TO 36, 51 TO 93, 96 TO 122, 125 TO 145 AND 146 CLUB HOUSE, S NO 94/2B AT HOL TURFE HAVELI

Boundaries:
GUT NO 95
GUT NO 94 OBLICK 1N GUT NO 90
WE
S
GUT NO 92 OBLICK 93

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 12276 sq.mt.
Sanctioned Built-up Area: 11497 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 125
No. of Floors sanctioned: 250
No. of Plinths: 125
No. of Stilts: 1
No. of Closed Parking: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 756 to 819 sq ft 125 29
Project Developer:
THE GOLDEN HERITAGE
Organization Type: Partnership

Address: S No 94/2/B, 0, Near Vijay Shree Nagar, Hole Shiwar, Nandurbar, Hol T. Haveli-425412

Office Phone: +91 95454 33777


Member details:
Member Name Designation
ANAND HASTIMAL JAIN Authorized Signatory
ANAND HASTIMAL JAIN Partner
AJAY HASTIMAL JAIN Partner


Other Professionals involved:
Professional Name Professional Type
DHANANJAY NARENDRA JOSHI Architect
Anil Sanjay Mali Engineer
CHETAN M KAMBHAD Contractor
VARDHAMAN SBHANDARI Chartered Accountant
Anil Sanjay Mali Other Professional


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

The Golden Heritage: A New Residential Opportunity in Nandurbar

The Golden Heritage is a new residential project poised to transform the landscape of Nandurbar, Maharashtra. Developed by a partnership firm, this project is registered with MahaRERA under ID P49700029921 and is currently under construction with an anticipated completion date of March 31st, 2025.

Located in Hol T. Haveli, the project spans a spacious 12,276 sq. meters, encompassing plots 3 to 36, 51 to 93, 96 to 122, 125 to 145, and the clubhouse situated on plot 146. The site is conveniently located in the NANDURBAR locality, easily accessible with its address being HOL TURFE HAVELI, NEAR VIJAY SHREE NAGAR, HOLE SHIWAR.

The Golden Heritage offers a range of amenities, including 125 individual plinths, 250 sanctioned floors, and 1 stilt level. The project also boasts a closed parking facility to ensure the security and convenience of residents.

The heart of the project lies in its thoughtfully designed residential units. The Golden Heritage offers 125 spacious 2BHK apartments, ranging in size from 756 to 819 sq. ft. These apartments are designed to cater to the needs of modern families, offering comfortable and functional living spaces.

The project is being financed by HDFC Bank Ltd. (IFSC Code: HDFC0001787), providing potential buyers with peace of mind and confidence in the project’s financial stability.

The Golden Heritage represents a unique opportunity for homebuyers seeking a comfortable and convenient lifestyle in a rapidly developing region. With its prime location, thoughtfully designed units, and modern amenities, The Golden Heritage promises a fulfilling residential experience.

Disclaimer: This essay is based on the provided information and does not constitute financial or investment advice. Prospective buyers are encouraged to conduct their own due diligence and research before making any investment decisions.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 72 16 4
2BHK 72.3 29 9
2BHK 72.9 1 0
2BHK 74.15 11 0
2BHK 75.9 33 12
2BHK 76 3 0

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Anil Sanjay Mali Other Professional
Anil Sanjay Mali Engineer

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
49 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
49 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
49 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
49 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
49 Overall Percentage of Completion of the work done For the entire Building /Wing 94
50 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
50 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
50 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
50 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
50 Overall Percentage of Completion of the work done For the entire Building /Wing 94
51 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
51 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
51 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
51 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
51 Overall Percentage of Completion of the work done For the entire Building /Wing 94
52 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
52 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
52 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
52 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
52 Overall Percentage of Completion of the work done For the entire Building /Wing 94
53 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
53 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
53 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
53 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
53 Overall Percentage of Completion of the work done For the entire Building /Wing 100
54 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
54 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
54 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
54 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
54 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
54 Overall Percentage of Completion of the work done For the entire Building /Wing 100
55 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
55 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
55 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
55 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
55 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
55 Overall Percentage of Completion of the work done For the entire Building /Wing 100
56 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
56 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
56 Overall Percentage of Completion of the work done For the entire Building /Wing 70
57 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
57 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
57 Overall Percentage of Completion of the work done For the entire Building /Wing 70
62 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
62 Overall Percentage of Completion of the work done For the entire Building /Wing 84
63 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
63 Overall Percentage of Completion of the work done For the entire Building /Wing 84
66 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
66 Overall Percentage of Completion of the work done For the entire Building /Wing 84
67 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
67 Overall Percentage of Completion of the work done For the entire Building /Wing 85
68 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
68 Overall Percentage of Completion of the work done For the entire Building /Wing 65
69 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
69 Overall Percentage of Completion of the work done For the entire Building /Wing 66
70 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
70 Overall Percentage of Completion of the work done For the entire Building /Wing 85
71 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
71 Overall Percentage of Completion of the work done For the entire Building /Wing 85
72 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
72 Overall Percentage of Completion of the work done For the entire Building /Wing 85
73 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
73 Overall Percentage of Completion of the work done For the entire Building /Wing 85
75 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
75 Overall Percentage of Completion of the work done For the entire Building /Wing 90.5
84 X number of Slabs of Super Structure 100
84 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
84 Overall Percentage of Completion of the work done For the entire Building /Wing 76
85 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
85 Overall Percentage of Completion of the work done For the entire Building /Wing 76
86 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
86 Overall Percentage of Completion of the work done For the entire Building /Wing 76
87 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
87 Overall Percentage of Completion of the work done For the entire Building /Wing 76
88 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
88 Overall Percentage of Completion of the work done For the entire Building /Wing 76
89 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
89 Overall Percentage of Completion of the work done For the entire Building /Wing 76
90 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
90 Overall Percentage of Completion of the work done For the entire Building /Wing 76
91 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
91 Overall Percentage of Completion of the work done For the entire Building /Wing 76
92 X number of Slabs of Super Structure 100
92 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
92 Overall Percentage of Completion of the work done For the entire Building /Wing 67
94 X number of Slabs of Super Structure 100
94 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
94 Overall Percentage of Completion of the work done For the entire Building /Wing 67
95 X number of Slabs of Super Structure 100
95 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
95 Overall Percentage of Completion of the work done For the entire Building /Wing 67
96 X number of Slabs of Super Structure 100
96 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
96 Overall Percentage of Completion of the work done For the entire Building /Wing 67
97 X number of Slabs of Super Structure 100
97 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
97 Overall Percentage of Completion of the work done For the entire Building /Wing 67
98 X number of Slabs of Super Structure 100
98 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
98 Overall Percentage of Completion of the work done For the entire Building /Wing 67

 

New documents listed below were uploaded to the Documents section:

  • 3 Disclosure of sold/ booked inventory

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 0 PAVER BLOCKS
Sewerage (Chamber, Lines, Septic Tank , STP) : 40 SEPTIC TANK WITH SOAK PIT
Street Lighting : 50

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 70.25 3 1
2BHK 72 16 4
2BHK 72.3 29 10
2BHK 72.35 3 0
2BHK 72.9 1 0
2BHK 73.25 11 1
2BHK 74.15 11 1
2BHK 75.9 33 13
2BHK 76 3 0
2BHK 76.15 15 2

 

New documents listed below were uploaded to the Documents section:

  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 100
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
3 Overall Percentage of Completion of the work done For the entire Building /Wing 100
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
4 Overall Percentage of Completion of the work done For the entire Building /Wing 100
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
5 Overall Percentage of Completion of the work done For the entire Building /Wing 100
6 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
6 Overall Percentage of Completion of the work done For the entire Building /Wing 100
8 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
8 Overall Percentage of Completion of the work done For the entire Building /Wing 100
21 X number of Podiums 100
21 Stilt Floor 100
21 Overall Percentage of Completion of the work done For the entire Building /Wing 100
22 X number of Podiums 100
22 Stilt Floor 100
22 Overall Percentage of Completion of the work done For the entire Building /Wing 100
23 X number of Podiums 100
23 Stilt Floor 100
23 Overall Percentage of Completion of the work done For the entire Building /Wing 100
24 X number of Podiums 100
24 Stilt Floor 100
24 Overall Percentage of Completion of the work done For the entire Building /Wing 100
25 X number of Podiums 100
25 Stilt Floor 100
25 Overall Percentage of Completion of the work done For the entire Building /Wing 100
26 X number of Podiums 100
26 Stilt Floor 100
26 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
26 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
26 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
26 Overall Percentage of Completion of the work done For the entire Building /Wing 100
27 X number of Podiums 100
27 Stilt Floor 100
27 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
27 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
27 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
27 Overall Percentage of Completion of the work done For the entire Building /Wing 100
28 X number of Podiums 100
28 Stilt Floor 100
28 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
28 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
28 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
28 Overall Percentage of Completion of the work done For the entire Building /Wing 100
29 X number of Basement(s) and Plinth 100
29 X number of Podiums 100
29 Stilt Floor 100
29 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
29 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
29 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
29 Overall Percentage of Completion of the work done For the entire Building /Wing 100
30 X number of Podiums 100
30 Stilt Floor 100
30 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
30 Overall Percentage of Completion of the work done For the entire Building /Wing 96
31 X number of Basement(s) and Plinth 100
31 X number of Podiums 100
31 Stilt Floor 100
31 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
31 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
31 Overall Percentage of Completion of the work done For the entire Building /Wing 96
32 X number of Podiums 100
32 Stilt Floor 100
32 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
32 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
32 Overall Percentage of Completion of the work done For the entire Building /Wing 96
33 X number of Podiums 100
33 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
33 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
33 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
33 Overall Percentage of Completion of the work done For the entire Building /Wing 96
34 X number of Podiums 100
34 Stilt Floor 100
34 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
34 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
34 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
34 Overall Percentage of Completion of the work done For the entire Building /Wing 96
35 X number of Podiums 100
35 Stilt Floor 100
35 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
35 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
35 Overall Percentage of Completion of the work done For the entire Building /Wing 96
36 X number of Basement(s) and Plinth 100
36 Stilt Floor 100
36 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
36 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
36 Overall Percentage of Completion of the work done For the entire Building /Wing 96
37 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
37 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
37 Overall Percentage of Completion of the work done For the entire Building /Wing 96
38 X number of Podiums 100
38 Stilt Floor 100
38 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
38 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
38 Overall Percentage of Completion of the work done For the entire Building /Wing 96
39 X number of Podiums 100
39 Stilt Floor 100
39 Overall Percentage of Completion of the work done For the entire Building /Wing 100
40 X number of Podiums 100
40 Stilt Floor 100
40 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
40 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
40 Overall Percentage of Completion of the work done For the entire Building /Wing 96
41 X number of Podiums 100
41 Stilt Floor 100
41 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
41 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
41 Overall Percentage of Completion of the work done For the entire Building /Wing 96
42 X number of Podiums 100
42 Stilt Floor 100
42 Overall Percentage of Completion of the work done For the entire Building /Wing 100
43 X number of Podiums 100
43 Stilt Floor 100
43 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
43 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
43 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
43 Overall Percentage of Completion of the work done For the entire Building /Wing 100
44 X number of Podiums 100
44 Stilt Floor 100
44 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
44 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
44 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
44 Overall Percentage of Completion of the work done For the entire Building /Wing 100
45 X number of Podiums 100
45 Stilt Floor 100
45 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
45 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
45 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
45 Overall Percentage of Completion of the work done For the entire Building /Wing 100
46 X number of Podiums 100
46 Stilt Floor 100
46 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
46 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
46 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
46 Overall Percentage of Completion of the work done For the entire Building /Wing 100
47 X number of Podiums 100
47 Stilt Floor 100
47 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
47 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
47 Overall Percentage of Completion of the work done For the entire Building /Wing 100
48 X number of Podiums 100
48 Stilt Floor 100
48 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
48 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
48 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
48 Overall Percentage of Completion of the work done For the entire Building /Wing 100
49 X number of Podiums 100
49 Stilt Floor 100
49 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
49 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
49 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
49 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
49 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
50 X number of Podiums 100
50 Stilt Floor 100
50 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
50 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
50 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
50 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
50 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
51 X number of Podiums 100
51 Stilt Floor 100
51 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
51 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
51 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
51 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
51 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
52 X number of Podiums 100
52 Stilt Floor 100
52 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
52 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
52 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
52 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
52 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
53 X number of Podiums 100
53 Stilt Floor 100
53 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
53 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
53 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
53 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
53 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
54 X number of Podiums 100
54 Stilt Floor 100
54 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
54 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
54 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
54 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
54 Overall Percentage of Completion of the work done For the entire Building /Wing 80
55 X number of Podiums 100
55 Stilt Floor 100
55 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
55 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
55 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
55 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
55 Overall Percentage of Completion of the work done For the entire Building /Wing 80
56 X number of Podiums 100
56 Stilt Floor 100
56 X number of Slabs of Super Structure 100
56 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
56 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
56 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
56 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
56 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
56 Overall Percentage of Completion of the work done For the entire Building /Wing 67
57 X number of Podiums 100
57 Stilt Floor 100
57 X number of Slabs of Super Structure 100
57 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
57 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
57 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
57 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
57 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
57 Overall Percentage of Completion of the work done For the entire Building /Wing 67
58 X number of Podiums 100
58 Stilt Floor 100
58 X number of Slabs of Super Structure 100
58 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
58 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
58 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
58 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
58 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
58 Overall Percentage of Completion of the work done For the entire Building /Wing 83
59 X number of Podiums 100
59 Stilt Floor 100
59 X number of Slabs of Super Structure 100
59 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
59 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
59 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
59 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
59 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
59 Overall Percentage of Completion of the work done For the entire Building /Wing 83
60 X number of Podiums 100
60 Stilt Floor 100
60 X number of Slabs of Super Structure 100
60 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
60 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
60 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
60 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
60 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
60 Overall Percentage of Completion of the work done For the entire Building /Wing 83
61 X number of Podiums 100
61 Stilt Floor 100
61 X number of Slabs of Super Structure 100
61 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
61 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
61 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
61 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
61 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
61 Overall Percentage of Completion of the work done For the entire Building /Wing 83
62 X number of Podiums 100
62 Stilt Floor 100
62 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
62 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
62 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
62 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
62 Overall Percentage of Completion of the work done For the entire Building /Wing 83
63 X number of Podiums 100
63 Stilt Floor 100
63 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
63 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
63 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
63 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
63 Overall Percentage of Completion of the work done For the entire Building /Wing 83
64 X number of Podiums 100
64 Stilt Floor 100
64 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
64 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
64 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
64 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
64 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
64 Overall Percentage of Completion of the work done For the entire Building /Wing 98
65 X number of Podiums 100
65 Stilt Floor 100
65 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
65 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
65 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
65 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
65 Overall Percentage of Completion of the work done For the entire Building /Wing 87
66 X number of Podiums 100
66 Stilt Floor 100
66 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
66 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
66 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
66 Overall Percentage of Completion of the work done For the entire Building /Wing 82
67 X number of Podiums 100
67 Stilt Floor 100
67 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
67 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
67 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
67 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
67 Overall Percentage of Completion of the work done For the entire Building /Wing 83
68 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
68 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
68 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
68 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
68 Overall Percentage of Completion of the work done For the entire Building /Wing 63
69 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
69 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
69 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
69 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
69 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
69 Overall Percentage of Completion of the work done For the entire Building /Wing 64
70 X number of Podiums 100
70 Stilt Floor 100
70 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
70 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
70 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
70 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
70 Overall Percentage of Completion of the work done For the entire Building /Wing 83
71 X number of Podiums 100
71 Stilt Floor 100
71 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
71 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
71 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
71 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
71 Overall Percentage of Completion of the work done For the entire Building /Wing 83
72 X number of Podiums 100
72 Stilt Floor 100
72 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
72 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
72 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
72 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
72 Overall Percentage of Completion of the work done For the entire Building /Wing 83
73 X number of Podiums 100
73 Stilt Floor 100
73 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
73 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
73 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
73 Overall Percentage of Completion of the work done For the entire Building /Wing 83
74 X number of Podiums 100
74 Stilt Floor 100
74 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
74 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
74 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
74 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
74 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
74 Overall Percentage of Completion of the work done For the entire Building /Wing 92.5
75 X number of Podiums 100
75 Stilt Floor 100
75 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
75 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
75 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
75 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
75 Overall Percentage of Completion of the work done For the entire Building /Wing 89.5
76 X number of Podiums 100
76 Stilt Floor 100
76 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
76 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
76 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
76 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
76 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
76 Overall Percentage of Completion of the work done For the entire Building /Wing 92.5
77 X number of Podiums 100
77 Stilt Floor 100
77 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
77 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
77 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
77 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
77 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
77 Overall Percentage of Completion of the work done For the entire Building /Wing 92.5
78 X number of Podiums 100
78 Stilt Floor 100
78 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
78 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
78 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
78 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
78 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
78 Overall Percentage of Completion of the work done For the entire Building /Wing 91
79 X number of Podiums 100
79 Stilt Floor 100
79 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
79 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
79 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
79 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
79 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
79 Overall Percentage of Completion of the work done For the entire Building /Wing 88
80 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
80 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
80 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
80 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
80 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
80 Overall Percentage of Completion of the work done For the entire Building /Wing 68
81 X number of Podiums 100
81 Stilt Floor 100
81 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
81 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
81 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
81 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
81 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
81 Overall Percentage of Completion of the work done For the entire Building /Wing 88
82 X number of Podiums 100
82 Stilt Floor 100
82 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
82 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
82 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
82 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
82 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
82 Overall Percentage of Completion of the work done For the entire Building /Wing 88
83 X number of Podiums 100
83 Stilt Floor 100
83 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
83 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
83 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
83 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 70
83 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
83 Overall Percentage of Completion of the work done For the entire Building /Wing 88
84 X number of Podiums 100
84 Stilt Floor 100
84 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
84 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
84 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
84 Overall Percentage of Completion of the work done For the entire Building /Wing 70
85 X number of Podiums 100
85 Stilt Floor 100
85 X number of Slabs of Super Structure 100
85 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
85 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
85 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
85 Overall Percentage of Completion of the work done For the entire Building /Wing 75
86 X number of Podiums 100
86 Stilt Floor 100
86 X number of Slabs of Super Structure 100
86 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
86 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
86 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
86 Overall Percentage of Completion of the work done For the entire Building /Wing 75
87 X number of Podiums 100
87 Stilt Floor 100
87 X number of Slabs of Super Structure 100
87 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
87 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
87 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
87 Overall Percentage of Completion of the work done For the entire Building /Wing 75
88 X number of Podiums 100
88 Stilt Floor 100
88 X number of Slabs of Super Structure 100
88 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
88 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
88 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
88 Overall Percentage of Completion of the work done For the entire Building /Wing 75
89 X number of Podiums 100
89 Stilt Floor 100
89 X number of Slabs of Super Structure 100
89 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
89 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
89 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
89 Overall Percentage of Completion of the work done For the entire Building /Wing 75
90 X number of Podiums 100
90 Stilt Floor 100
90 X number of Slabs of Super Structure 100
90 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
90 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
90 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
90 Overall Percentage of Completion of the work done For the entire Building /Wing 75
91 X number of Basement(s) and Plinth 100
91 X number of Podiums 100
91 Stilt Floor 100
91 X number of Slabs of Super Structure 100
91 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
91 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
91 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
91 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 50
91 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
91 Overall Percentage of Completion of the work done For the entire Building /Wing 75
92 X number of Podiums 100
92 Stilt Floor 100
92 X number of Slabs of Super Structure 50
92 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
92 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
92 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
92 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
92 Overall Percentage of Completion of the work done For the entire Building /Wing 60
93 X number of Podiums 100
93 Stilt Floor 100
93 X number of Slabs of Super Structure 50
93 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
93 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
93 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
93 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
93 Overall Percentage of Completion of the work done For the entire Building /Wing 60
94 X number of Podiums 100
94 Stilt Floor 100
94 X number of Slabs of Super Structure 50
94 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
94 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
94 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
94 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
94 Overall Percentage of Completion of the work done For the entire Building /Wing 60
95 X number of Podiums 100
95 Stilt Floor 100
95 X number of Slabs of Super Structure 50
95 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
95 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
95 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
95 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
95 Overall Percentage of Completion of the work done For the entire Building /Wing 60
96 X number of Podiums 100
96 Stilt Floor 100
96 X number of Slabs of Super Structure 50
96 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
96 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
96 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
96 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
96 Overall Percentage of Completion of the work done For the entire Building /Wing 60
97 X number of Podiums 100
97 Stilt Floor 100
97 X number of Slabs of Super Structure 50
97 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
97 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
97 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
97 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
97 Overall Percentage of Completion of the work done For the entire Building /Wing 60
98 X number of Podiums 100
98 Stilt Floor 100
98 X number of Slabs of Super Structure 50
98 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
98 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
98 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
98 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
98 Overall Percentage of Completion of the work done For the entire Building /Wing 60
99 X number of Podiums 100
99 Stilt Floor 100
99 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
99 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
99 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
99 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
99 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
99 Overall Percentage of Completion of the work done For the entire Building /Wing 91
100 X number of Podiums 100
100 Stilt Floor 100
100 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
100 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
100 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
100 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
100 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
100 Overall Percentage of Completion of the work done For the entire Building /Wing 91
101 X number of Podiums 100
101 Stilt Floor 100
101 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
101 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
101 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
101 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
101 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
101 Overall Percentage of Completion of the work done For the entire Building /Wing 91
102 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
102 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
102 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
102 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
102 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
102 Overall Percentage of Completion of the work done For the entire Building /Wing 71
103 X number of Podiums 100
103 Stilt Floor 100
103 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
103 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
103 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
103 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
103 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
103 Overall Percentage of Completion of the work done For the entire Building /Wing 91
104 X number of Podiums 100
104 Stilt Floor 100
104 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
104 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
104 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
104 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
104 Overall Percentage of Completion of the work done For the entire Building /Wing 88

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 72 16 4
2BHK 75.9 12 12

 

New documents listed below were uploaded to the Documents section:

  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Other – Technical
  • 2 Disclosure of sold/ booked inventory

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [11]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of sold/ booked inventory
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [6]
  • Proforma of Allotment letter [3]
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal