MH
Nagpur
P50500034253
RERA ID: P50500034253
Project Name: THE PARK VIEW
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Lashkaribag Basti, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440017

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
PLOT NO.1, PACHPAOLIHOUSING ACCOMODATION SCHEME, COPORATION NO.760,CTS NO.62

Boundaries:
ROAD
PLOT NO 2N ROAD
WE
S
OPEN LAND

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 553 sq.mt.
Sanctioned Built-up Area: 2209 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 11
No. of Plinths: 1

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 690 sq ft 10 9
3BHK 901 sq ft 10 4
Project Developer:
NAVNIRMAN BUILDERS & LAND DEVELOPER
Organization Type: Partnership

Address: First Floor Shop No. 107, Rahul Complex Ii, S T Stand Square, Ganeshpeth, S T Stand, Nagpur (M Corp.), Nagpur (Urban), Nagpur-440018

Office Phone: +91 70203 87041


Member details:
Member Name Designation
DINESH SHESHRAO WALKE Partner
CHHABUTAI SHESHRAO WALKE Partner


Other Professionals involved:
Professional Name Professional Type
LOKESH KADU Architect
RAHUL BAGADE Engineer
GAD & ASSOCIATES Chartered Accountant


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing The Park View: A New Residential Project in Nagpur

Nestled in the heart of Nagpur, The Park View is a new residential project promising a comfortable and modern living experience. Developed by NAVNIRMAN BUILDERS & LAND DEVELOPER, a reputable partnership firm, this project is set to redefine urban living in the bustling city.

The Park View boasts a prime location in Lashkarbagh Basti, strategically situated on PLOT NO. 1, PACHPAOLI HOUSING ACCOMODATION SCHEME, COPORATION NO. 760, CTS NO. 62. The project enjoys easy access to key amenities and infrastructure, making it an ideal choice for families and individuals alike. The project is registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) with the ID P50500034253, ensuring transparency and compliance with regulatory guidelines.

The project is spread across a total plot area of 553 sq. meters and comprises a single building with 11 sanctioned floors. The project offers a variety of residential units, including 10 spacious 2BHK apartments spanning 690 sq. ft. and 10 well-designed 3BHK apartments measuring 901 sq. ft.

The Park View is designed to provide residents with a comfortable and modern lifestyle. While specific amenities are yet to be confirmed, the project is expected to offer features that enhance the quality of life for its residents.

With its prime location, well-planned layout, and experienced developer, The Park View is poised to become a sought-after residential destination in Nagpur. The project is scheduled for completion by December 31st, 2025, offering potential buyers a unique opportunity to invest in a promising and well-constructed residential development.

For further details and inquiries, please contact NAVNIRMAN BUILDERS & LAND DEVELOPER at 7020387041.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 64.14 10 9
3BHK 83.75 10 4

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 78
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 42
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 55
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
1 Overall Percentage of Completion of the work done For the entire Building /Wing 71

 

New documents listed below were uploaded to the Documents section:

  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Conservation, Rain water Harvesting : 25 AS PER PLAN
Fire Protection And Fire Safety Requirements : 22 AS PER SANCTIONED PLAN
Electrical Meter Room, Sub-Station, Receiving Station : 25 METER PANEL SHALL BE PROVIDED
Water Supply : 52 BOREWELL / CORPORATION WATER
Sewerage (Chamber, Lines, Septic Tank , STP) : 42 AS PER SANCTIONED PLAN
Storm Water Drains : 35 AS PER PLAN

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 64.14 10 5
3BHK 83.75 10 4

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 20 AS PER PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 22 AS PER SANCTIONED PLAN
Water Supply : 25 BOREWELL / CORPORATION WATER
Electrical Meter Room, Sub-Station, Receiving Station : 10 METER PANEL SHALL BE PROVIDED

 

New documents listed below were uploaded to the Documents section:

  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 45
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
1 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 12
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 7
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.4

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Storm Water Drains : 12 AS PER PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : 15 AS PER SANCTIONED PLAN
Water Supply : 18 BOREWELL / CORPORATION WATER
Electrical Meter Room, Sub-Station, Receiving Station : 5 METER PANEL SHALL BE PROVIDED

 

New documents listed below were uploaded to the Documents section:

  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [10]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details [2]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [7]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [7]
  • Proforma of Allotment letter [2]