RERA ID: P50500048042
Project Name: JUPITER
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2024-12-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Kothari Lay Out, Kachhimet, Amravati Road, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440023

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
50

Boundaries:
9 MTRS WIDE ROAD
PLOT NO 51N PLOT NO 49
WE
S
6 MTRS WIDE ROAD

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 658 sq.mt.
Sanctioned Built-up Area: 1684 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 7
No. of Plinths: 1
No. of Open Parking: 9

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
3BHK 937 to 959 sq ft 13 3
Project Developer:
CHARRUDATTA CHANDRASHEKHAR KKALE c/o CHANDRASHEKHAR BABURAO KALE
Organization Type: Individual

Address: 16, Rajas, Bandhu Nagar, Geeta Nagar, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440030

Office Phone: +91 70203 87041


Other Professionals involved:
Professional Name Professional Type
EMANATE DESIGN Architect
Ankit Talreja GAD & Associates Chartered Accountant
JAYPRAKASH GANDHI Engineer
GIRHE CONSTRUCTION Contractor


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Jupiter: A New Residential Project in Nagpur

Nestled in the heart of Nagpur, Jupiter is a promising new residential project set to redefine contemporary living. Developed under RERA ID P50500048042, this project offers a unique opportunity to own a spacious and well-designed 3BHK apartment in a prime location.

Location and Amenities:

Jupiter is conveniently located in Kothari Lay Out, Kachhimet, on Amravati Road, providing easy access to the city’s key amenities. Situated on a 658 sqmt plot, the project boasts a 7-storey building, offering panoramic views of the surroundings. The building features 9 open parking spaces for both 4-wheelers and 2-wheelers, ensuring convenient parking for residents.

The Perfect Home:

Jupiter offers 13 spacious 3BHK apartments, ranging from 937 to 959 sq ft, catering to a diverse range of families. Each apartment is meticulously designed to provide comfortable and functional living spaces, maximizing natural light and ventilation. The project is designed with modern amenities and facilities, ensuring a luxurious and convenient lifestyle for its residents.

Project Status and Timeline:

As a new project, Jupiter is currently under construction and scheduled for completion by December 31st, 2024. This gives potential buyers ample time to make an informed decision and secure their dream home.

A Secure and Transparent Investment:

Jupiter is a fully compliant project registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA), ensuring transparency and accountability. The project is backed by ICICI Bank, with an IFSC code of ICIC0000059, providing further assurance to investors.

Embrace the Jupiter Lifestyle:

Jupiter offers an unparalleled opportunity to own a luxurious and comfortable home in a thriving location. With its convenient amenities, spacious apartments, and commitment to quality, Jupiter promises a fulfilling lifestyle for its residents. For those seeking a modern and well-designed home in Nagpur, Jupiter is the perfect choice.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 87.06 7 1
3BHK 89.12 6 2

 

New documents listed below were uploaded to the Documents section:

  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 1 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • 1 Architect’s Certificate on Completion of Project (Form 4)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 32 AS PER SANCTIONED PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 52 AS PER SANCTIONED PLAN
Water Supply : 35 NMC WATER AFTER OC/BORWELL
Electrical Meter Room, Sub-Station, Receiving Station : 30 ELECTRIC PANEL SHALL BE PROVIDED
Fire Protection And Fire Safety Requirements : 15 AS PER SANCTION PLAN
Water Conservation, Rain water Harvesting : 10 AS PER SANCTIONED PLAN/ BORWELL

 

New documents listed below were uploaded to the Documents section:

  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
1 Overall Percentage of Completion of the work done For the entire Building /Wing 67.3

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Slabs of Super Structure 100
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 92
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 32
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
1 Overall Percentage of Completion of the work done For the entire Building /Wing 64.4

 

New documents listed below were uploaded to the Documents section:

  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
3BHK 87.06 7 1
3BHK 89.12 6 2

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 25 AS PER SANCTIONED PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 45 AS PER SANCTIONED PLAN
Water Supply : 28 NMC WATER AFTER OC/BORWELL
Electrical Meter Room, Sub-Station, Receiving Station : 22 ELECTRIC PANEL SHALL BE PROVIDED
Fire Protection And Fire Safety Requirements : 12 AS PER SANCTION PLAN
Water Conservation, Rain water Harvesting : 5 AS PER SANCTIONED PLAN/ BORWELL

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [4]
  • Building Plan Approval / NA Order for plotted development [2]
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of sold/ booked inventory [4]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [6]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [4]
  • b Details of encumbrances concerned to Legal [4]