MH
Kolhapur
P53000028661
RERA ID: P53000028661
Project Name: HIRASHREE LAKE CITY APARTMENT PHASE III
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-06-30
Proposed Date of Completion
 
The Occupancy Certificate (OC) is seen uploaded to the Documents section on the MahaRERA portal. Please check and confirm its validity and whether it is for full or partial occupancy.
Project Address:
Rankala Lake, A Ward Ambai Tank, Kolhapur (M Corp.), Karvir, Kolhapur-416012

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
R.S.No.1110A 1A

Boundaries:
Remaining Property of RSNo 1110A 1A
9 meter internal wide roadN 18 Meter Wide Road
WE
S
6 meter wide side margin

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 3017 sq.mt.
Sanctioned Built-up Area: 10843 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 2
No. of Floors sanctioned: 12
No. of basements: 1
No. of Plinths: 2
No. of Closed Parking: 55

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
Bungalow 1477 sq ft 8 3
Others 528 to 1333 sq ft 77 75
Shop 201 to 302 sq ft 12 7
Project Developer:
Krishnat Shripatrao Patil c/o Shripatrao Tukaram Patil
Organization Type: Individual

Address: C S No 250 B/1A/12 Plot No 2A, Dc Plaza, Nagala Park, Kolhapur (M Corp.), Karvir, Kolhapur-416003

Office Phone: +91 23126 67885


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Mr Sarjerao Shripatrao Patil Individual Area Share
Mr Balasaheb Shripatrao Patil Individual Revenue Share
Mr Babasaheb Shripatrao Patil Individual Revenue Share
Mr Sanjay Shivaji Patil Individual Revenue Share
Mr Vijay Shivaji Patil Individual Revenue Share


Other Professionals involved:
Professional Name Professional Type
Sambhaji Patil Architect
Nishant Powar Engineer
V V Topkar and associates Chartered Accountant
Jaydeep Ganpat Patil Contractor
ADV SHIVPRASAD VANDURE PATIL AND ASSOCIATES Other Professional


Projects in the state by this developer:
P53000053944 - HIRASHREE LAKE CITY APARTMENT PHASE IV - Kolhapur
P53000028661 - HIRASHREE LAKE CITY APARTMENT PHASE III - Kolhapur
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Hirashree Lake City Apartment Phase III: Your Gateway to Tranquility in Kolhapur

Nestled amidst the scenic beauty of Kolhapur, Hirashree Lake City Apartment Phase III promises an exceptional living experience, seamlessly blending modern amenities with the serenity of its surroundings. This new project, registered with MahaRERA (P53000028661), offers a unique opportunity to own your dream home in a prime location, just steps away from the iconic Rankala lake.

A Project Built on Trust and Transparency

Hirashree Lake City Apartment Phase III is developed by a reputable firm, adhering to all regulatory requirements and ethical practices. The project boasts a clear title with no outstanding litigations, ensuring a smooth and hassle-free ownership experience.

A Harmonious Blend of Nature and Modernity

Spanning across a generous 3017 sq. meters, the project comprises two meticulously designed buildings, offering a diverse range of units to cater to every lifestyle. From spacious 2BHK and 3BHK apartments to luxurious bungalows and convenient shops, Hirashree Lake City Apartment Phase III provides an ideal living solution for individuals, families, and investors alike.

Enjoy a Lifestyle Enriched by Amenities

The project features a host of modern amenities designed to enhance your daily life. With a dedicated basement level, a two-level plinth, and 12 sanctioned floors, the project offers ample space for comfortable living. Additionally, the project provides 55 closed parking spaces, ensuring the safety and convenience of your vehicles.

A Prime Location for a Tranquil Life

Hirashree Lake City Apartment Phase III is strategically located in the A ward Ambai Tank area of Kolhapur, offering close proximity to the serene Rankala lake. Imagine waking up to the refreshing view of the lake, enjoying peaceful walks by its serene waters, and relishing the tranquility of your surroundings. The project’s location also provides easy access to all essential amenities, including schools, hospitals, shopping malls, and transportation hubs.

Your Investment in a Brighter Future

Hirashree Lake City Apartment Phase III offers more than just a home; it presents an opportunity to invest in a secure and promising future. The project’s prime location, carefully planned amenities, and a renowned developer ensure a high return on investment, making it an attractive choice for both end-users and investors.

Embrace the Promise of a Serene Life

Hirashree Lake City Apartment Phase III invites you to experience the perfect harmony of modern living and natural beauty. With its spacious and thoughtfully designed units, luxurious amenities, and prime location, the project offers a unique opportunity to create your dream home in a serene and peaceful environment. Contact us today to learn more and embark on your journey to a life filled with tranquility and joy.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1001 66.03 1 1
1002 69.22 1 1
1004 67.83 1 1
1005 67.83 1 1
1007 69.22 1 1
1008 66.03 1 1
101 66.56 1 1
102 69.31 1 1
103 69.93 1 1
104 69.31 1 0
105 69.31 1 0
106 69.93 1 1
107 69.31 1 1
108 66.56 1 1
201 66.03 1 1
202 69.22 1 1
203 68.73 1 1
204 67.83 1 1
205 67.83 1 1
206 68.73 1 1
207 69.22 1 1
208 66.03 1 1
301 66.56 1 1
302 69.32 1 1
303 68.91 1 1
304 67.9 1 1
305 67.9 1 1
306 68.91 1 1
307 69.32 1 1
308 66.56 1 1
401 66.03 1 1
402 69.22 1 1
403 68.73 1 1
404 67.83 1 1
405 67.83 1 1
406 68.73 1 1
407 69.22 1 1
408 66.03 1 1
501 49.13 1 1
502 89.03 1 1
503 68.91 1 1
504 67.9 1 1
505 67.9 1 1
506 68.91 1 1
507 89.03 1 1
508 49.13 1 1
601 66.03 1 1
602 69.22 1 1
603 68.73 1 1
604 67.83 1 1
605 67.83 1 1
606 68.73 1 1
607 69.22 1 1
608 66.03 1 1
701 49.13 1 1
702 89.03 1 1
703 68.91 1 1
704 67.9 1 1
705 67.9 1 1
706 68.91 1 1
707 89.03 1 1
801 66.03 1 1
802 69.22 1 1
803 68.73 1 1
804 67.83 1 1
805 67.83 1 1
806 68.73 1 1
807 69.22 1 1
808 66.03 1 1
901 66.5 1 1
902 69.32 1 1
903 123.3 1 1
904 67.9 1 1
905 67.9 1 1
906 123.9 1 1
907 69.32 1 1
908 66.56 1 1
Bungalow 137.22 8 3
Shop 01 23.22 1 1
Shop 02 19.76 1 0
Shop 03 28.14 1 0
Shop 04 19.01 1 1
Shop 05 18.68 1 1
Shop 06 22.84 1 0
Shop 07 22.84 1 1
Shop 08 18.68 1 1
Shop 09 18.86 1 1
Shop 10 28.14 1 1
Shop 11 19.76 1 0
Shop 12 23.22 1 0

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 100
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
2 Overall Percentage of Completion of the work done For the entire Building /Wing 76

 

New documents listed below were uploaded to the Documents section:

  • 12 Disclosure of sold/ booked inventory
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1001 66.03 1 1
1002 69.22 1 1
1004 67.83 1 1
1005 67.83 1 1
1007 69.22 1 1
1008 66.03 1 1
101 66.56 1 1
102 69.31 1 1
103 69.93 1 1
104 69.31 1 0
105 69.31 1 0
106 69.93 1 1
107 69.31 1 1
108 66.56 1 1
201 66.03 1 1
202 69.22 1 1
203 68.73 1 1
204 67.83 1 1
205 67.83 1 1
206 68.73 1 1
207 69.22 1 1
208 66.03 1 1
301 66.56 1 1
302 69.32 1 1
303 68.91 1 1
304 67.9 1 1
305 67.9 1 1
306 68.91 1 1
307 69.32 1 1
308 66.56 1 1
401 66.03 1 1
402 69.22 1 1
403 68.73 1 1
404 67.83 1 1
405 67.83 1 1
406 68.73 1 1
407 69.22 1 1
408 66.03 1 1
501 49.13 1 1
502 89.03 1 1
503 68.91 1 1
504 67.9 1 1
505 67.9 1 1
506 68.91 1 1
507 89.03 1 1
508 49.13 1 1
601 66.03 1 1
602 69.22 1 1
603 68.73 1 1
604 67.83 1 1
605 67.83 1 1
606 68.73 1 1
607 69.22 1 1
608 66.03 1 1
701 49.13 1 1
702 89.03 1 1
703 68.91 1 1
704 67.9 1 1
705 67.9 1 1
706 68.91 1 1
707 89.03 1 1
801 66.03 1 1
802 69.22 1 1
803 68.73 1 1
804 67.83 1 1
805 67.83 1 1
806 68.73 1 1
807 69.22 1 1
808 66.03 1 1
901 66.5 1 1
902 69.32 1 1
903 123.3 1 1
904 67.9 1 1
905 67.9 1 1
906 123.9 1 1
907 69.32 1 1
908 66.56 1 1
Shop 01 23.22 1 1
Shop 02 19.76 1 0
Shop 03 28.14 1 0
Shop 04 19.01 1 1
Shop 05 18.68 1 1
Shop 06 22.84 1 0
Shop 07 22.84 1 1
Shop 08 18.68 1 1
Shop 09 18.86 1 1
Shop 10 28.14 1 1
Shop 11 19.76 1 0
Shop 12 23.22 1 0

 

New documents listed below were uploaded to the Documents section:

  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)

 

New documents listed below were uploaded to the Documents section:

  • 11 Disclosure of sold/ booked inventory
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
2 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
2 Overall Percentage of Completion of the work done For the entire Building /Wing 69.5

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [12]
  • Building Plan Approval / NA Order for plotted development [10]
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout) [2]
  • Copy of the legal title report [2]
  • Declaration in FORM B
  • Details of encumbrances [2]
  • Disclosure of sold/ booked inventory [10]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) [3]
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [10]
  • Occupancy Certificate/ Completion Certificate/ Architect’s certificate of completion for plotted development
  • Other
  • Proforma of Allotment letter [2]