MH
Nagpur
P50500050049
RERA ID: P50500050049
Project Name: GOLDEN VISTA
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-03-31
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2025-03-31).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Pipla, Besa Pipla, Nagpur (Rural), Nagpur-440037

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PH NO.38, KH NO.136/2/A OF MOUJA PIPLA

Boundaries:
KHASRA NO 131
KHASRA NO 139N KHASRA NO 135
WE
S
KHASRA NO 136

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 5869 sq.mt.
Sanctioned Built-up Area: 18746 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 21
No. of Plinths: 2
No. of Stilts: 2
No. of Open Parking: 200
No. of Closed Parking: 2

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 646 sq ft 44 15
3BHK 802 to 961 sq ft 124 16
Shop 147 to 243 sq ft 11 2
Project Developer:
GOLDEN HOMES INFRASTRUCTURES
Organization Type: Partnership

Address: 3Rd Floor, Plot No 107, Wardha Road, Vivekanand Nagar, Near Sai Mandir Chowk, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440015

Office Phone: +91 70203 87041


Member details:
Member Name Designation
ASHOK AGRAWAL Partner
ASEMA UPARE Partner
KAVITA MITTAL Partner
YASH AGRAWAL Authorized Signatory
MANMEET CHHABDA Partner


Other Professionals involved:
Professional Name Professional Type
CD GIRIPUNJE Architect
ATUL TALEKAR Engineer
CA UPENDRA SINGH THAKUR Chartered Accountant
MJM Associates Chartered Accountant


Projects in the state by this developer:
P50500053913 - GOLDEN AVENUE - Nagpur
P50500050049 - GOLDEN VISTA - Nagpur
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Golden Vista: A New Horizon in Pipla, Nagpur

Golden Vista, a new real estate project by Golden Homes Infrastructures, is poised to redefine luxury living in Pipla, Nagpur. This ambitious project, registered under RERA with ID P50500050049, is set to offer a unique blend of modern amenities and serene surroundings, making it an ideal destination for discerning homebuyers.

Located in Pipla, a tranquil village situated in the Nagpur (Rural) Taluka, Golden Vista boasts a prime location with easy access to the bustling city of Nagpur. The project is spread over 5869 square meters of land, demarcated by Khalsa numbers 135, 139, 131, and 136. The project plan envisions two buildings with a total sanctioned built-up area of 18746 square meters, spanning over 21 floors, including two stilts.

Golden Vista promises an unparalleled lifestyle with a host of amenities designed to cater to every need. The project boasts a generous provision of 200 open parking spaces for both four-wheelers and two-wheelers, ensuring hassle-free parking. Furthermore, two closed parking spaces are also available for added convenience.

The project is backed by Golden Homes Infrastructures, a renowned partnership firm known for its commitment to quality and customer satisfaction. Their expertise and dedication are reflected in the meticulously planned and executed design of Golden Vista.

Golden Vista is not just an address; it is an opportunity to embrace a life of comfort and convenience. With its prime location, modern amenities, and commitment to excellence, Golden Vista is set to become a landmark in Pipla, offering residents a unique and fulfilling living experience. As the project progresses towards its proposed completion date of March 31st, 2025, it promises to be a highly sought-after destination for those seeking a perfect blend of urban convenience and peaceful living.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 60.1 44 15
3BHK 74.6 40 0
3BHK 79.34 44 16
3BHK 89.28 40 0
Shop 13.73 1 0
Shop 14.1 1 1
Shop 15.47 1 0
Shop 17.89 2 0
Shop 18.19 2 0
Shop 20.99 2 1
Shop 22.63 2 0

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 62.5
2 X number of Basement(s) and Plinth 100
2 Stilt Floor 80
2 X number of Slabs of Super Structure 12
2 Overall Percentage of Completion of the work done For the entire Building /Wing 29.2

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2026-03-31

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 25 AS PER PLAN
Water Supply : 25 AS PER PLAN
Electrical Meter Room, Sub-Station, Receiving Station : 5 AS PER PLAN

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 74.6 40 0
3BHK 89.28 40 0
Shop 15.47 1 0
Shop 18.19 2 0
Shop 22.63 2 0

 

Building/Plot Details section updated for field(s) as below:

Field updated New value
Number of Plinth 2
Number of Sanctioned Floors 21
Number of Stilts 2
Number of Closed Parking 2

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Excavation 100
2 X number of Basement(s) and Plinth 25
2 X number of Podiums 0
2 Stilt Floor 0
2 X number of Slabs of Super Structure 0
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 0
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
2 Overall Percentage of Completion of the work done For the entire Building /Wing 12.5

 

Firm Details section updated for field(s) as below:

Field updated New value
Total Number of Proposed Building/Wings (In the Layout/Plot) 2
Number of Sanctioned Building out of Above Proposed Count Applied for this Registration 2
Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) 18746.8

 

The “Plot Bearing No / CTS no / Survey Number / Final Plot no” field in the project location details has been corrected to: PH NO.38, KH NO.136/2/A OF MOUJA PIPLA

 

A correction has been made to the project location address. The complete address is now: Pipla, Besa Pipla, Nagpur (Rural), Nagpur-440037

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 40 AS PER PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 22 AS PER PLAN
Water Supply : 20 AS PER PLAN

 

New documents listed below were uploaded to the Documents section:

  • 10 Building Plan Approval / NA Order for plotted development
  • 9 Building Plan Approval / NA Order for plotted development
  • 8 Building Plan Approval / NA Order for plotted development
  • 7 Building Plan Approval / NA Order for plotted development
  • 11 Building Plan Approval / NA Order for plotted development
  • 3 Commencement Certificates / NA Order for plotted development
  • 3 Declaration about Commencement Certificate
  • 2 Declaration about Commencement Certificate
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Disclosure of sold/ booked inventory
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 1 Other – Technical

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 95
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 55
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 52
1 Overall Percentage of Completion of the work done For the entire Building /Wing 50.7

 

Sanctioned FSI of the project applied for registration (Sanctioned Built-up Area) field under Firm Details section updated with new value 11698.23

 

New documents listed below were uploaded to the Documents section:

  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Commencement Certificates / NA Order for plotted development

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 X number of Podiums 0
1 X number of Slabs of Super Structure 90
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 42
1 Overall Percentage of Completion of the work done For the entire Building /Wing 46.7

 

New documents listed below were uploaded to the Documents section:

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 18 AS PER PLAN
Water Supply : 14 AS PER PLAN
Internal Roads & Footpaths : 37 AS PER PLAN

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 79.34 44 16
Shop 20.99 2 1

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval / NA Order for plotted development [6]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [6]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory [3]
  • Other – Finance
  • Other – Legal
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [3]
  • b Details of encumbrances concerned to Legal [3]