RERA ID: P53000048751
Project Name: 16 INDU VILLAS
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Kasaba Bawada, Powar Park, , Karvir, Kolhapur-416006

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Plot No. 39 and 40 out of R.S. No. 542

Boundaries:
Plot No 34 to 38 of R S No 542
R S No 543 and R S No 550N 9 Mtr Wide Road
WE
S
Open Space of R S No 542

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1524 sq.mt.
Sanctioned Built-up Area: 1660 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 16
No. of Floors sanctioned: 32
No. of Plinths: 16
No. of Open Parking: 31
No. of Closed Parking: 32

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Bungalow 912 to 1025 sq ft 16 2
Project Developer:
Shahaji Gopalrao Powar c/o Gopalrao Bapu Powar
Organization Type: Individual

Address: Plot No 42, R S No 542, Powar Park, Kasaba Bawada, Near Anand Swarup Park, , Karvir, Kolhapur-416006

Office Phone: +91 98237 27475


Other Professionals involved:
Professional Name Professional Type
SSK & SHRISHTI ASSOCIATES Architect
Mr Mahesh Vishnu Patole Engineer
Nitish Vandure Patil & Associates Chartered Accountant
Tanaji Pingale Other Professional


Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing 16 INDU VILLAS: Your Dream Home Awaits in Kasaba Bawada

Nestled in the serene locality of Kasaba Bawada, Kolhapur, Maharashtra, 16 INDU VILLAS (RERA ID: P53000048751) offers an exclusive opportunity to own your dream home. This new residential project, developed by a reputable builder, promises a tranquil and luxurious lifestyle amidst lush greenery.

A Haven of Comfort and Luxury:

16 INDU VILLAS comprises 16 meticulously designed bungalows, each offering spacious living spaces ranging from 912 to 1025 square feet. The project is strategically located on Plot No. 39 and 40 of R.S. No. 542, boasting a picturesque view and easy access to key amenities.

Designed for Your Comfort:

The project offers a harmonious blend of modern architecture and functional design, ensuring a comfortable and convenient living experience. Amenities include:

  • Spacious Bungalows: Indulge in spacious living areas designed to cater to your every need.
  • Ample Parking: Enjoy the convenience of 31 open parking spaces and 32 closed parking spaces, ensuring ample space for your vehicles.
  • Tranquil Surroundings: Experience the serenity of open spaces and lush greenery, providing a relaxing and peaceful atmosphere.

Location Advantage:

Situated in Kasaba Bawada, 16 INDU VILLAS offers the perfect blend of tranquility and accessibility. Its proximity to essential amenities, including schools, hospitals, and shopping centers, ensures a convenient and fulfilling lifestyle.

A Promising Investment:

16 INDU VILLAS presents an excellent investment opportunity, with its strategic location and well-planned amenities. The project is expected to be completed by December 31st, 2027, ensuring a timely handover of your dream home.

Contact Us Today:

To learn more about 16 INDU VILLAS and secure your dream home in this prestigious project, contact us today. We are confident that this project will exceed your expectations and offer you the perfect blend of comfort, luxury, and convenience.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Bungalow 84.76 1 0
Bungalow 86.33 1 0
Bungalow 87.6 1 0
Bungalow 88.67 5 0
Bungalow 89.26 5 1
Bungalow 89.31 1 1
Bungalow 94.36 1 0
Bungalow 95.26 1 0

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 32 0 30

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
1 Overall Percentage of Completion of the work done For the entire Building /Wing 67
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
2 Overall Percentage of Completion of the work done For the entire Building /Wing 67
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
3 Overall Percentage of Completion of the work done For the entire Building /Wing 67
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
4 Overall Percentage of Completion of the work done For the entire Building /Wing 67
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
5 Overall Percentage of Completion of the work done For the entire Building /Wing 67
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
6 Overall Percentage of Completion of the work done For the entire Building /Wing 67
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
7 Overall Percentage of Completion of the work done For the entire Building /Wing 67
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 80
8 Overall Percentage of Completion of the work done For the entire Building /Wing 67
9 X number of Slabs of Super Structure 100
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
9 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
9 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
10 X number of Slabs of Super Structure 100
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
10 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
10 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
11 X number of Slabs of Super Structure 100
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
11 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
11 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
12 X number of Slabs of Super Structure 100
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
12 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
12 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
12 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
13 X number of Slabs of Super Structure 100
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
13 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
13 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
13 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
13 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
14 X number of Slabs of Super Structure 100
14 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
14 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
14 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
14 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
14 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
14 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
15 X number of Slabs of Super Structure 100
15 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
15 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
15 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
15 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
15 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
15 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5
16 X number of Slabs of Super Structure 100
16 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
16 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
16 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
16 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 45
16 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
16 Overall Percentage of Completion of the work done For the entire Building /Wing 52.5

 

New documents listed below were uploaded to the Documents section:

  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Disclosure of sold/ booked inventory

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Bungalow 89.31 1 1

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
1 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
1 Overall Percentage of Completion of the work done For the entire Building /Wing 59
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
2 Overall Percentage of Completion of the work done For the entire Building /Wing 59
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
3 Overall Percentage of Completion of the work done For the entire Building /Wing 59
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
4 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
4 Overall Percentage of Completion of the work done For the entire Building /Wing 59
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
5 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
5 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
5 Overall Percentage of Completion of the work done For the entire Building /Wing 59
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
6 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
6 Overall Percentage of Completion of the work done For the entire Building /Wing 59
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
7 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
7 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
7 Overall Percentage of Completion of the work done For the entire Building /Wing 59
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
8 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
8 Overall Percentage of Completion of the work done For the entire Building /Wing 59
9 X number of Slabs of Super Structure 45
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
10 X number of Slabs of Super Structure 45
10 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
10 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
10 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
10 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
11 X number of Slabs of Super Structure 45
11 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
11 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
11 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
12 X number of Slabs of Super Structure 45
12 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
12 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
12 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
12 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
13 X number of Slabs of Super Structure 45
13 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
13 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
13 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
13 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
14 X number of Slabs of Super Structure 45
14 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
14 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
14 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
14 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
15 X number of Slabs of Super Structure 45
15 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
15 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
15 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
15 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
16 X number of Slabs of Super Structure 45
16 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
16 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
16 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
16 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5

 

New documents listed below were uploaded to the Documents section:

  • 7 Disclosure of sold/ booked inventory
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 Completed

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Bungalow 89.26 5 1

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [7]
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Disclosure of sold/ booked inventory [6]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [7]
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance [2]
  • b Details of encumbrances concerned to Legal [2]