MH
Akola
P50100033083
RERA ID: P50100033083
Project Name: Lotus Green
Project Type: Residential
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2026-12-31
Proposed Date of Completion
 


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Geeta Nagar, Behind Tulshan Bunglows, Akola (M Corp.), Akola-444001

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
17/1/A

Boundaries:
Land of Mukinda
Land of Tulsiram KaleN Land of Rukhminibai B Kalore and Others
WE
S
Land of Daulat Kalore

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Project location map below based on coordinates provided by the developers to MahaRERA.
If this points to the wrong location, please notify the developers.



Key Details
Total Project Area: 5884 sq.mt.
Sanctioned Built-up Area: 19328 sq.mt.
Recreational Open Space: 624 sq.mt.
No. of Buildings sanctioned: 6
No. of Floors sanctioned: 44
No. of Plinths: 6
No. of Closed Parking: 507

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
1BHK 286 to 536 sq ft 299 31
1RK 240 to 260 sq ft 14 0
2BHK 408 to 551 sq ft 226 5
3BHK 716 sq ft 11 0
Shop 176 to 1087 sq ft 10 0
Project Developer:
Pankaj Rameshchandra Kothari c/o Rameshchandra G Kothari
Organization Type: Individual

Address: A,103 1St Floor, Rami Heritage, Kirti Nagar, Old Rto Office, Akola (M Corp.), Akola-444002

Office Phone: +91 94221 60398


Other Professionals involved:
Professional Name Professional Type
Ar. Kamlesh Kriplani Architect
Er. Dhyanesh Dahatonde Engineer
Pradeep R Agrawal Engineer
Agrawal Bajoria Padiya & Associates Chartered Accountant


Projects in the state by this developer:
P50100047492 - Lotus Park - Akola
P50100033083 - Lotus Green - Akola
Litigations

Litigations related to the project ? No
When this data gets the AI treatment, it churns out conclusions like the one below. But hey, a Real Intelligence like yourself, would go a step further by visiting the project site, meeting the people involved, carefully analyzing all the options, and then making an informed decision. Right? Happy hunting!

Introducing Lotus Green: A New Residential Haven in Akola

Nestled in the heart of Geeta Nagar, Akola, Lotus Green is a new residential project poised to redefine urban living. Developed under the RERA ID P50100033083, this project promises a harmonious blend of contemporary design, modern amenities, and a strategic location, making it an attractive investment opportunity for discerning homebuyers.

A Project Rooted in Quality and Sustainability:

Lotus Green is designed with meticulous attention to detail, ensuring a comfortable and fulfilling lifestyle. The project spans 5884 square meters, encompassing six meticulously planned buildings, each reaching a height of four floors. The project prioritizes open spaces, dedicating 624 square meters to recreational areas, creating a serene environment conducive to relaxation and community building.

Variety of Living Spaces to Suit Every Need:

Lotus Green caters to a diverse range of preferences, offering a wide selection of unit types:

  • 1BHK (286 to 536 sq ft) - 299 Nos: Ideal for individuals and small families seeking modern and efficient living.
  • 1RK (240 to 260 sq ft) - 14 Nos: Compact and stylish studios perfect for singles or young professionals.
  • 2BHK (408 to 551 sq ft) - 226 Nos: Spacious and well-designed apartments suitable for growing families.
  • 3BHK (716 sq ft) - 11 Nos: Luxurious and expansive units offering ample space and comfort.
  • Shop (176 to 1087 sq ft) - 10 Nos: Commercial units ideal for entrepreneurs and businesses looking to establish a presence in this thriving location.

Location Advantage:

Strategically located in Geeta Nagar, behind Tulshan Bunglows, Lotus Green benefits from excellent connectivity to essential amenities. Residents will have easy access to schools, hospitals, shopping centers, and other social infrastructure, ensuring a convenient and fulfilling lifestyle.

Commitment to Transparency and Reliability:

Lotus Green is developed under the stringent regulations of MahaRERA, ensuring transparency and accountability throughout the project lifecycle. The project is also supported by The Akola Janata Commercial Co-operative Bank Ltd, signifying a strong financial foundation.

A Promise of a Brighter Future:

With its well-planned design, diverse unit options, and strategic location, Lotus Green offers a unique opportunity to invest in a vibrant and thriving community. The project is expected to be completed by December 31st, 2026, promising a timely and efficient delivery.

For individuals seeking a modern, comfortable, and strategically located home in Akola, Lotus Green presents a compelling choice. It is an investment in a brighter future, a haven of peace and tranquility, and a testament to quality and excellence in urban living.

Units booking and availability updated under Buildings section

Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
2BHK 39.88 165 5

 

There are additions/modifications under Professionals section

Professional Name Professional Type
Pradeep R Agrawal Engineer

 

Progress updated under Buildings section

Bldg No. Tasks / Activity Percentage of Work
1 Stilt Floor 100
1 X number of Slabs of Super Structure 15
1 Overall Percentage of Completion of the work done For the entire Building /Wing 31.5
2 Stilt Floor 100
2 X number of Slabs of Super Structure 40
2 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
2 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
2 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 28
2 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 15
2 Overall Percentage of Completion of the work done For the entire Building /Wing 43.3
3 Stilt Floor 100
3 X number of Slabs of Super Structure 100
3 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
3 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
3 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
3 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 90
3 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
3 Overall Percentage of Completion of the work done For the entire Building /Wing 78
4 Stilt Floor 100
4 X number of Slabs of Super Structure 50
4 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
4 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
4 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
4 Overall Percentage of Completion of the work done For the entire Building /Wing 42.5
5 Stilt Floor 100
5 X number of Slabs of Super Structure 15
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
5 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
5 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
5 Overall Percentage of Completion of the work done For the entire Building /Wing 34
6 Stilt Floor 100
6 X number of Slabs of Super Structure 45
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
6 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
6 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 30
6 Overall Percentage of Completion of the work done For the entire Building /Wing 44

 

Progress updated under Ameneties section

Common areas And Facilities, Amenities Percent Details
Street Lighting : 0 Street Lighting
Fire Protection And Fire Safety Requirements : 0 Fire Extinguisher
Water Conservation, Rain water Harvesting : 0 Rain Water Harvesting
Internal Roads & Footpaths : 10 Footpaths
Sewerage (Chamber, Lines, Septic Tank , STP) : 15 Septic tank
Water Supply : 15 Tap Water
Open Parking : 0 Open Parking
Aggregate area of recreational Open Space : 0 Garden and Temple

 

New documents listed below were uploaded to the Documents section:

  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • Building Plan Approval / NA Order for plotted development
  • CERSAI details
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [5]
  • Declaration about Commencement Certificate
  • Declaration in FORM B
  • Details of encumbrances
  • Proforma of Allotment letter