MH
Hingoli
P51200027577
RERA ID: P51200027577
Project Name: Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2025-03-10
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Hingoli, Sengoan Narsi Road-431513

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
146 A

Boundaries:
S NO 146
S NO 146 and Bharat gas godownN 12 Mtr Road
WE
S
12 mtr Road

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 8000 sq.mt.
Sanctioned Built-up Area: 7458 sq.mt.
Recreational Open Space: 7777 sq.mt.
No. of Buildings sanctioned: 9
No. of Floors sanctioned: 27
No. of Plinths: 9
No. of Open Parking: 9

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 7623 to 11435 sq ft 132 0
2BHK 5475 sq ft 48 0
Project Developer:
AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
Organization Type: Public Authority

Address: Mhada Aurangabad, Griha Nirman Bhavan, Cbs Road, Near Mahaveer Stambh, Baba Petrol Pump, Aurangabad (M Corp.), Aurangabad-431001

Office Phone: +91 24023 34035
Website URL: mhada.maharashtra.gov.in


Member details:
Member Name Designation
NITIN LAXMAN SHINDE Authorized Signatory
NITIN LAXMAN SHINDE Authorized Signatory


Other Professionals involved:
Professional Name Professional Type
PRAGATI CONSTRUCTION Contractor
DATTATRAYA PARSHURAM Architect
SUDHAKAR BAHEGAVANKAR Engineer
VAIJANATH PHAD Chartered Accountant


Projects in the state by this developer:
P51500054769 - Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, Aurang - Aurangabad
P52300049313 - Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, Beed - beed
P51500034364 - CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD - Aurangabad
P51200027577 - Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli - Hingoli
P51500026531 - CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABAD - Aurangabad
P52400017486 - 736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATUR - Latur
P51500013212 - CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD - Aurangabad
P51400012018 - 364 EWS T/S UNDER PMAY AT JALNA DIS JALNA - Jalna
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

A New Affordable Housing Project in Hingoli: MHADA’s Commitment to Inclusive Development

The Aurangabad Housing and Area Development Board (MHADA), a leading public authority in Maharashtra, is embarking on a new residential project in Hingoli district, aimed at providing affordable housing options for the local community. The project, registered under RERA ID P51200027577, is currently under construction and is slated for completion by March 10th, 2025.

This project, titled “Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli,” focuses on constructing 132 Economically Weaker Section (EWS) and 48 Low Income Group (LIG) housing units, aligning with the Prime Minister’s Awas Yojana (PMAY) scheme. This initiative reflects MHADA’s commitment to inclusive development, providing access to quality housing for diverse income segments.

Located in Hingoli, the project is situated on a plot spanning 8000 square meters, identified as Survey Number 146 A. The project encompasses 9 buildings, each designed with 27 sanctioned floors, totaling a sanctioned built-up area of 7458 square meters. Notably, the project includes a significant 7777 square meters dedicated to recreational open space, prioritizing the well-being and community living of its residents.

The project’s strategic location in Hingoli, conveniently accessible via Sengoan Narsi Road, ensures proximity to essential amenities and services. The project’s detailed layout, including the boundaries, plot area, and amenities, are meticulously defined in the project plan.

MHADA, as a reputable public authority, has established a transparent and accountable process for the project. Regular updates on the project’s progress are accessible through MHADA’s official website, mhada.maharashtra.gov.in. Potential residents can also reach out to the MHADA office in Aurangabad for any queries or inquiries.

This project represents a significant step towards addressing the housing needs of the Hingoli community. MHADA’s commitment to providing affordable and well-designed housing solutions ensures a positive impact on the quality of life for its residents, contributing to the overall development of the region.

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Excavation 100
1 X number of Basement(s) and Plinth 100
1 X number of Slabs of Super Structure 99
1 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
1 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
1 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
1 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
1 Overall Percentage of Completion of the work done For the entire Building /Wing 57.9
2 Excavation 100
2 X number of Basement(s) and Plinth 100
2 X number of Slabs of Super Structure 99
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
2 Overall Percentage of Completion of the work done For the entire Building /Wing 45.9
3 Excavation 100
3 X number of Basement(s) and Plinth 100
3 X number of Slabs of Super Structure 90
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
3 Overall Percentage of Completion of the work done For the entire Building /Wing 46
4 Excavation 100
4 X number of Basement(s) and Plinth 100
4 X number of Slabs of Super Structure 99
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
4 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 60
4 Overall Percentage of Completion of the work done For the entire Building /Wing 57.9
5 Excavation 100
5 X number of Basement(s) and Plinth 50
5 Overall Percentage of Completion of the work done For the entire Building /Wing 15
6 Excavation 100
6 X number of Basement(s) and Plinth 100
6 X number of Slabs of Super Structure 95
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 40
6 Overall Percentage of Completion of the work done For the entire Building /Wing 50.5
7 Excavation 100
7 X number of Basement(s) and Plinth 100
7 X number of Slabs of Super Structure 95
7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
7 Overall Percentage of Completion of the work done For the entire Building /Wing 41.5
8 Excavation 100
8 X number of Basement(s) and Plinth 100
8 X number of Slabs of Super Structure 70
8 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
8 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
8 Overall Percentage of Completion of the work done For the entire Building /Wing 32
9 Excavation 100
9 X number of Basement(s) and Plinth 100
9 X number of Slabs of Super Structure 85
9 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 15
9 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9 Overall Percentage of Completion of the work done For the entire Building /Wing 38

 

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)

 

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1BHK 708.24 96 0
1BHK 1062.36 36 0
2BHK 508.68 48 0

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Deviation Report with respect to Allotment letter
  • Deviation Report with respect to model copy of Agreement
  • Disclosure of Interest in Other Real Estate Organizations
  • Proforma of Agreement for sale
  • Proforma of Allotment letter
  • a Details of encumbrances concerned to Finance
  • b Details of encumbrances concerned to Legal