RERA ID: P50500050570
Project Name: Swapna-Niketan by NMC
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-03-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Wanjara, Kamptee Road, Nagpur (Rural), Nagpur-440026

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Kh No 24/4 24/6 CTS 29 30

Boundaries:
Shri Karemore Field
Pioli Nadi and Shri Karemore fieldN Kamptee Road and Basti
WE
S
Pioli Nadi

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 12913 sq.mt.
Sanctioned Built-up Area: 19084 sq.mt.
Recreational Open Space: 2024 sq.mt.
No. of Buildings sanctioned: 8
No. of Floors sanctioned: 64
No. of Plinths: 8
No. of Open Parking: 816
No. of Closed Parking: 192

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 301 sq ft 480 480
Project Developer:
SANDEEP DWELLERS PVT. LTD.
Organization Type: Company

Address: 3 B, Gulmohar, Temple Road, Civil Lines, Opp. Hislop College, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440001

Office Phone: +91 71225 53866
Website URL: www.sandeepdwellers.com


Member details:
Member Name Designation
GAURAV AGARWALA Authorized Signatory
ASHOK AGARWALA Managing Director
ANIL AGARWALA Authorized Signatory
RAHUL AGARWALA Authorized Signatory


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
The Nagpur Slum Rehabilitation Authority Public Authority Revenue Share


Other Professionals involved:
Professional Name Professional Type
Aman Kumar Singh Engineer
Ashish Shiwarkar Engineer
Paresh Tank Chartered Accountant
Rahul Agarwala Architect
Ar. Dinesh Warade Architect


Projects in the state by this developer:
P50500055135 - SDPL Om Tatsat - Nagpur
P50500053748 - SDPL Aashray Beltarodi II - Nagpur
P50500050570 - Swapna-Niketan by NMC - Nagpur
P50500049338 - Aaranyam - A Project by SDPL - Nagpur
P50500046033 - SDPL Om II - Nagpur
P50500045716 - SDPL Greens Rowhouse II - Nagpur
P50500034209 - SDPL Aashray Hazaripahad II - Nagpur
P50500034184 - SDPL Aashray Hazaripahad III - Nagpur
P50500033667 - SDPL Aashray Dabha II - Nagpur
P50500030259 - SDPL Aashray Godhani - Nagpur
…and 13 more
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Swapna-Niketan by NMC: A New Residential Project in Nagpur

Introducing Swapna-Niketan, a promising new residential project developed by Sandeep Dwellers Pvt. Ltd., located in the picturesque village of Wanjara, Nagpur. This project, registered with MahaRERA under ID P50500050570, promises to redefine urban living with its strategic location, modern amenities, and thoughtfully designed 1BHK apartments.

Situated on a sprawling 12,913 sq. meters plot, Swapna-Niketan encompasses eight thoughtfully designed buildings, each rising to a height of six floors. The project is strategically located near Kamptee Road, offering residents easy access to the city’s central areas, schools, hospitals, and commercial hubs. The project is also strategically located near Pioli Nadi, offering residents a serene and tranquil living environment.

Swapna-Niketan boasts a total sanctioned built-up area of 19,084 sq. meters, offering a healthy balance between open spaces and built-up area. The project also boasts an impressive 2,024 sq. meters of dedicated recreational open space, providing residents ample opportunities for leisure and recreation.

The project offers 480 beautifully designed 1BHK apartments, each measuring 301 sq. ft., providing comfortable and functional living spaces for individuals and small families. The project also offers ample parking facilities with 816 open parking spaces and 192 closed parking spaces, ensuring that every resident has a secure and convenient parking spot.

Swapna-Niketan is a project that promises to elevate the standards of urban living in Nagpur. Its prime location, modern amenities, and thoughtfully designed 1BHK apartments offer a compelling opportunity for those seeking a comfortable, convenient, and enriching lifestyle.

This project is expected to be completed by March 31st, 2025, and is poised to become a landmark residential project in the city of Nagpur.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 28.05 480 480

 

New documents listed below were uploaded to the Documents section:

  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 51
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 13
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
1 Overall Percentage of Completion of the work done For the entire Building /Wing 39.9
2 X number of Slabs of Super Structure 88
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 43
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
2 Overall Percentage of Completion of the work done For the entire Building /Wing 36.1
3 X number of Slabs of Super Structure 63
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 15
3 Overall Percentage of Completion of the work done For the entire Building /Wing 31.8
4 X number of Slabs of Super Structure 88
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 69
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
4 Overall Percentage of Completion of the work done For the entire Building /Wing 38.7
5 X number of Slabs of Super Structure 63
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 39
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 15
5 Overall Percentage of Completion of the work done For the entire Building /Wing 31.7
6 X number of Basement(s) and Plinth 100
6 X number of Slabs of Super Structure 63
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 22
6 Overall Percentage of Completion of the work done For the entire Building /Wing 29.5
7 X number of Slabs of Super Structure 88
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 55
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
7 Overall Percentage of Completion of the work done For the entire Building /Wing 36.3
8 X number of Slabs of Super Structure 88
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 64
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 20
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
8 Overall Percentage of Completion of the work done For the entire Building /Wing 39.7

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Internal Roads & Footpaths : 37 As per norms

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 28.05 480 480

 

New documents listed below were uploaded to the Documents section:

  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 88
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 21
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 32.9
2 X number of Slabs of Super Structure 75
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 18
2 Overall Percentage of Completion of the work done For the entire Building /Wing 30.3
3 X number of Slabs of Super Structure 50
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 5
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
3 Overall Percentage of Completion of the work done For the entire Building /Wing 26
4 X number of Slabs of Super Structure 75
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 39
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 18
4 Overall Percentage of Completion of the work done For the entire Building /Wing 33.2
5 X number of Slabs of Super Structure 50
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 5
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
5 Overall Percentage of Completion of the work done For the entire Building /Wing 26.5
6 X number of Slabs of Super Structure 50
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
6 Overall Percentage of Completion of the work done For the entire Building /Wing 21
7 X number of Slabs of Super Structure 63
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 18
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 15
7 Overall Percentage of Completion of the work done For the entire Building /Wing 29.6
8 X number of Slabs of Super Structure 75
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
8 Overall Percentage of Completion of the work done For the entire Building /Wing 32

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [3]
  • Building Plan Approval / NA Order for plotted development [11]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [3]
  • Other – Technical [3]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal