RERA ID: P53000029051
Project Name: Royal Dreamland
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-03-31
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Phulewadi, A Ward, Kolhapur (M Corp.), Karvir, Kolhapur-416012

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
R.S.No.1486/C/4/A Pai

Boundaries:
R S No 1485-5 and R S No 1486K-4B
R S No 119AN 30 Meter DP Road
WE
S
R S No 1486C-4-A-2

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3926 sq.mt.
Sanctioned Built-up Area: 8865 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 16
No. of basements: 1
No. of Plinths: 2
No. of Closed Parking: 113

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 414 to 416 sq ft 48 36
2BHK 614 to 653 sq ft 79 44
3BHK 859 to 869 sq ft 17 13
Office 250 to 446 sq ft 3 3
Shop 114 to 332 sq ft 5 5
Project Developer:
SURAJ ESTATE DEVELOPERS
Organization Type: Partnership

Address: O/12, Royal Courts, Railway Station Road, Near Panch Bungalow, Shahupuri, Kolhapur (M Corp.), Karvir, Kolhapur-416001

Office Phone: +91 23125 31089


Member details:
Member Name Designation
Chetan Hasmukhbhai Vasa Partner
Sunit Chinubhai Parikh Partner
Anand Shankarrao Mane Partner
Rajiv Chinubhai Parikh Authorized Signatory
Divyaraj Hasmukhbhai Vasa Partner


Other Professionals involved:
Professional Name Professional Type
Gap Associates Architect
Gaurav Phadnis & Co Chartered Accountant
Mr Nikhil Rambhia Engineer


Projects in the state by this developer:
P53000048148 - ROYAL PLANET - Kolhapur
P53000046495 - ROYAL 09 TOURIST BUSINESS HUB - Kolhapur
P53000029051 - Royal Dreamland - Kolhapur
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Royal Dreamland: A New Residential Development in the Heart of Kolhapur

Royal Dreamland, a new real estate project by Suraj Estate Developers, promises to be a landmark development in Kolhapur, Maharashtra. Registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA) under ID P53000029051, this project is set to offer a unique blend of modern living and prime location.

Situated in the thriving locality of Phulewadi, the project is strategically located in A Ward, Kolhapur, with easy access to major thoroughfares. The project is bordered by a 30-meter wide DP road to the east and strategically placed in close proximity to other key landmarks, ensuring convenient access to essential amenities and services.

Royal Dreamland spans across a sprawling 3926 square meters of land, meticulously planned to accommodate two residential buildings. The project boasts a sanctioned FSI of 8865, allowing for a total built-up area of 9293 square meters. With a permissible total FSI of 18158, the project has the potential for further development in the future.

The development plans for Royal Dreamland include a thoughtfully designed layout with modern amenities, aiming to provide residents with a comfortable and convenient living experience. The project features a basement level for parking, two plinth levels, and a total of 16 sanctioned floors, offering a range of housing options to cater to diverse needs. The project also boasts 113 closed parking spaces, ensuring ample space for vehicle accommodation.

Suraj Estate Developers, a well-established partnership firm, has a proven track record in the real estate industry. With their commitment to quality construction and customer satisfaction, Royal Dreamland promises to be a prestigious addition to the Kolhapur cityscape.

While the project is still in its initial stages, the projected completion date is set for March 31, 2026. This timeline reflects the developers’ dedication to delivering a well-constructed and meticulously planned development on time.

Royal Dreamland presents an exciting opportunity for those seeking modern, comfortable, and well-connected living spaces in Kolhapur. With its strategic location, thoughtful amenities, and reputable developer, this project is poised to become a prominent address in the city, offering a unique blend of convenience, luxury, and community living.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 38.48 16 15
1BHK 38.66 32 21
2BHK 57.06 31 9
2BHK 59.2 32 21
2BHK 60.69 16 14
3BHK 79.83 7 3
3BHK 80.76 10 10
Office space 23.23 1 1
Office space 31.97 1 1
Office space 41.45 1 1
Shop 10.62 1 1
Shop 19.05 2 2
Shop 22.02 1 1
Shop 30.86 1 1

 

New documents listed below were uploaded to the Documents section:

  • 1 Architect’s Certificate on Completion of Project (Form 4)
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)
  • 1 Status of Conveyance
  • 5 Status of Formation of Legal Entity (Society/Co Op etc.)
  • 4 Status of Formation of Legal Entity (Society/Co Op etc.)
  • 3 Status of Formation of Legal Entity (Society/Co Op etc.)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 X number of Basement(s) and Plinth 100
2 X number of Podiums 100
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
2 Overall Percentage of Completion of the work done For the entire Building /Wing 100

 

New documents listed below were uploaded to the Documents section:

  • 2 Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 113 0 100

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Water Conservation, Rain water Harvesting : 100 Completed
Internal Roads & Footpaths : 100 Completed
Energy management : 100 Completed
Solid Waste Management And Disposal : 100 Completed
Treatment And Disposal Of Sewage And Sullage Water : 100 Completed
Landscaping & Tree Planting : 100 Completed
Storm Water Drains : 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : 100 Completed
Water Supply : 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : 100 Completed
Community Buildings : 100 Completed
Fire Protection And Fire Safety Requirements : 100 Completed

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 9 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Progress updated under Ameneties section

Name Proposed Booked WorkDone(In %)
Covered Parking ( In Numbers) 113 0 90

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Fire Protection And Fire Safety Requirements : 95 work started
Energy management : 20 work started
Water Conservation, Rain water Harvesting : 95 work started
Internal Roads & Footpaths : 95 work started
Water Supply : 95 work started
Sewerage (Chamber, Lines, Septic Tank , STP) : 95 work started
Landscaping & Tree Planting : 20 work not yet started
Community Buildings : 50 work started
Treatment And Disposal Of Sewage And Sullage Water : 85 work started
Storm Water Drains : 95 work started
Electrical Meter Room, Sub-Station, Receiving Station : 95 work started

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 38.48 16 15
1BHK 38.66 32 21
2BHK 57.06 31 9
2BHK 59.2 32 21
3BHK 80.76 10 10

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 X number of Basement(s) and Plinth 100
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
1 Overall Percentage of Completion of the work done For the entire Building /Wing 90
2 X number of Basement(s) and Plinth 95
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
2 Overall Percentage of Completion of the work done For the entire Building /Wing 93

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) [2]
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [10]
  • Building Plan Approval / NA Order for plotted development [8]
  • Commencement Certificates / NA Order for plotted development [2]
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration in FORM B
  • Details of encumbrances
  • Disclosure of sold/ booked inventory [8]
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [8]
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Other
  • Proforma of Allotment letter [2]
  • Status of Formation of Legal Entity (Society/Co Op etc.)