RERA ID: P50100031464
Project Name: Rajgruha
Project Type: Others
Project Status: New Project *
* Projects that started May 2017 onwards, after RERA was implemented.
2027-12-31
Extended Date of Completion
The project missed completion date 1 time(s) earlier (2024-06-30).


While Developers may verbally quote early handover dates, please note that RERA authorities would only consider the official completion dates when hearing any complaints.
Project Address:
Aadarsh Colony, Ghod Dod Road, Akola (M Corp.), Akola-444004

Plot Bearing No / CTS no / Survey Number/Final Plot no.:
Sheet No 71 , Survey No. 9/5/2, 9/5/3 amd 9/5/4

Boundaries:
Plot belonging to Madhukar Chandwadkar
Service LaneN 100 Ft Ghod Daud Road
WE
S
Uttarsingh Nandansingh Andereli Plot

The location of a project plays a very important role in its market value. The developers should invariably maintain correct location in RERA records. Potential customers should always verify the correctness of the location record.

Location coordinates were not provided to MahaRERA by the developers. Below is an approximate location, and may contain error.



Key Details
Total Project Area: 1799 sq.mt.
Sanctioned Built-up Area: 2327 sq.mt.
Recreational Open Space: 0 sq.mt.
No. of Buildings sanctioned: 1
No. of Floors sanctioned: 5
No. of Plinths: 1
No. of Stilts: 1
No. of Closed Parking: 23

Units on Offer and Availability
Category Carpet Area No of Units Units already Booked / Sold
2BHK 647 to 785 sq ft 36 0
Shop 145 to 176 sq ft 11 0
Project Developer:
SUGAT WAGHMARE c/o GYANESHWAR WAGHMARE
Organization Type: Individual

Address: Sugat Bhavan, Ranpise Nagar, Near Bara Jotirlinga Mandir, Bara Jotirlinga Mandir, Akola (M Corp.), Akola-444001

Office Phone: +91 74224 55133


Co-Promotors:
Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement
Sugat Waghmare Others Area Share
Rajgruha Magasvargiya Gruha Colony Societies Area Share


Other Professionals involved:
Professional Name Professional Type
Ankeet Agarwal Architect
Shyamsunder Sadhwani Engineer
Pratik Khambalkar Engineer
Harsh Kumat Chartered Accountant


Litigations

Litigations related to the project ? No

New documents listed below were uploaded to the Documents section:

  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
  • 2 a Details of encumbrances concerned to Finance
  • 1 Disclosure of Interest in Other Real Estate Organizations
  • 1 CERSAI details
  • 1 Disclosure of sold/ booked inventory
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
  • 3 Declaration in FORM B
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
  • 1 b Details of encumbrances concerned to Legal
  • 1 Other – Technical
  • 1 Deviation Report with respect to model copy of Agreement
  • 1 Deviation Report with respect to Allotment letter

 

There is a change in Project timelines and the completion date is moved ahead. The project is now scheduled to complete by 2027-12-31

 

Documents listed below were found uploaded on the first day this project was indexed. More documents, whenever uploaded, will be shared as posts on dates of upload.

  • Architect’s Certificate of Percentage of Completion of Work (Form 1) [2]
  • Building Plan Approval / NA Order for plotted development
  • Commencement Certificates / NA Order for plotted development
  • Copy of Layout Approval (in case of layout)
  • Copy of the legal title report [2]
  • Declaration about Commencement Certificate
  • Declaration in FORM B [2]
  • Details of encumbrances
  • Engineer’s Certificate on Cost Incurred on Project (Form 2) [2]
  • Other